HomeMy WebLinkAboutAttachment 1 Reso CC appv03-058RESOLUTION NO. 04-
A RESOLUTION OF THE PLANNING COMMISSION
OF THE CITY OF DUBLIN
RECOMMENDING CITY COUNCIL ADOPTION OF STAGE 2 PLANNED DEVELOPMENT
ZONING FOR PA 03-058 DUBLIN TRANSIT CENTER SITE B-2 (AVALON BAY
COMMUNITIES) LOCATED AT THE SOUTHWEST CORNER OF DUBLIN BOULEVARD
AND IRON HORSE PARKWAY
(APN 986-0001-011-00)
WHEREAS, the Applicant, Avalon Bay Communities, has requested approval of Stage 2 Planned
Development Zoning for PA 03-058, Dublin Transit Center Site B-2, for the construction of a 305-unit
apartment community with 15,000+ square feet of retail on approximately +3.57 acres of land, located on
a portion of Site B of the Dublin Transit Center, within the Eastern Dublin Specific Plan, at the southwest
corner of Dublin Boulevard and Iron Horse Parkway; and
WHEREAS, the Applicant has submitted a complete application for Stage 2 Planned
Development Zoning for the construction of a 305-unit apartment community with 15,000+_ square feet of
retail which is available and on file in the Planning Division; and
WHEREAS, the Applicant has submitted project plans in conjunction with the requested
entitlement dated October 25, 2004 and a Stage 2 Development Plan; and
WHEREAS, the California Environmental Quality Act (CEQA), together with the State
guidelines and City environmental regulations require that certain projects be reviewed for environmental
impacts and that environmental documents be prepared; and
WHEREAS, Pursuant to the California Environmental Quality Act, Staff has recommended that
the project be found exempt from CEQA pursuant to Government Code section 65457 for residential
projects that are consistent with a specific plan. The Project is within the scope of the Final
Environmental Impact Report for the Dublin Transit Center General Plan Amendment, Eastern Dublin
Specific Plan Amendment, Stage 1 Planned Development Zoning, Tentative Parcel Map, and
Development Agreement (SCI-I 2001120395) which was certified by City Council Resolution No. 215-02
dated November 19, 2002. This recommendation is based on a determination that there are no
supplemental impacts that would require preparation of a Supplemental EIR; and
WHEREAS, a public hearing was scheduled before the Planning Commission on November 9,
2004; and
WHEREAS, proper notice of said public hearing was given in all respects as required by law; and
WHEREAS, a Staff Report was submitted to the Planning Commission describing the project and
outlining the issues surrounding the request; and
WHEREAS, the Planning Commission did hold a public hearing on said project application on
November 9, 2004; and
IITfACHMENT ~
WHEREAS, the Planning Commission did use its independent judgment and considered all said
reports, recommendations, and testimony hereinabove set forth; and
NOW, THEREFORE, BE IT RESOLVED THAT THE Planning Commission of the City of
Dublin does hereby make the following findings and determinations regarding said Stage 2 Planned
Development Zoning:
A. The proposed amendment will be harmonious and compatible with existing and potential
development in surrounding areas.
B. The subject site is physically suitable for the type and intensity of the zoning district being
proposed.
C. The proposed amendment will not adversely affect the health or safety of persons residing or
working in the vicinity, or be detrimental to the public health, safety, and welfare.
D. The proposed amendment is consistent with the Dublin General Plan and Eastern Dublin Specific
Plan.
E. The proposed Planned Development Zoning District meets the purpose and intent of Chapter 8.32
Planned Development Zoning District of the Dublin Zoning Ordinance.
F. Development under the Planned District Development Plan will be harmonious and compatible
with existing and future development in the surrounding area.
BE IT FURTHER RESOLVED that the Planning Commission does hereby recommend that the
City Council approve the Stage 2 Planned Development Zoning in substantially the form attached as
Exhibit A for PA 03-058 Dublin Transit Center Site B-2 (Avalon Bay Communities).
PASSED, APPROVED AND ADOPTED this 9~h day of November 2004.
AYES:
NOES:
ABSENT:
ABSTAIN:
Planning Commission Chair
ATTEST:
Planning Manager
2
Stage 2 Development Plan
Stage 2 Planning Development Zoning District (PA 03-058)
Dublin Transit Center Site B-2
Avalon Bay Communities
(portion of APN 986-0001-011-00)
This is a Stage 2 Development Plan pursuant to Chapter 8.32 of the Dublin Zoning
Ordinance for Dublin Transit Center Site B-2, located at the southwest corner of Dublin
Boulevard and Iron Horse Parkway. This Development Plan meets all of the requirements
for Stage 2 Planned Development review of the project.
This Development Plan includes Site, Architectural, Circulation, and other plans and exhibits
prepared by GGLO, dated October 25, 2004, and Landscape Plans prepared by The Guzzardo
Partnership Inc., dated October 25, 2004, referred to as Project Plans labeled as Attachment
to the December 7, 2004 City Council Agenda Statement, stamped approved and on file in the
Planning Department. The Planned Development District allows the flexibility needed to
encourage innovative development while ensuring that the goals, policies and action programs of
the General Plan, Eastern Dublin Specific Plan, and provisions of Section 8.32, Planning
Development Zoning District of the Zoning Ordinance are satisfied.
The Stage 2 Planned Development Zoning District Development Plan meets the requirements of
Section 8.32.040.B of the Zoning Ordinance and consists of the following:
1. Zoning
2. Permitted Uses
3. Conditional Uses
4. Temporary Uses
5. Accessory Uses
6. Dublin Zoning Ordinance -Applicable Requirements
7. Density & Affordability
8. Development Regulations
9. Parking/Garage and Loading
10. Site Plan and Architecture
11. Preliminary Landscape Plan
12. Compliance with Stage 2 Planned Development Plans
Stake 2 Planned Development Zoning_District Development Plan
1. Zoning
PD, Planned Development Zoning District. This is aHigh-Density Residential Zoning
District which provides for high- density residential uses and ancillary commercial.
2. Permitted Uses
Permitted uses shall be as adopted by Ordinance 21-02, the Dublin Transit Center Stage 1
Planned Development Zoning Development Plan (PA 00-013) and are as follows:
EXHIBIT A
PD, Planned Development Zoning District
PA 03-0~8 Dublin Transit Center Site B-2
High-Density Residential Uses (Site B-2)
Accessory Structures and Uses (See below)
Ancillary Retail and Service Uses (See below)
Community Care Facility/Small
Home Occupations (per Chapter 8.64 of the Dublin Zoning Ordinance)
Multi-Family Dwelling
Parking Garage
Private Recreation Facility (for homeowner's association and/or tenant's use)
Small Family Daycare/Home
Eating Drinkin;; and Entertainment Establishments including, but not limited to:
Bagel Shop
Cafe
Coffee House
Delicatessen
Ice Cream/Yogurt
Micro-Brewery
Outdoor Seating
Restaurant (serving alcohol permitted, no drive-thru's allowed)
Theater -Indoor (dinner, movie, live play, etc.)
Local-Serving Retail Uses including, but not limited to:
Art Gallery/Supply Store
Auto Parts
Bakery
Bicycle Shop
Book Store
Clothing Store
Computers/Electronic Equipment
Drug Store
Florist/Plant Shop
Gift Shop
Hardware Hobby Shop
Home Appliances
Jewelry Store
Liquor Store
Music Store
Newspapers and Magazines
Paint, Glass and Wallpaper Store
Parking Lot/Garage -Commercial
Party Supplies
Pet Store and Supplies
Photographic Supply Store
Picture Framing Shop
Shoe Store
Specialty Food Store/Grocery/Supermarket -including meat, fish, wine, candy, health
food, etc.
2
PU, Planned Development Zoning District
PA 03-058 Dublin Transit Center Site B-2
Local-Serving Retail Uses including, but not limited to (continued):
Specialty Goods -including cooking supplies, housewares, linen, window coverings,
chinalglassware, etc.
Sporting Goods
Stationary/Office Supplies
Toy Store
Variety Store
Video Store
Local Serving Service Uses including, but not limited to:
Automatic Teller Machines (ATM)
Bank, Savings and Loan, and other financial institutions
Barber/Beauty Shop/Nail Salon
Copying and Printing
Dry Cleaner (no plant on premises)
Laundromat
Locksmith
Medical Clinic
Photographic Studio
Professional Offices, including: accounting, architectural, dental, engineering, legal,
medical, optometry, etc.
Photographic Studio
Real Estate/Title Office
Shoe Repair
Tailor
Travel Agency
Watch and Clock Repair
3. Conditional Uses
Conditional uses shall be as adopted by Ordinance 21-02, the Dublin Transit Center Stage
Planned Development Zoning Development Plan (PA 00-013) and are as follows:
Conditional Uses (the following would need to be approved by the Planning Commission):
Bar
Community Care Facility/Large
Day Care Center
Hospital/Medical Center
Nightclub
Religious Facility
School/Private
PD. Planned Development Zoning District
PA 03-058 Dublin Transit Center Site B-2
4. Temporary Uses
Temporary uses shall be as adopted by Ordinance 21-02, the Dublin Transit Center Stage 1
Planned Development Zoning Development Plan (PA 00-013) and are as follows:
Temporar~_
Sales Office/Model Home Complex/Rental Office
Temporary Construction Trailer
5. Accessory Uses
Accessory uses shall be as adopted by Ordinance 21-02, the Dublin Transit Center Stage 1
Planned Development Zoning Development Plan (PA 00-013) and the Dublin Zoning
Ordinance.
6. Dublin Zoning Ordinance -Applicable Requirements
Except as specifically modified by the provisions of this PD, Planned Development Zoning
District Development Plan, all applicable general requirements and procedures of the Dublin
Zoning Ordinance shall be applied to the land uses designated in this PD, Planned
Development Zoning District Development Plan.
7. Density & Affordability
Site Area: f3.57 acres (net)
Density: 70 dwelling units per acre (net)
as distributed within Dublin Transit Center Site B
Number of Units: 305 dwelling units
Unit Types: Studio: 20 units
Apartment/Flat: 249 units
Townhouse (walk-up): 36 units
Apartment Type Apartment Plan No. of
Units Unit size
(nets uare foota e Bathrooms
Studio Flat S1, S2 & S3 20 522 sf-644 sf 1
1 Bedroom Flat Al, AH1S, A53, A53.1,
A53.2, A55.1 & A55.2 121 681 sf- 835 sf 1
1 Bedroom Flat + den A2 2 877 sf 1
2 Bedroom Flat B2, B2.1, B2.2, B2.3,
B2.5, B2.6, B3 & B4 112 1,048 sf- 1,315 sf 2
3 Bedroom Flat C2.1, C2.2, C2.3 & C3 14 1,048 sf- 1,471 sf 2 or2.5
1 Bedroom Townhouse TH1, TH1.2 & TH2 12 877 sf- 1,364 sf 1.5
2 Bedroom Townhouse TH2.1 14 1,182 sf 2.5
3 Bedroom Townhouse TH7.1 & TH7.2 10 1,655 sf- 1,847 sf 3
Total: 305
Note: All units are equipped to accommodate a washer and dryer.
4
PD, Planned Development Zoning District
PA 03-Oi8 Dublin Transit Center Si[e B-2
iT.,.+ Affnrrlohility•
10% re wired ~ Studio 1 Bedroom 2 Bedrooms 3 Bedrooms Total
Moderate 2 units 13 units 12 units 3 units 30 units
80% or 120%
Note: The location of each attordable umt >s to be determ>nea by ~:ommumty lievetopment
Director who may designate this task to the Housing Specialist.
8. Development Regulations
Unless otherwise stated below, all development regulations in this Stage 2 Planned
Development Zoning District are subject to the requirements of the R-M and comparable
Commercial Zoning Districts.
_Develo ment Standard Multi-Famil Resid`entiaVAncilla Commercial
Lot Area: +3.57 acres (net)
Lot Dimensions: irregularly shaped at its widest oint
Lot Width: 157 feet along Dublin Boulevard
Lot Depth: 499 feet along Iron Horse Parkway
Setbacks: 15 - 40 feet (varies) along Dublin Boulevard
none re wired along Iron Horse Parkway
90.5 feet from the center line
of the Villa e Green
none required along north-sotrth
driveway
Hei ht Limits:
Residential/Commercial
Structure 5 stories over parking
62 feet - 5 inches
highest on south side
Parking Structure 5 '/2 stories
6 levels above half a level of
subterranean parking
Re wired Parkin 1.5 spaces er dwelling unit
(see discussion) 3 spaces er 1,000 sf of commercial use
Residential 458 spaces
Commercial 47 spaces
Total Parking re wired 505 s aces
Lot Covera e: 72%
9. Parking/Garage and Loading
A total of 543 parking stalls, either in the parking structure or on the street will be provided
with the project. The parking structure will be able to accommodate 506 spaces. Primary
access to the parking structure will be located from Iron Horse Parkway on the east side of
the project. A secondary vehicular entrance/exit available from north-south driveway located
between Sites B-1 and B-2 (west side of the project site). The additional 37 spaces will be
provided as parallel parking along the surrounding streets -Iron Horse Parkway to the east,
the north-south driveway to the west, and the street abutting the Village Green to the south.
5
PD. Planned Development Zoning District
PA 03-Oi8 Dublin Transit Center Site B-2
Based on recommendations from a parking analysis conducted for the project (see Omni-
Means dated January 1, 2003), the amount of ground level commercial parking and
residential guest parking will vary during the peak hours of the day. Therefore, a shared
parking program will be employed which results in varying percentages and the
redesignation of spaces throughout the day and evening for commercial customers and
residential guests. The standards are described as follows:
Residential Parkin
• All Residential units will be assigned at least one space in the parking structure.
• Residential "second-assigned spaces" will be assigned to the upper levels of the
parking structure.
• Sixty-five ground level and on-street spaces will be designated as shared parking with
the retail uses between lam and 12am. After 6 p.m., all ground floor parking within
the structure will be designated for residential guest parking.
Commercial Parking/Loading
• During the hours of 7 a.m. and 6 p.m., commercial customer parking will be located
on the surrounding streets.
• Nine of the 47 ground floor spaces in the parking structure will be designated as
employee parking with a time limit beyond 2 hours. If additional employee parking
is necessary (exceeding the 9 designated spaces), the project management will issue
controlled parking permits allowing employees to park for longer than 2 hours in any
of the public spaces located in the guest parking area of the structure, on Iron Horse
Parkway, or along the Village Green.
• Two street side parallel parking spaces on Iron Horse Parkway will be designated as a
commercial load zone between the hours of 7 a.m. and 9 a.m.
Security
• For security purposes, the parking structure gate on Iron Horse Parkway will open to
the public at 7 a.m. and close when the last retailer/business closes (time to be
determined based on tenants).
• The parking structure gate on the north-south driveway will open to the public at 7
a.m. and close at 12 a.m. However, overnight residential guest parking will be
permitted.
• Residents, Police, and Fire Department will have 24-hour access to the parking
garage.
Parking/Garage and Loading shall be provided in accordance with the Dublin Zoning
Ordinance standards and regulations, except as stated herein and as shown otherwise on the
plans and exhibits prepared by GGLO, dated received October 13, 2004 or August 23, 2004,
and Landscape Plans prepared by The Guzzardo Partnership Inc., dated October 13, 2004 or
16 August 2004. referred to as Project Plans labeled Exhibit A to the December 9, 2004 CitX
Council. Staff Report, stamped approved and on file in the Planning Department. The
minimum number of parking spaces shall be provided in accordance with Section 8 above.
6
PD. Planned Development Zoning District
PA 03-0~8 Dublin Transit Center Site B-2
10. Site Plan and Architecture
This Development Plan applies to approximately X3.57 net acres on the southwest corner of
Dublin Boulevard and Iron Horse Parkway. The site slopes approximately 5 feet from north
to south. However, all residential finish floors will be at the same elevation throughout the
building. The project is comprised of residential uses with ancillary or neighborhood-serving
commercial uses:
Residential: A total of 305 residential apartments would be built within a 5-story
structure. So as to prevent the parking structure from becoming a focal element, the
building sections are linked together architecturally to wrap the six levels of structured
parking. A 4-story row of 10 townhouses faces the Village Green at the south end of the
project. Exterior decks along the rear portion of these units overlook one of two common
area landscaped exterior recreational courtyards.
The site layout provides for 2 large courtyards enclosed on a114 sides by the residential
units and open to the sky. The northerly courtyard serves as the front yard to the open
patio spaces as well as opportunities for recreation. It includes an outdoor "cucina" or
barbecue area, an exterior Bocce Ball court, and two landscaped spaces with
opportunities for passive activities. The southerly courtyard includes the pool, spa, and
connections to the fitness center and clubhouse for exclusive use by the residents.
Both courtyards include shrub planting for screening and framing of architectural
elements and trees to provide a human scale. Attached to the parking structure and facing
one of the courtyards, the main building lobby, pool courtyard, and enclosed residential
recreational spaces (clubhouse and fitness area) would be accessed from a ground level
entrance portal along Iron Horse Parkway. Pedestrian access is provided via portals on
all sides of the building.
With the exception of the Dublin Boulevard frontage, ground level units along the
building perimeter will be provided with stoop entries elevated from 1 to 5 feet above the
public way and tied directly to the sidewalk. They would be screened from the public
way with landscaping or set back and separated from the public way by front courtyards.
The units facing the courtyard with the pool will be elevated approximately 2'-6" feet
above the courtyard to create an effective buffer between those uses. Courtyards with
passive recreational opportunities will be located approximately 6" to 1'-0" below the
residential finish floor elevations. All of the units will have balconies, decks, or patios.
Ancillary Commercial: Approximately 15,389 square feet of ancillary, neighborhood-
serving commercial uses are allowed for development at the ground level along Iron
Horse Parkway on the east side of the project. This space will include the leasing office
for the residential portion of the project. Residents and guests will have access to the
leasing office from either the public way, from the pool courtyard, or from the ground-
level parking garage. Access to the retail areas will be from the public way, or from the
ground-level parking garage.
Parking Structure: A six-level parking structure will be located in the center of the
project and wrapped by the residential units so that it is hidden on all four sides. Half of
the ground level will be at grade at one end of the project and subterranean at the other
end. The sixth level will be roof deck parking with railings at car height and pre-
7
PD, Planned Development Zoning District
PA 03-058 Dublin 'Cransit Center Site B-2
fabricated car ports. Residents will have direct access to the parking structure from
residential corridors at levels 1 through 5 of the building. The corridor adjacent to the
parking garage will be separated from the parking garage by around-attenuating fire
wall. Vehicular access to the parking structure will be from Iron Horse Parkway and the
north-south driveway along the westerly side of the site. Spaces assigned for guest and
commercial use will be subject to a shared parking arrangement discussed below.
The site layout and architectural design of this project will be consistent with the urban
lifestyle and character of mixed uses planned for the Dublin Transit Center. The detailing of
the retail storefronts, townhouse stoops, and urban landscape will accentuate enhanced
pedestrian circulation and scale of this area. Attention has been paid to the massing of the
building to reflect the image depicted in conceptual sketches found in the Stage 1
Development Plan.
The architectural style is described by the project proponent as "Spanish Mission" with
detailing reflective of styles that are prevalent in the City of Dublin. Exterior articulation and
color palette area aimed at minimizing visual mass and scale. Roof lines are low-pitched hip
roofs with concrete mission tiles. This material also is used on canopy or shed roof covers
over townhouse stoops and some retail entrances. Exterior materials include cast stone
veneer along the base and entries. Scored plaster and painted stucco finishes are used on the
upper stories.
The project has two main entries and several secondary entries. An entry courtyard marked
by a pedestrian portal and low staircase is located on the Dublin Boulevard frontage. The
main lobby entrance is accessed from Iron Horse Parkway. Secondary entrance portals
leading to internal courtyards, corridors and/or elevator and stair platforms are positioned on
other sides or ends of the building. As with the primary entrance portals, the secondary
entrance portals would be demarcated by archways of cast stone veneer clearly visible from
public way.
See attached plans and building elevations prepared by GGLO, labeled Exhibit A dated
received October 13, 2004 or August 23, 2004, and Landscape Plans prepared by The
Guzzardo Partnership Inc., dated October 13, 2004 or 16 August 2004, referred to as Project
Plans labeled Exhibit A to the December 9, 2Q4~ City Council Staff Report, stamped
approved and on file in the Planning Department. Any modifications to the project shall be
substantially consistent with these plans and of equal or superior materials and design
quality.
11. Preliminary Landscape Plan
The landscape plan reinforces the urban design intent by creating a pedestrian oriented
perimeter with generous sidewalks, street tree planting, and enhanced paving patterns at key
elements. Foreground planting frames the front entry stoops and anchors the privacy wall
along Dublin Boulevard. This wall is reflected in the portal walls on the north-south
driveway. The European plaza concept is realized on the north-south driveway with the
inclusion of special paving patterns and pedestrian scaled street trees and pole lights. The
Village Green will be developed as part of this project in response to the need for public open
space as stated in the Stage 1 Development Plan.
8
PD. Planned Development Zoning District
PA 03-058 Dublin Transit Center Site B-2
The Village Green provides open space to serve the Transit Center community with room for
active play, gardens, and seating areas. The Village Green is linked to the north-south
driveway and Iron Horse Parkway via pedestrian paving patterns and plazas flanked by
accent trees on each end. The edge of the Village Green is delineated with sidewalks and
street trees around the perimeter.
See plans (Sheets L-1 through L-4) prepared by The Guzzardo Partnership Inc., dated
received October ?, 2004' referred to as Project Plans labeled Exhibit A to the December 7,
2004 City Council Staff Report, stamped approved and on file in the Planning Department.
12. Compliance with Stage 2 Planned Development Plans
The project shall substantially comply with the project plans and exhibits prepared by
GGLO, dated and details received October ?, 2004, and Landscape Plans prepared by The
Guzzardo Partnership Inc., dated October `~, 2004, referred to as Project Plans labeled Exhibit
A to the December 7, 2004 City Council Staff Report, stamped approved and on file in the
Planning Department. Such project plans are incorporated by reference. Any modifications
to the project shall be substantially consistent with these plans and of equal or superior
materials and design quality.
9