RECOMMENDATION
~
l.
2.
3 .
Receive Presentation from singer & Hodges
Receive Input from Public
Approve Design Alternate #2 with Sand base
Eliminating the Seat Wall and Planting Strip
Submit the Design Alternates to the Dublin
Unified School District for Approval
Funds are Available in the 1990-95 Capital
Improvement Program as follows:
Design/Inspection - $ 7,110
Improvements 32,195
TOTAL - $39,305
The City will fund $34,305 and the District will
contribute the balance of $5,000
4 .
FINANCIAL STATEMENT
DESCRIPTION At the March 26, 1990 meeting of the Dublin City
Council, the council authorized staff to enter into a contract agreement
with singer & Hodges, Inc. for the development of a kindergarten tot lot at
Frederiksen School. Further, staff was directed to negotiate a development
agreement with the Dublin Unified School District for the project which was
approved by the council on July 9, 1990.
Prior to the development of the design for the tot lot, staff and the
consultant met with representatives from the School District to discuss the
scope of the project. The direction received from the School District was
to develop a playground which would provide a safe, stimulating and
developmentally appropriate play area for the kindergarten children, and
one that would provide varied uses as follows:
1. Teacher directed obstacle course
2. Individual development
3. Small group play
4. Open space area
utilizing this information, the consultant developed a design for the tot
lot which was reviewed at a neighborhood meeting held on August 2, 1990.
Based on the input received at that meeting, the design was refined and
presented to the Parks and Recreation Commission on August 7, 1990.
Two design alternates will be available for review by the city Council at
the meeting. Both design alternates include a multi-use play structure I
swing, balance beam, and spring rider. Additionally each design contains a
three foot planting strip adjacent to the fence and a concrete seat wall to
provide seating for both children and adults. Al though both designs
include basically the same amenities, Design Alternate #2 provides for a
larger play area with more challenging equipment. Design Alternate #2 is
the recommended design of the Parks and Recreation Commission.
----------------------------------------------------------------------
ITEM NO. a.1
COPIES TO: singer & Hodges, Inc.
Dublin Unified School District
Agenda statement - Fredericksen
August 13, 1990
Page Two
Although the Dublin Unified School District Board has not formally reviewed
the design¡ initial discussions with the School District indicate that the
Board may not be in favor of the use of sand as play area surfacing
material. Thus, the consultant was directed to provide staff with
al ternati ve surfacing materials. The surfacing materials recommended by
the consultant and approved by the Consumer Products Safety Commission are
summarized below:
Sand
In general, sand has good resiliency and is the most commonly used
playground surface in this region. Sand is well draining and is one of the
least expensive, absorbent surfaces. The potential problem of pet feces is
occasionally mentioned when sand is discussed, but does not appear to be a
serious problem in most public agencies. Sand does spill and is carried
out of the play area so that it can cause scratches to flooring in adjacent
school buildings.
IIFibarll
IIFibartl is a shredded wood fiber which has excellent absorbent safety
characteristics and is relatively easy to install. It requires slightly
more maintenance than sand because the lighter particles tend to blow
around. It is more difficult to sift through IIfibarll than sand to remove
litter and debris. "Fibar", if installed per manufacturer's specifications,
is more expensive than sand.
"Playsafetl Protective Surfacino
"Playsafetl surfacing is a rubber, absorbent cushion that is poured in place
under play equipment. tlPlaysafe" meets the Product Safety commissioner's
safety standards and has been used in school grounds and parks. "Playsafe"
is the most maintenance-free of the rubber surfaces because it is poured as
one unit rather than assembled in sections. The surfacing is a good deal
more expensive than sand or "Fibar", but requires little maintenance.
The cost comparison for the various surface materials is as follows:
12" Depth Sand.........$ .60 to .75
12" Depth "Fibar"......$ 2.75 to 2.95
"Playsafe".............$11.00 to 12.00
Should the District prefer either the "Fibar" or "Playsafell surfacing, it
is staff's recommendation that the District absorb the additional cost.
Preliminary cost estimates have been prepared for each alternate and are
shown below:
Alternate #1 (with sand surfacing) $34,040
Alternate #1 (with nFibarll surfacing) $37,890
Alternate #1 (with "Playsafe" surfacing) $55,600
Alternate #2 (with sand surfacing) $39,410
Alternate #2 (with "Fibar" surfacing) $43,920
Alternate #2 (with nPlaysafe" surfacing) $64,665
The preliminary cost estimates are currently over the allowable project
budget of $ 3 2,195. In order to reduce the cost of the project, the
concrete seat wall could be replaced with a concrete curb and the planting
strip could be eliminated.
AGENDA STATEMENT - Fredericksen Tot Lot
August 13{ 1990
Page Three
Revised preliminary cost estimates with these items deleted are as follows:
Alternate #1 (with sand surfacing) $28,660
Alternate #1 (with "Fibar" surfacing) $32,510
Alternate #1 (with IIPlaysafe" surfacing) $50{220
Alternate #2 (with sand surfacing) $34,025
Alternate #2 (with tlFibar" surfacing) $38,535
Alternate #2 (with "Playsafe surfacing) $59,280
It is recommended that the city council take the following action:
1. Receive Presentation from singer & Hodges, Inc.
2. Receive Public Input
3. Approve Design Alternate #2 with Sand Base Eliminating the Seat
Wall and Planting strip
4. Submit the Design Alternates to the Dublin Unified School
District for Approval