HomeMy WebLinkAbout7.3 Park Project Updates
Page 1 of 3
STAFF REPORT
PARKS & COMMUNITY SERVICES COMMISSION
DATE: January 22, 2018
TO: Honorable Chair and Commissioners
FROM:
Troy Brown, Parks & Community Services Director
SUBJECT:
Park Project Updates
Prepared by: Michael Boitnott, CIP Manager
EXECUTIVE SUMMARY:
The Commissions will receive a report on the progress of current park projects.
STAFF RECOMMENDATION:
Receive the Report.
FINANCIAL IMPACT:
None.
DESCRIPTION:
The following is an update on the progress of current and a summary of recently
completed park projects:
The Wave - Emerald Glen Park Concession Building (CIP No. PK0105)
The project consists of the installation and construction of a concession building at The
Wave facility. The concession will primarily serve patrons of The Wave, but can also
serve park visitors through a secondary service window. City Council approved the
acquisition of a prefabricated concession building on November 21, 2017.
Status: Out to bid for site and utility improvements necessary to accommod ate
installation and commissioning of the prefabricated building.
Next Milestone: January 17, 2018 - Construction Bid Opening. Work is expected to
begin early March 2018.
The Wave - Emerald Glen Recreation and Aquatic Complex (CIP No. PK0105)
The project provides for the design and construction of The Wave aquatic complex at
Emerald Glen Park. The Wave opened for business on May 27, 2017.
Status: Project closeout
Next Milestone: Spring 2018 - City Council consideration of project acceptance.
7.3
Packet Pg. 11
Page 2 of 3
Dublin Crossing Community Park (CIP No. PK0115)
The City Council approved an amendment to the Dublin Crossing Development
Agreement that requires the developer, Dublin Crossing LLC, to design and construct
the 30-acre park as phases of residential development are completed.
Status: The developer has completed a concept plan and preliminary budget for the 30 -
acre park, which was approved by the City Council on January 9, 2018.
Next Milestone: The development of the plans and specification for construction of th e
park improvements.
Dublin Heritage Park Cemetery (CIP No. PK0215)
The project provides for the renovation of the existing Pioneer Cemetery, which may
include improved pathways, renovated plaza area near St. Raymond’s church and
renovated landscaping. On August 15, 2017, City Council directed staff to engage the
Heritage and Cultural Arts Commission to review the Dublin Historic Park Master Plan
and the future projects contained within the Master Plan.
Status: Preparing plans and specifications for the project.
Next Milestone: Summer 2018 - City Council and Heritage and Cultural Arts
Commission consideration of renovation plan.
Sean Diamond Park (CIP No. PK0216)
The project constructs a five-acre neighborhood park including a central gathering point
with lighted rose garden and public art, playgrounds for children ages 2 -to-5 and 5-to-
12-year olds, a tennis court, picnic area with shade structure, informal lawn area, grass
volleyball court, restroom building, pathways for circulation and exercise
Status: Construction is near substantial completion.
Next Milestone: Summer 2018 - City Council consideration of project acceptance.
Fallon Sports Park - Phase 2 (CIP No. PK0414)
The project provides for the second phase of improvements at the park which inc lude:
parking for 145 vehicles, two synthetic turf soccer fields with conduits stubbed for future
lighting, lighted 90-foot baseball diamond with scorekeepers’ booth and scoreboard,
restrooms and concession building, group picnic area for 100 people, hards cape and
landscaping, and Fallon and Central Parkway landscape and sidewalk
Status: Construction is substantially complete.
Next Milestone: Spring 2018 - City Council consideration of project acceptance.
Dublin Sports Ground Renovation (CIP No. PK0416)
This project included improvements to baseball fields #4, #5 and #6, including the
installation of six new dugout shade structures and benches, three new scorekeeper
booths, trash and recycling receptacles and concrete accessible paving and drinking
fountain for field #6.
7.3
Packet Pg. 12
Page 3 of 3
Status: Project is complete.
Jordan Ranch Neighborhood Park (CIP NO. PK0514)
This project provides for a Neighborhood Park which includes: shaded playground with
areas for tots ages two to five and youth ages five to 12, group picnic area with tables
and barbecues; open space meadow for informal sports, games and passive activities;
a basketball court; a volleyball court; trail access and a restroom.
Status: Project is near substantial completion.
Next Milestone: City Council accepted the park improvements on December 19, 2017
Clover Park and Sunrise Park - Dublin Ranch Subarea 3 (CIP No. PK0117)
The project provides for the design and construction of Sunrise Park, a 10.75 -acre
community nature park, and the adjacent Clover Park, a two -acre neighborhood square.
The Clover park design is being completed by the City and funded by the Developer of
Subarea 3. Sunrise Park is being designed and constructed by the Developer.
Status: Clover Park plans and specifications are complete and have been provided to
the Developer. Developer is finalizing plans and specifications for Sunrise Park.
Next Milestone: Developer to finalize plans and specifications and bid project for
construction - Spring 2018.
Moller Ranch Neighborhood Square (CIP No. PK0118)
The City Council approved a Park Improvement Agreement this year to allow the
Developer to design and construct the neighborhood square on a 1.07 -acre site within
the Moller Ranch/Tassajara Hills subdivision.
Status: Developer preparing concept design plans.
Next Milestone: Developer to provide concept plans for staff review.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
None.
ATTACHMENTS:
None.
7.3
Packet Pg. 13