HomeMy WebLinkAbout4.06 SidewalkRepairAI01-02CITY CLERK File # E11G1d01-&& AGENDA STATEMENT CITY COUNCIL MEETING DATE: July 3, 2001 SUBJECT: Acceptance of Work - Contract No. 01-02, 2000-2001 Annual Sidewalk Safety Repair Program and Curb Modifications at Amador Valley Boulevard/Starward Drive Report Prepared by: Lee S. Thompson, Public Works Director ATTACHMENTS: None RECOMMENDATION: Accept improvements under Contract No. 01-02 and authorize the release of retention after 35 days if there are no subcontractor claims FINANCIAL STATEMENT: Budget Actual Sidewalk Safety Repair: Improvements (Remove & Replace) $46,850 $44,458 Curb Ramps (CDBG) $11,614 $11,614 Subtotal: $58,464 $56,072 AVB/Starward Drive Improvements: $20,984 $19,020 TOTAL: $79,448 $75,092 The Sidewalk Safety Repair is funded through the General Fund (001). Curb ramps are funded through a Community Development Block Grant (209). The Amador Valley Boulevard/Starward Drive improvements are funded through Gas Tax (206). DESCRIPTION: On March 20, 2001, the City Council awarded Contract No. 01-02, 2000-2001 Annual Sidewalk Safety Repair Program and Curb Modifications at Amador Valley Boulevard/Starward Drive, to Vanguard Construction. The Annual Sidewalk Safety Repair Program repaired sidewalk locations that are offset 3/4" or more and posed potential tripping hazards. This contract specified removal and replacement of existing sidewalk, curb and gutter. This year's project included the construction of 14 curb ramps at various street corners. An additional portion of this contract modified the curb and striping at the intersection of Amador Valley Boulevard and Starward Drive. ------------------------------------------------------------------------- COPIES TO: Vanguard Construction C4- ITEM NO. sue, g:\mntcproj\sidewalk\AS acceptance �y, (� Staff has reviewed the work on the project and has determined that the work is complete. Staff recommends that the City Council accept the improvements under Contract No. 01-02 and authorize the release of retention after 35 days if there are no subcontractor claims. Page 2