HomeMy WebLinkAbout4.04 AccptWrk89-6DSG Fence
CITY OF DUBLIN
AGENDA STATEMENT
City Council Meeting Date: May 22, 1989
SUBJECT:
Acceptance of Work - Contract No. 89-6
Dublin Sports Grounds Barrier Fence
(Report by Public Works Director Lee Thompson)
EXHIBITS ATTACHED:
None
RECOMMENDATION: ~ ~ ~ept improvements constructed under Contract 89-6
\ Lv'...... :~~ authorize payment to Calco Fence in the amount of
$15,373.20.
FINANCIAL STATEMENT:
Budget authorized:
$16,000.00
Project cost:
Construction:
Est. Design/inspection:
$15,373.20
598.50
$15,971. 70
DESCRIPTION:
On March 27, 1989, the City Council authorized a budget transfer in the
amount of $16,000 and authorized Staff to solicit bids for construction of
an l8-foot-high barrier fence at two softball diamonds adjacent to 1-580 in
order to prevent balls from being hit onto the freeway. Caltrans recently
completed construction of a new auxiliary lane which brings traffic closer
to the Sports Grounds than it was previously.
On April 10th, the City Council awarded Contract 89-6 for construction of
the barrier fence to Calco Fence, Inc.
Work on the project has been inspected and determined to be complete and in
accordance with the approved plans and specifications. Staff recommends
that the City Council accept the improvements and authorize payment to Calco
Fence in the amount of $15,373.20.
- - - - - -- - - - - - - - - -- - -- - - - - - -- - -- - -- - -- -- - -- - -- -- - -- -- - -- -- -- -- - -- -- - - - -- -- -- ---
ITEM NO.
I .
'! / i
.l.¡ .r.......
..' <I- .
COPIES TO: Calco Fence
Oakland Fence