Loading...
HomeMy WebLinkAbout4.2 - 1667 Project Acceptance and New CIP Page 1 of 3 STAFF REPORT CITY COUNCIL DATE: January 9, 2018 TO: Honorable Mayor and City Councilmembers FROM: Christopher L. Foss, City Manager SUBJECT: Project Acceptance for Dublin Sports Grounds and New Capital Improvement Project (CIP) Creation for a Master Plan and All-Abilities Playground Design Prepared by: Rosemary Alex, Parks and Facilities Devlopment Coordinator EXECUTIVE SUMMARY: On May 2, 2017, the City Council awarded a construction contract for the Dublin Sports Grounds Renovation (CIP No. PK0416). The work is now complete and ready for City Council acceptance and approval of a budget change. Additionally, the City Council will consider the authorization of a new CIP (PK0518) to complete the Dublin Sports Grounds Master Plan, which would include an all-abilities playground. STAFF RECOMMENDATION: Adopt the Resolution Accepting the Dublin Sports Grounds Renovation Project (CIP No. PK0416), approve the creation of the Dublin Sports Grounds Rehabilitation Project (CIP No. PK0518), and approve the budget change. FINANCIAL IMPACT: In order to close out the Dublin Sports Grounds Renovation project (CIP No. PK0416), a budget change in the amount of $10,000 is needed to cover additional Staff time and inspection services during the course of construction, as shown in the table below. Page 2 of 3 Project Funding Sources State of California Housing Grants 831,100.00$ General Fund 50,000.00$ Total Funding Sources 881,000.00$ Project Expenditures Non-Construction Costs: Miscellaneous (Filling Fees, Printing, Postage, Legal) $ 7,758.00 Staff Time $ 29,900.00 Maintenance Equipment (Groomer, Two Gators, Tractor) $ 114,137.00 Contract Services (Design, Geotech, Inspection) $ 179,959.00 Site Furniture and Structures $ 248,254.00 Original Construction Contract Amount $ 291,160.00 Change Order #1 $ 19,831.83 Total Project Costs 890,999.83$ Additional Budget Needed to Close Project 10,000.00$ In addition, Staff is seeking approval to create the Dublin Sports Grounds Rehabilitation Project (CIP No. PK0518), funded with an initial $300,000, to complete a master plan for the overall park. The General Fund Reserve for the Dublin Sports Ground has a balance of $2.5 million and can cover the total budget increase of $310,000 for the two actions requested in this report. DESCRIPTION: Project Acceptance On May 2, 2017, the City Council approved a construction contract with Suarez and Munoz Construction, Inc. for the Dublin Sports Grounds Renovation Project (CIP No. PK0416). The primary source of funding for the project was from the State of California Department of Housing and Community Development the Housing-Related Parks Program. The scope of work included improvements to baseball fields #4, #5 and #6, including the installation of six new dugout shade structures and benches, three new scorekeeper booths, trash and recycling receptacles and concrete accessible paving and drinking fountain for field #6. During construction, there were some corrective measures by the contractor in order to close out the Project resulting in additional Staff time. A budget change in the amount of $10,000 is requested to cover the additional Staff and inspection costs. The City presently holds a performance bond in the amount of $291,160 to provide the necessary security for the performance of the work involved. Since the work is now complete and ready for acceptance, the performance security requirement can be reduced in accordance with authority contained in Section 66499.7 of the Government Code, to an amount necessary to guarantee warranty of the work for a one -year period following acceptance of the work. The Contractor will provide a new maintenance bond Page 3 of 3 in the amount of $31,991 which is 10% of the final contract amount, and is sufficient to cover the one-year guarantee period. New Capital Improvement Project (PK0518) -Dublin Sports Grounds Rehabilitation With the grant-funded portion of the Project complete, Staff is seeking City Council authorization to form a new CIP. The proposed project will entail the completion of the master planning process that was initiated with the community input meeting in February 2016. The new project will continue the planning process and complete a master plan and report for the overall park. As part of the overall master plan, Staff will include the development of detailed plans and specifications to construct an all-abilities playground. The $300,000 will allow Staff to proceed with the master planning process and initiate design documents for the playground this Fiscal Year. As part of the budget process for next Fiscal Year, Staff will seek additional resources for the construction portion of the project. NOTICING REQUIREMENTS/PUBLIC OUTREACH: A copy of the Staff Report will be sent to Suarez and Munoz Construction, Inc. ATTACHMENTS: 1. Resolution Accepting the Dublin Sports Grounds Renovation Project 2. Budget Change Form ATTACHMENT #1 RESOLUTION NO. XX - 18 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN * * * * * * * * * * * ACCEPTING THE DUBLIN SPORTS GROUNDS RENOVATION PROJECT (CIP NO. PK0416) WHEREAS, on May 2, 2017 the City of Dublin entered into a contract with Suarez and Munoz Construction, Inc. to construct the Dublin Sports Renovation Project (CIP No. PK0416); and WHEREAS, the improvements have been completed in accordance with the plans and specifications, and any approved modifications thereof, to the satisfaction of the City Engineer of the City of Dublin; and WHEREAS, as a condition of the contract, Suarez and Munoz Construction Inc. is required to warranty the improvements for a period of one year following acceptance of the work by the City of Dublin and maintain a maintenance bond in the amount of 10% of the final contract value; and NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby accept the improvements, Dublin Sports Renovation Project (CIP No. PK0416), and authorize Staff to file a Notice of Completion with Alameda County. BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby authorize the City Manager or his designee to release the retention, if after 35 days of filing the Notice of Completion there are no subcontractor claims. PASSED, APPROVED AND ADOPTED this 9th day of January, 2018, by the following vote: AYES: NOES: ABSENT: ABSTAIN: ______________________________ Mayor ATTEST: _________________________________ City Clerk Budget Change Reference #: From Un-Appropriated ReservesXBudget Transfer Between Funds From Designated Reserves Other Account AmountAccountAmount pk0416.9100.9101 - Salaries & Benefits $5,900 pk0416.9200.9209 - Inspections $4,100 3500.9501.49999 (Transfers In)$10,000 pk0416.1001 (1001.9501.89101) - General Fund - Transfers Out $10,000 pk0518.9100.9101 - Salaries & Benefits $40,000 pk0518.9200.9202 - Design $100,000 pk0518.9200.9206 - Testing $10,000 pk0518.9500.9502 - Processing/Filling Fees $20,000 pk0518.9400.9401- Improvements - Not Bldg $130,000 3500.9501.49999 (Transfers In)$300,000 pk0518.1001 (1001.9501.89101) - General Fund - Transfers Out $300,000 1/9/2018 Posted By:Date: As Presented at the City Council Meeting **********Finance Use Only********** CITY OF DUBLIN (1) Dublin Sports Ground Renovation budget changes - to cover the additional staff and project inspection time to complete the construction of recent improvements at Dublin Sports Grounds REASON FOR BUDGET CHANGE FISCAL YEAR 2017-18 BUDGET CHANGE FORM DECREASE BUDGET AMOUNTINCREASE BUDGET AMOUNT City Council's Approval Required EXP: Dublin Sports Ground Renovation (1) EXP: Dublin Sports Ground Rehabilitation (2) (2) Dublin Sports Ground Rehabilitation budget changes - to allow Staff to complete the master plan and to initiate detailed plans and specifications for the All-Abilities Playground at Dublin Sports Grounds during this current fiscal year Attachment #2