HomeMy WebLinkAbout4.8 - 2594 Award Pedestrian Improvements Project on Am
Page 1 of 3
STAFF REPORT
CITY COUNCIL
DATE: May 7, 2019
TO: Honorable Mayor and City Councilmembers
FROM:
Christopher L. Foss, City Manager
SUBJECT:
Award of Contract to Golden Bay Construction Inc., for Amador Valley
Boulevard - Wildwood Road and Stagecoach Road Intersections
Improvements, Project No. ST0317
Prepared by: Sai Midididdi, Associate Transportation Engineer (Civil)
EXECUTIVE SUMMARY:
The City Council will consider approving the plans and specifications and awarding a
construction contract to Golden Bay Construction, Inc. for the Amador Valley Boulevard
– Wildwood Road and Stagecoach Road Intersection s Improvements, Project No.
ST0317. The project will: construct a bulb out bioretention planter and install a
Rectangular Rapid Flashing Beacon at Amador Valley Boulevard and Wildwood Road;
modify the traffic signal, construct new curb ramps, and modify medians at Amador
Valley Boulevard and Stagecoach Road; and will convert the Amador Valley Boulevard
median irrigation to recycled water east of Stagecoach Road.
STAFF RECOMMENDATION:
Adopt the Resolution Approving the Plans and Specifications and Awarding a Contract
to Golden Bay Construction, Inc., for Amador Valley Boulevard - Wildwood Road and
Stagecoach Road Intersections Improvements Project No. ST0317.
FINANCIAL IMPACT:
As approved in the 2018-2023 Capital Improvement Program, the total remaining
budget for the Amador Valley Boulevard – Wildwood Road and Stagecoach Road
Intersections Improvements is $859,971.86. The lowest responsive bid for construction
was $636,761.70. A construction contingency of $75,000 is requested for unforeseen
construction issues, bringing the total potential construction cost to $711,761.70.
Sufficient funding is available in the project budget to cover th e construction contract
costs.
DESCRIPTION:
The Five-Year Capital Improvement Program (CIP), adopted by City Council, includes
Amador Valley Boulevard - Wildwood Road and Stagecoach Road Intersections
Improvements, CIP No. ST0317 (Attachment 1). The project will construct a landscaped
Page 2 of 3
bioretention planter and bulb out and will install pedestrian activated Rectangular Rapid
Flashing Beacons (flashing pedestrian warning lights) at the Amador Valley Boulevard
and Wildwood Road intersection. The project will also modify traffic signal infrastructure
and signal timing, for safer pedestrian crossing, construct new cub ramps, and modify
the medians, roadway striping, and signs at the Stagecoach Road intersection. The
project will also convert the Amador Valley Boulevard median irrigation from potable
water to recycled water.
The plans and specifications were completed and advertised for bids in March 2019. A
total of two sealed bids were received on April 2, 2019. A summary of the bids is
provided as Attachment 2. The low bid of $636,761.70 was submitted by Golden Bay
Construction Inc. The low bid contained an arithmetic error between an item unit cost
and the mathematical sum, which subsequently decreased the total base bid price by
$40. The Public Contract Code and the City’s bid documents define this as a “minor bid
irregularity,” and authorize the City to waive this irregularity and proceed with the award
of the contract.
Staff has reviewed the bid results and bidder qualification statements, checked
references and necessary licenses, and recommends that the City Council adopt the
Resolution (Attachment 3), awarding the project construction contract to Golden Bay
Construction Inc, as the lowest responsive bidder. To facilitate the approval of contract
change orders and to avoid construction delay, it is requested that the City Manager be
authorized to approve change orders up to the contingency amount of $75,000. The
Resolution will authorize this change as it relates to this project.
Staff expects the project to begin in early June 2019 and anticipates completion by the
end of September 2019. To minimize impact to school-related vehicular, bicycle, and
pedestrian traffic, the contract specifications require the contractor to diligently pursue
all work items prior to August 10. Work occurring after August 10 shall not result in
closure of more than one crosswalk at a time.
This project is exempt under Section 15301 (Existing Facilities) of the CEQA
Guidelines.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
Strategy 3: Pursue efforts to help strengthen the City’s infrastructure and technology.
Strategic Objective 3b: Continue to embrace technology to improve traffic street and
engineering infrastructure.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
A copy of this staff report was sent to Golden Bay Construction, Inc. and to the Alameda
County Transportation Commission, Independent Watchdog Committee.
ATTACHMENTS:
1. ST0317 - Amador Valley Boulevard at Wildwood Road and Stagecoach Road
Intersections Improvements Project
2. Bid Results
Page 3 of 3
3. Resolution Approving the Plans and Specifications and Awarding a Contract to
Golden Bay Construction, Inc., for the Amador Valley Boulevard - Wildwood Rd and
Stagecoach Rd Intersections Project
Number ST0317 Program STREETS
ESTIMATED COSTS
PRIOR
YEARS
2018-2019
BUDGET 2019-2020 2020-2021 2021-2022 2022-2023
FUTURE
YEARS
ESTIMATE TOTALS
9100 $639 $33,071 $33,710
9200 $13,712 $165,538 $179,250
9400 $874,300 $874,300
9500 $1,000 $1,000
$14,352 $1,073,908 $1,088,260
FUNDING SOURCE
PRIOR
YEARS
2018-2019
BUDGET 2019-2020 2020-2021 2021-2022 2022-2023
FUTURE
YEARS
ESTIMATE TOTALS
1001 $193,000 $193,000
2204 $159,035 $159,035
2205 $14,352 $493,772 $508,124
2214 $84,560 $84,560
2215 $103,541 $103,541
2302 $40,000 $40,000
$14,352 $1,073,908 $1,088,260
Measure B Sales Tax - Bike &
Pedestrian Fund (ACTC)
Measure B Sales Tax - Local
Streets Fund (ACTC)
Salaries & Benefits
Contract Services
Improvements
AMADOR VALLEY BLVD - WILDWOOD ROAD & STAGECOACH INTERSECTIONS IMPROVEMENTS
TOTAL
Measure BB Sales Tax - Local
Streets Fund (ACTC)
Measure BB Sales Tax - Bike &
Pedestrian Fund (ACTC)
Measure D
General Fund
Miscellaneous
TOTAL
2018-2023 CAPITAL IMPROVEMENT PROGRAM
PROJECT DESCRIPTION
This project includes safety improvements for vehicle, bicycle, and pedestrian traffic on Amador Valley Boulevard at the intersections of Wildwood Road and Stagecoach Road.
The project will facilitate safe merging of two vehicle lanes into one lane on westbound Amador Valley Boulevard at Wildwood Road and will enhance traffic signal timing at
Stagecoach Road for safer pedestrian crossings and improved signal coordination. Improvements at Wildwood Road include a curb extension and a Rectangular Rapid Flashing
Beacon to augment the existing lighted crosswalk. Improvements at Stagecoach Road include a median and signal modifications. Other improvements will include roadway
striping modifications, sign modifications, and curb ramp upgrades. The project is anticipated to be complete in summer 2019.
ANNUAL OPERATING IMPACT:None
MANAGING DEPARTMENT: Public Works
ST 0317
Bid Date:
BASED BID
ITEM Qty.UNIT Unit Cost Extension Unit Cost Extension
1 Mobilization 1 LS $63,500.00 $63,500.00 $71,000.00 $71,000.00
2 Traffic control 1 LS $98,046.00 $98,046.00 $71,000.00 $71,000.00
3 Construction stormwater pollution prevention best management practices 1 LS $4,200.00 $4,200.00 $9,000.00 $9,000.00
4 Temporarily re-wire Pole I as specified in plans 1 LS $10,080.00 $10,080.00 $9,300.00 $9,300.00
5 Remove & Salvage Existing Traffic Signal Pole and Traffic Signal Equipment 3 EA $840.00 $2,520.00 $800.00 $2,400.00
6 Remove pole j foundation 1 LS $2,800.00 $2,800.00 $2,600.00 $2,600.00
7 Trim and abandon pole i and d foundations 1 LS $1,540.00 $1,540.00 $1,400.00 $1,400.00
8 Remove & Salvage Existing Traffic Signal Controller Cabinet 1 EA $1,400.00 $1,400.00 $1,300.00 $1,300.00
9 Remove & Salvage Existing Vehicle Signal Head 6 EA $140.00 $840.00 $130.00 $780.00
10 Remove & Salvage Existing Pedestrian Signal Head 3 EA $140.00 $420.00 $130.00 $390.00
11 Remove & Salvage Existing Mounting Bracket 6 EA $70.00 $420.00 $65.00 $390.00
12 Remove & Salvage Existing Pedestrian Push Button 8 EA $84.00 $672.00 $75.00 $600.00
13 Relocate Type IIA service enclosure on new cabinet 1 EA $1,680.00 $1,680.00 $1,550.00 $1,550.00
14 Furnish & Install NEMA TS2-Type 1 Controller Cabinet with Naztec Model 980 ATC Controller 1 EA $42,000.00 $42,000.00 $38,400.00 $38,400.00
15 1 LS $6,440.00 $6,440.00 $5,900.00 $5,900.00
16 Furnish & Install BBS 1 EA $8,680.00 $8,680.00 $8,000.00 $8,000.00
17 Install City-furnished Temple Edge-lit SNS on Signal Pole 4 EA $1,120.00 $4,480.00 $1,100.00 $4,400.00
18 Furnish & Install LED Vehicle Signal Head - 3 sec 12" 10 EA $784.00 $7,840.00 $720.00 $7,200.00
19 Furnish & Install LED Countdown Pedestrian Signal Head 3 EA $672.00 $2,016.00 $620.00 $1,860.00
20 Furnish & Install Polara iNavigator APS Station 8 EA $1,162.00 $9,296.00 $1,065.00 $8,520.00
21 Furnish & Install Polara Central Control Unit in Cabinet 1 EA $4,270.00 $4,270.00 $3,900.00 $3,900.00
22 Furnish & Install LED Luminaire 1 EA $1,470.00 $1,470.00 $1,350.00 $1,350.00
23 Furnish and Install 2" Conduit (incl. trenching or boring)50 LF $131.00 $6,550.00 $120.00 $6,000.00
24 Furnish and Install Type D (4x4) Bike Loop 1 EA $4,480.00 $4,480.00 $4,100.00 $4,100.00
25 Install Conduit into Existing Box (CB)5 EA $588.00 $2,940.00 $540.00 $2,700.00
26 Install City-furnished Type 23-4-100 Pole on New Foundation 1 EA $11,900.00 $11,900.00 $10,900.00 $10,900.00
27 Install City-furnished Type 24-4-100 Pole on New Foundation 1 EA $11,900.00 $11,900.00 $10,900.00 $10,900.00
28 Furnish & Install Signal Head Mount Type MAS 4 EA *$655 $2,620.00 $610.00 $2,440.00
29 Furnish & Install Signal Head Mount Type SV-1-T 1 EA $700.00 $700.00 $700.00 $700.00
30 Furnish & Install Signal Head Mount Type SV-3-TB 1 EA $1,330.00 $1,330.00 $1,220.00 $1,220.00
31 Furnish & Install Pedestrian Signal Head Mount SP-2-T 2 EA $1,071.00 $2,142.00 $1,000.00 $2,000.00
32 Furnish & Install Signal Conductors and Cables 1 LA $29,400.00 $29,400.00 $27,000.00 $27,000.00
33 Furnish & Install Opticom Model 721 EVP Detector 2 EA $1,148.00 $2,296.00 $1,100.00 $2,200.00
34 Remove and Salvage Existing Signs 7 EA $91.00 $637.00 $100.00 $700.00
35 Furnish and Install R73-3 (CA) (36x36)2 EA $721.00 $1,442.00 $660.00 $1,320.00
36 Relocate existing pull box and reterminate conduits 2 EA $700.00 $1,400.00 $640.00 $1,280.00
37 Furnish and Install No. 5 Pull Box 2 EA $910.00 $1,820.00 $830.00 $1,660.00
38 Connect new and existing conduits (CC)6 EA $1,260.00 $7,560.00 $1,150.00 $6,900.00
39 Remove In-Roadway Warning Lights 1 LS $4,640.00 $4,640.00 $2,150.00 $2,150.00
40 Install City-furnished Caltrans Type 1-B (15') pole on Existing Foundation 1 EA $2,352.00 $2,352.00 $2,150.00 $2,150.00
41 Install City-furnished Caltrans Type 1-B (15') pole on New Foundation 1 EA $4,480.00 $4,480.00 $4,100.00 $4,100.00
42 Relocate Type 15D electrolier on New Foundation 1 EA $8,680.00 $8,680.00 $8,000.00 $8,000.00
43 Furnish and Install R4-7 (24x30), OM1-1, and R3-4 (36x36) sign on galvanized steel pole 1 EA $608.00 $608.00 $580.00 $580.00
44 Furnish and Install R3-7 (36x36) sign on new telespar post 1 EA $405.00 $405.00 $380.00 $380.00
45 Furnish and Install Flexible Channelizer Posts 10 EA $101.00 $1,010.00 $95.00 $950.00
46 Furnish and Install Type 2 (OM 2-2H) Object Markers 1 LS $135.00 $135.00 $130.00 $130.00
47 Relocate existing pole and signs 3 EA $540.00 $1,620.00 $518.00 $1,554.00
48 Install reflective yellow paint on median nose curb (top and face)10 LF $27.00 $270.00 $26.00 $260.00
49 Remove Concrete (Vertical Curb)50 LF $45.00 $2,250.00 $20.00 $1,000.00
50 Remove Concrete (Curb and Gutter)178 LF $45.00 $8,010.00 $20.00 $3,560.00
51 Remove Concrete (Sidewalk and Ramp)1280 SF $9.00 $11,520.00 $16.00 $20,480.00
52 Remove Concrete (Median)47 SF $9.00 $423.00 $20.00 $940.00
53 Cold Plane Asphalt Concrete Pavement 145 SQYD $71.00 $10,295.00 $56.00 $8,120.00
54 Hot Mix Asphalt (Type A)47.3 TON $464.00 $21,947.20 $750.00 $35,475.00
55 Miscellaneous Concrete Construction (Curb and Gutter)168 LF $83.00 $13,944.00 $106.00 $17,808.00
56 Miscellaneous Concrete Construction (Vertical Curb)30 LF $83.00 $2,490.00 $96.00 $2,880.00
57 Miscellaneous Concrete Construction (Curb Ramp) 715 SF $23.00 $16,445.00 $32.00 $22,880.00
58 Miscellaneous Concrete Construction (Sidewalk)984 SF $17.00 $16,728.00 $21.00 $20,664.00
59 Miscellaneous Concrete Construction (Median)20 SF $23.00 $460.00 $23.00 $460.00
60 Miscellaneous Concrete Construction (Bioretention Structure)5 CY $4,092.00 $20,460.00 $7,600.00 $38,000.00
61 Detectable Warning Surface 88 SF $46.00 $4,048.00 $65.00 $5,720.00
62 Adjust Utility Box Frame and Cover 2 EA $300.00 $600.00 $350.00 $700.00
63 Convert Drainage Inlet to Manhole 1 EA $2,250.00 $2,250.00 $7,500.00 $7,500.00
64 Modify Drainage Inlet 1 EA $2,250.00 $2,250.00 $7,500.00 $7,500.00
65 Drainage Inlet (Type A)1 EA $9,800.00 $9,800.00 $87,000.00 $87,000.00
66 4" Perforated Plastic Pipe Underdrain 17 LF $20.00 $340.00 $14.00 $238.00
67 4" Plastic Pipe Cleanout with Cap 6 LF $95.00 $570.00 $105.00 $630.00
68 Bioretention Soil Mix 13.2 CY $220.00 $2,904.00 $170.00 $2,244.00
69 Class II Permeable Material 7.5 CY $220.00 $1,650.00 $200.00 $1,500.00
70 Streambed Cobblestone (4" Dia Max)0.4 CY $2,710.00 $1,084.00 $2,800.00 $1,120.00
71 Irrigation and Landscaping 1 LS $52,463.00 $52,463.00 $45,460.00 $45,460.00
72 Remove Existing Striping(Revocable)1238 LF $5.00 $6,190.00 $5.30 $6,561.40
73 Remove Existing Pavement Marking(Revocable)2 EA $338.00 $676.00 $320.00 $640.00
74 Field Adjust Signal Pole (incl. field drilling, adjusting mountings, and welding plugs)(Revocable)1 EA $4,995.00 $4,995.00 $4,800.00 $4,800.00
75 Install Green Methyl Methacrylate (MMA) Resin (Revocable)599 SF $16.00 $9,584.00 $15.00 $8,985.00
76 Furnish and Install Thermoplastic Detail 22 (incl. 4" cross-hatch)(Revocable) 270 LF $4.00 $1,080.00 $3.80 $1,026.00
77 Furnish and Install Thermoplastic Detail 27B (incl. 4" cross-hatch)(Revocable) 86 LF $2.00 $172.00 $2.00 $172.00
78 Furnish and Install Thermoplastic Detail 38 (incl. 4" cross-hatch)(Revocable) 190 LF $3.00 $570.00 $2.70 $513.00
79 Furnish and Install Thermoplastic Detail 39(Revocable)390 LF $2.00 $780.00 $2.00 $780.00
80 Furnish and Install Thermoplastic Detail 39A(Revocable)284 LS $2.00 $568.00 $2.00 $568.00
81 Furnish and Install Thermoplastic Yield Limit Line(Revocable)60 SF $15.00 $900.00 $14.00 $840.00
82 Furnish and Install Thermoplastic Type IV (R) Arrow(Revocable)2 EA $162.00 $324.00 $154.00 $308.00
83 Furnish and Install Thermoplastic Shared Lane Marking (Sharrow)(Revocable) 3 EA $178.00 $534.00 $170.00 $510.00
84 Furnish and Install Thermoplastic Bicycle Pavement Marking and Arrow(Revocable) 4 EA $202.00 $808.00 $200.00 $800.00
85 Furnish and Install "STOP" pavement marking(Revocable)1 EA $68.00 $68.00 $65.00 $65.00
86 Furnish and Install Thermoplastic Trail Crosswalk(Revocable)1 EA $297.00 $297.00 $280.00 $280.00
87 Furnish and Install Thermoplastic Crosswalk(Revocable)1 EA $2,565.00 $2,565.00 $2,400.00 $2,400.00
88 Furnish and Install Thermoplastic Crosswalk Striping (Conform)(Revocable) 1 LS $1,418.00 $1,418.00 $1,400.00 $1,400.00
89 Furnish and Install Non-Reflective Raised Pavement Markers(Revocable) 86 LF $3.25 $279.50 $3.00 $258.00
90 Install Green Traffic Paint(Revocable)599 SF $8.00 $4,792.00 $8.00 $4,792.00
91 Furnish and Install Traffic Paint Detail 22 (incl. 4" cross-hatch)(Revocable) 270 LF $3.25 $877.50 $3.20 $864.00
92 Furnish and Install Traffic Paint Detail 27B (incl. 4" cross-hatch)(Revocable) 86 LF $1.50 $129.00 $1.30 $111.80
93 Furnish and Install Traffic Paint Detail 38 (incl. 4" cross-hatch)(Revocable) 190 LF $2.75 $522.50 $2.60 $494.00
94 Furnish and Install Traffic Paint Detail 39(Revocable)390 LF $2.00 $780.00 $1.80 $702.00
95 Furnish and Install Traffic Paint Detail 39A(Revocable)284 LS $2.00 $568.00 $1.80 $511.20
96 Furnish and Install Traffic Paint Yield Limit Line(Revocable)60 SF $12.00 $720.00 $11.50 $690.00
97 Furnish and Install Traffic Paint Type IV (R) Arrow(Revocable)2 EA $122.00 $244.00 $115.00 $230.00
98 Furnish and Install Traffic Paint Shared Lane Marking (Sharrow)(Revocable) 3 EA $130.00 $390.00 $122.00 $366.00
99 Furnish and Install Traffic Paint Bicycle Pavement Marking and Arrow(Revocable) 4 EA $149.00 $596.00 $140.00 $560.00
100 Furnish and Install Traffic Paint "STOP" pavement marking(Revocable)1 EA $230.00 $230.00 $220.00 $220.00
101 Furnish and Install Traffic Paint Trail Crosswalk(Revocable)1 EA $2,835.00 $2,835.00 $2,600.00 $2,600.00
102 Furnish and Install Traffic Paint Crosswalk(Revocable)1 EA $1,343.00 $1,343.00 $1,270.00 $1,270.00
103 Furnish and Install Traffic Paint Crosswalk Striping (Conform)(Revocable)1 LS $68.00 $68.00 $64.00 $64.00
TOTAL *$636,761.70 $729,774.40
* Mathamatical summation error and a unit extension error
List of Sub-Contractors
SWPP Tully Consulting Group
Marine Landscape, Inc.
Electrical W. Bradley Electric W. Bradley Electric
Survey Benchmark Engineering, Inc.
Golden Bay Construction Inc.
Description Golden Bay Construction Inc. Sposeto Engineering Inc.
Striping and Signs
APPARENT LOW BIDDER
Sierra Traffic Markings, Inc. Sierra Traffic Markings, Inc.
Landscape Doms Landscaping, Inc.
Project No. :
PUBLIC WORKS DEPARTMENT
Sposeto Engineering Inc.
Modify existing controller cabinet foundation, incl. raising controller cabinet to temporary height
Pedestrian Improvements at the Amador Valley Boulevard/Wildwood Road and Amador Valeey BoulevardStagecoach Road
Intersections
DESCRIPTION
CITY OF DUBLIN
ENGINEERING DIVISION
BID SUMMARY
April 9, 2019
Project Name:
1
RESOLUTION NO. XX- 19
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
* * * * * * * * *
APPROVING THE PLANS AND SPECIFICATIONS AND AWARDING A CONTRACT TO
GOLDEN BAY CONSTRUCTION INC. FOR AMADOR VALLEY BOULEVARD - WILDWOOD
ROAD AND STAGECOACH ROAD INTERSECTIONS IMPROVEMENTS, CIP NO. ST0317
WHEREAS, the design team completed plans and specifications for Amador Valley
Boulevard - Wildwood Road and Stagecoach Road Intersection Improvements, CIP No.
ST0317 (“Project”). The work includes installation of pedestrian warning lights, construction of
curb extension and improved roadway signage and markings at Wildwood Road; and the
modification of traffic signal and concrete median, curb ramp upgrades and improved roadway
signage and markings at Stagecoach Road; and
WHEREAS, the City of Dublin did, on April 2, 2019, publicly open, examine, and declare
all sealed bids for doing the work described in the approved plans and specifications for the
Project, which plans and specifications, are hereby expressly referred to for a description of
said work and for all particulars relative to the proceedings under the request for bids; and
WHEREAS, Golden Bay Construction Inc’s bid contained a minor bid irregularity in that
there was mathematical error decreasing the proposed contract price by forty dollars ($40) and
the Public Contract Code and the City’s bid documents authorize the City to waive any minor
irregularity and proceed with the award of contract; and
WHEREAS, said bids were submitted to the Public Works Director, who has
recommended that the bid hereinafter is the lowest responsive bid for doing said work.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin
hereby approves the plans and specifications for the Project.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby
waive the minor bid irregularity since the mathematical error only decreased the lowes t
responsible bid by forty dollars ($40).
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby
award the Contract for the Project, to the lowest responsive bidder, Golden Bay Construction
Inc., at a bid of six hundred thirty six thousand seven hundred sixty one dollars and seventy
cents ($636,761.70), the particulars of which bid are on file in the Office of the Public Works
Director.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby
authorize the City Manager or his designee to approve the Project Contract Change Orders
based on the appropriate funds designated for the Project up to the contingency amount of
seventy five thousand dollars ($75,000).
BE IT FURTHER RESOLVED that the City Manager or his designee is authorized to
execute the Project Construction Agreement with Golden Bay Construction Inc.
PASSED, APPROVED AND ADOPTED this 7th day of May 2019, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
________________________________________
Mayor
ATTEST:
_____________________________
City Clerk