STAFF REPORT
CITY COUNCIL
DATE: April 2, 2019
TO: Honorable Mayor and City Councilmembers
FROM:
Christopher L. Foss, City Manager
SUBJECT:
Increase Contract Change Order Authorization, for Public Safety Complex
– Police Services Building (Project No. GI0116) and Dublin Boulevard
Widening (Project No. ST1012)
Prepared by: Michael Boitnott, Capital Improvement Program Manager
EXECUTIVE SUMMARY:
The City Council will consider increasing the contract change order authority for the City
Manager in relation to two projects - the Public Safety Complex and the Dublin
Boulevard Widening Project.
For the Public Safety Complex, Sausal Corporation needs to make additional structural
upgrades necessary to bring the building up to “essential faci lity” status and related
improvements, as well as add project scope to replace the existing parking lot, and
install a 180 kVA solar voltaic system on top of the police vehicle carports. For the
Dublin Boulevard Widening Project, Granite Construction Company needs to repave
and install video detection at the intersection of Dublin Boulevard and Dougherty Road
and install street lighting along the Dublin Sports Grounds parking lot. Additionally,
emergency pavement repairs on Village Parkway by Granite were made at the City's
request and along with reimbursable improvements for Zayo Communications.
STAFF RECOMMENDATION:
Adopt the Resolution Authorizing the City Manager to Execute Contract Change
Orders with Sausal Corporation, for the Public Safety Complex - Police Services
Building, CIP No. GI0116; and, adopt the Resolution Authorizing the City Manager to
Execute Contract Change Orders with Granite Construction Company for the Dublin
Boulevard Widening Project, CIP No. ST1012.
FINANCIAL IMPACT:
Sufficient funds are available in the respective project budgets for the proposed
increases in the Contract Change Order authorization for the added project scope.
DESCRIPTION:
Page 2 of 4
Public Safety Complex
On February 6, 2018, the City Council awarded a construction contract to Sausal
Corporation, with a total not to exceed amount of $16,811,740 including a construction
contingency, Resolution 14-18 (Attachment 3) for the Public Safety Complex - Police
Services Building, CIP No. GI0116. At the same time, the City Cou ncil authorized the
City Manager, or his designee, to approve project contract change orders, based on
appropriated project funds, up to the contingency amount of $1,528,340.
The project provides for the demolition of three existing buildings, renovation and
reconstruction of two buildings, and associated site improvements to accommodate
current and future Dublin Police Services office space needs. The Public Safety
Complex also houses the Alameda County Fire Department Administrative Offices and
will also serve as the City’s Emergency Operation Center (EOC).
During construction, the City conducted an evaluation by a structural engineer to
evaluate the existing building and it was determined that several structural upgrades ,
which were believed to have been completed in 2013, to bring the building up to
“essential facility” status were not made. At this time the structural upgrades need to be
completed prior to occupancy by Dublin Police Services and opening the new EOC.
Staff has been working with the general contractor, Sausal Corporation to price and
implement a contract change order to complete the necessary “essential facility”
improvements and upgrades and to minimize delay in moving Dublin Police Services to
the Public Safety Complex at an estimated cost of $1,400,000. The necessary
improvements also require the Alameda County Fire Administrati ve Offices be vacated
in order to bring the building, which will be shared by Dublin Police Services, up to
“essential facility” status.
When the project was originally bid and awarded, Fire Administration was planned to
occupy their offices and their side of the site during construction. While Fire
Administration is out of the building, it is advantageous to reconstruct the portion of the
parking lot that is used by Fire Administration. The estimated cost of reconstructing the
Fire Administration parking lot is included in the estimated cost stated above of
$1,400,000.
With this proposed change order, Staff is also recommending adding the installation of a
180kVA solar photovoltaic system on top of the police vehicle carports to reduce future
power bills. The carport structures within the existing contract were designed to allow
for convenient installation of a solar photovoltaic system. The cost for add ing a solar
photovoltaic system to the carports and integrating it with the buildings electrical system
would increase the contract amount by an approximate cost of $600,000.
Staff is recommending that the City Council authorize the City Manager, or his
designee, to execute contract change orders for the additional project scope with
Sausal Corporation, at an additional cost of $2,000,000, which increases the total
project contingency to $3,528,340 and increases the not to exceed contract total to
$18,811,740.
Page 3 of 4
Dublin Boulevard Widening
On July 17, 2018, the City Council awarded a construction contract to Granite
Construction Company with a total not to exceed amount of $6,253,454 including a
construction contingency, Resolution 94-18 (Attachment 4) for the Dublin Boulevard
Widening Project, CIP No. ST1012. At the same time, the City Council authorized the
City Manager, or his designee, to approve project contract change orders, based on
appropriated project funds, up to the contingency amount of $575,000.
The project provides for the widening of Dublin Boulevard to six travel lanes between
Sierra Court/Civic Plaza and Dublin Court; the addition of bicycle lanes on both sides of
Dublin Boulevard; intersection improvements at both Sierra and Dublin Courts; new
sidewalk on both sides of the street including a pedestrian bridge over a drainage
channel east of Dublin Sports Grounds; landscape improvements, including the
replacement of the existing street trees plus additional street trees; and bus shelter
relocation.
Late last year, a segment of Village Parkway between Amador Valley Boulevard and the
City limits was approaching unsafe conditions because of ground subsidence. Staff
directed Granite Construction Company to proceed with emergency repairs while Dublin
Unified School District was on winter break to minimize impacts to the public. These
repairs cost approximately $235,000.
In addition to the Village Parkway pavement repairs, Staff is recommending a contract
change order to expand the project scope of the Dublin Boulevard Widening Project to
include pavement resurfacing and installation of video detection at the intersection of
Dublin Boulevard and Dougherty Road and installation of street lighting along the Dublin
Sports Grounds parking lot and achieve an economy of scale with a larger project.
These improvements have an estimated cost of approximately $265,000.
While the City’s Contractor was constructing the Dublin Boulevard improvements, there
were improvements being constructed concurrently by Zayo Communication to relocate
their utilities out of the way of the new road alignment. Zayo Communication was unable
to complete the necessary improvements without delaying the City’s contractor,
therefore Zayo Communication agreed to have the City’s Contractor construct the
improvements, to prevent the project from being delayed , and to reimburse the City for
the cost to complete the improvement. The cost of the Zayo Communication
improvements is approximately $25,000.
Staff is recommending that the City Council authorize the City Manager, or his
designee, to execute contract change orders for the additional project scope with
Granite Construction Company, at an additional cost of $525,000, which increases the
total project contingency to $1,100,000.00 and increases the not to exceed contract
total to $6,778,454.00.
STRATEGIC PLAN INITIATIVE:
N/A
Page 4 of 4
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
A copy of this staff report was sent to Sausal Corporation and Granite Construction
Company.
ATTACHMENTS:
1. Resolution Authorizing the City Manager to Execute Contract Change Orders with
Sausal Corporation, for Public Safety Complex - Police Services Building, CIP No.
GI0116
2. Resolution Authorizing the City Manager to Execute Contract Change Orders with
Granite Construction Company, for Dublin Boulevard Widening Project, CIP No.
ST1012
3. Resolution 14-18 Awarding a Contract to Sausal Corporation
4. Resolution 94-18 Awarding a Contract to Granite Construction Company
RESOLUTION NO. XX- 19
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
*********
AUTHORIZING THE CITY MANAGER TO APPROVE CONTRACT CHANGE
ORDERS WITH SAUSAL CORPORATION FOR PUBLIC SAFETY COMPLEX –
POLICE SERVICES BUILDING, CIP NO. GI0116.
WHEREAS, on February 6, 2018, the City of Dublin entered into a contract with
Sausal Corporation to construct the Public Safety Complex – Police Services Building,
CIP No. GI0116; and
WHEREAS, City Council of the City of Dublin authorized the City Manager or his
designee to approve Contract Change Orders based on the appropriated funds
designated for the Project up to the contingency amount of $1,528,340.00.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
Dublin does hereby incorporate additional improvements to be constructed by the
project, to include structural upgrades necessary to bring the building up to “essential
facility” status and related improvements, and replacement of the existing parking lot
adjacent to the Alameda County Fire Department side of the building at an estimated
cost of $1,400,000.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does
hereby incorporate additional improvements to be constructed by the project to include
the installation of 180 kVA solar voltaic system on top of vehicle carports located within
the police parking lot at an estimated $600,000.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does
hereby authorize the City Manager or his designee to execute Contract Change Orders
with Sausal Corporation up to the revised contingency amount of $3,528,340.00 and
increase the not to exceed contract total to $18,811,740.00 .
PASSED, APPROVED AND ADOPTED this 2nd day of April, 2019, by the
following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
________________________________
Mayor
ATTEST:
_______________________________________
City Clerk
RESOLUTION NO. XX- 19
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
*********
AUTHORIZING THE CITY MANAGER TO APPROVE CONTRACT CHANGE
ORDERS WITH GRANITE CONSTRUCTION COMPANY FOR DUBLIN BOULEVARD
WIDENING PROJECT, CIP NO. ST1012.
WHEREAS, on July 17, 2018, the City of Dublin entered into a contract with
Granite Construction Company to construct the Dublin Boulevard Widening Project, CIP
No. ST1012; and
WHEREAS, City Council of the City of Dublin authorized the City Manager or his
designee to approve Contract Change Orders based on the appropriated funds
designated for the Project up to the contingency amount of $575,000.00.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin
does hereby incorporate additional improvements to be constructed by the project, to
include repaving and installing video detection at the intersection of Dublin and
Dougherty, installation of street lighting along the Dublin Sports Grounds parking lot, and
emergency pavement repairs on Village Parkway at an estimated $500,000.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does
hereby incorporate additional improvements to be constructed by the project to include
improvements constructed by the City of Dublin within the Project limits for and to be
reimbursed by Zayo Communications at an estimated $25,000.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does
hereby authorize the City Manager or his designee to execute Contract Change Orders
with Granite Construction Company up to the revised contingency amount of
$1,100,000.00 and increase the not to exceed contract total to $6,778,454.
PASSED, APPROVED AND ADOPTED this 2nd day of April, 2019, by the
following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
________________________________
Mayor
ATTEST:
_______________________________________
City Clerk
RESOLUTION NO. 14 — 18
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
APPROVING THE PLANS AND SPECIFICATIONS, WAIVING MINOR BID IRREGULARITY,
AWARDING A CONTRACT TO SAUSAL CORPORATION, AND APPROVING AN AGREEMENT
WITH SWINERTON BUILDERS, DBA SWINERTON MANAGEMENT & CONSULTING FOR THE
PUBLIC SAFETY COMPLEX — POLICE SERVICES BUILDING, CIP NO. G10116.
WHEREAS, Staff completed plans and specifications for the Public Safety Complex — Police
Services Building, CIP No. G10116 ("Project"). The Project includes the demolition of two existing
buildings, renovation of one building, reconstruction of one building, and associated site
improvements including secured parking, guest parking, and an entry plaza to accommodate current
and future Dublin Police Services' needs; and
WHEREAS, the City of Dublin did, on January 18, 2018, publicly open, examine, and declare
all sealed bids for doing the work described in the approved Plans, Specifications, and Modifications
for the Project, which Plans, Specifications, and Modifications are hereby expressly referred to for a
description of said work and for all particulars relative to the proceedings under the request for bids;
and
WHEREAS, Sausal Corporation's bid contained a minor bid irregularity in that there was a
mathematic error summing the total of the unit bid items, which subsequently lowered the total base
bid price by One Hundred Dollars ($100.00) and the Public Contract Code and the City's bid
documents and authorize the City to waive any minor bid irregularities, and proceed with the award of
the contract; and
WHEREAS, said bids were submitted to the Public Works Director, who has recommended
that the bid hereinafter is the lowest and best bid for doing said work.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin hereby
approves the plans and specifications for the Project.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby waive the
minor bid irregularity contained within Sausal Corporation bid, and award a Contract for Project No.
G10116 Public Safety Complex — Police Services Building, to the lowest responsible bidder, to wit,
Sausal Corporation, for the base bid plus four add alternate items, and a ten percent contingency, at
a bid of $16,811,740.00, the particulars of which bid are on file in the Office of the Public Works
Director.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby authorize
the City Manager or his designee to execute the Construction Agreement with Sausal Corporation
and to approve Contract Change Orders based on the appropriated funds designated for the Project
up to the contingency amount of $1,528,340.00.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby approve
the Agreement with Swinerton Builders, dba Swinerton Management & Consulting for construction
management and inspection services for the Project, as attached hereto as Exhibit A to this
Resolution, for the not to exceed amount of $975,000.00.
Reso No. 14-18, Adopted 2/6/2018, Item No. 7.1 Page 1 of 2
BE IT FURTHER RESOLVED that the City Manager is authorized to execute the Agreement
with Swinerton Builders, dba Swinerton Management & Consulting.
PASSED, APPROVED AND ADOPTED this 6th day of February, 2018, by the following vote:
AYES: Councilmembers Biddle, Goel, Gupta and Hernandez, and Mayor Haubert
NOES:
ABSENT:
ABSTAIN:
ATTEST:ra" Z
��-
%�
City Clerk
iAA1_1_
G
Mayor'
Reso No. 14-18, Adopted 2/6/2018, Item No. 7.1 Page 1 of 2
RESOLUTION NO. 94 —18
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
APPROVING THE PLANS AND SPECIFICATIONS; AWARDING A CONTRACT TO GRANITE
CONSTRUCTION COMPANY AND WAIVE MINOR BID IRREGULARITY; AUTHORIZING THE
CITY MANAGER TO EXECUTE AGREEMENTS WITH ALAMEDA COUNTY TRANSPORTATION
COMMISSION FOR DUBLIN BOULEVARD WIDENING PROJECT, PROJECT NO. ST1012
WHEREAS, the design team has completed the plans and specifications for the Dublin
Boulevard Widening Project CIP No. ST1012 ("Project"). The work includes widening Dublin
Boulevard to three lanes in each direction and modify the median islands between Civic Plaza and
Dublin Court, the addition of bike lanes, new curb gutter and sidewalk along both sides of the street,
installing a pedestrian bridge across the Zone 7 channel, and repaving Dublin Boulevard from Civic
Plaza to Dougherty Road; and
WHEREAS, the City of Dublin did, on June 19, 2018, publicly open, examine, and declare all
sealed bids for doing the work described in the approved Plans and Specification for the Project,
which Plans and Specification are hereby expressly referred to for a description of said work and for
all particulars relative to the proceedings under the request for bids; and,
WHEREAS, Granite Construction Company's bid contained a minor bid irregularity in that
there was a mathematic error decreasing the proposed contract price by $90,500 and the Public
Contract Code and the City's bid documents authorize the City to waive any minor irregularity and
proceed with the award of the contract; and
WHEREAS, said bids were submitted to the Public Works Director, who has recommended
that the bid hereinafter is the lowest responsive responsible bid for doing said work.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin hereby
approves the plans and specifications for the Project.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby
authorizes the City Manager to execute agreements with Alameda County Transportation
Commission for the project.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby waive the
minor bid irregularity since the mathematical error only decreased the lowest responsible bid by
$90,500.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby award
the Contract for the Project, to the lowest responsive responsible bidder therefore, to wit, Granite
Construction Company, at a bid of Five Million, Six Hundred and Seventy -Eight Thousand, Four
Hundred and Fifty -Four Dollars and no cents ($5,678,454.00) the particulars of which bid are on file in
the Office of the Public Works Director.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby authorize
the City Manager of his designee to approve the Project Contract Change Orders based on the
appropriated funds designated for the Project up to the contingency amount of $575,000.
Reso No. 94-18, Adopted 7/17/2018, Item No. 4.11 Page 1 of 2
BE IT FURTHER RESOLVED that the City Manager is authorized to execute the Project
Construction Agreement.
PASSED, APPROVED AND ADOPTED this 17th day of July 2018, by the following vote:
AYES: Councilmembers Gupta, Hernandez, Thalblum and Mayor Haubert
NOES:
ABSENT: Councilmember Goel
ABSTAIN:
r•
ATTEST: Mayor
City Clerk
Reso No. 94-18, Adopted 7/17/2018, Item No. 4.11 Page 2 of 2