Loading...
HomeMy WebLinkAboutItem 4.7 - 3316 Civic Center HVAC & Roof Design Builder Agr (2)STAFF REPORT CITY COUNCIL DATE: July 21, 2020 TO: Honorable Mayor and City Councilmembers FROM: Linda Smith, City Manager SUBJECT: Award of Design/Builder Agreement to ADC Construction Management, Inc. for the Civic Center HVAC and Roof Replacement Project, Project No. GI0119 Prepared by: Michael Boitnott, Capital Improvement Program Manager EXECUTIVE SUMMARY: The City Council will consider awarding a Design/Builder Agreement to ADC Construction Management, Inc., for the Civic Center HVAC and Roof Replacement project, CIP No. GI0119. The base project scope includes the replacement of the flat roof assembly, roof mounted HVAC equipment, modifications to the existing HVAC duct system, HVAC controls, minor structural upgrades, fire alarm panel and ancillary devices, and the installation of new ethernet data cable drops. The City Council will also consider approving a budget change to increase project funding. STAFF RECOMMENDATION: Adopt the Resolution Awarding a Design/Builder Agreement to ADC Construction Management, Inc., for the Civic Center HVAC and Roof Replacement Project, CIP No. GI0119, and approve the budget change. FINANCIAL IMPACT: As approved in the 2020-2025 Capital Improvement Program (CIP), the total budget for the Civic Center HVAC and Roof Replacement (CIP No. GI0119) is $5,443,487. The project is split between HVAC and roof improvements to the east side of the Civic Center ($3,612,634) and similar improvements at the west side of the Civic Center, the site of the future Cultural Arts Center ($1,830,853). The budget and cost of the latter will be shifted to the Cultural Arts Center Project budget in the CIP. The “best value proposal” (discussed later in the report) received from a pre-qualified design-build entity for the project was $3,693,895. Staff recommends the inclusion of one add-alternate item for $142,936, for a total Design/Builder Agreement amount of $3,836,831. Staff also recommends including a contingency in the amount of $500,000, which is approximately 13% of the recommended Agreement amount, bringing the total potential design/build cost to $4,336,831. Page 1 of 5 Page 2 of 5 In addition to the Agreement costs, the project budget includes expenditures for soft costs, which include staff time, consultant costs, permits, fees, and other miscellaneous costs. Award of the Agreement would require a budget increase of $1,387,366. The available project funds and proposed budget adjustment are summarized as follows: Existing Funding Sources General Fund $2,000,000 IT Fund $200,000 Internal Services Fund - Facilities Replacement $3,243,487 Total Funding $5,443,487 Budget Shift to the Cultural Arts Center Project ($1,830,853) Current Project Budget (Revised) $3,612,634 Project Costs Base Proposal $3,693,895 Add Alternate #1 - Replacement of Window Film $142,936 Contingency $500,000 Soft Costs $663,169 Total Costs $5,000,000 Funding Shortfall ($1,387,366) Additional Funding Sources Internal Services Fund - Facilities Replacement $887,366 General Fund Non-Streets CIP Reserve $500,000 Total Additional Funding $1,387,366 DESCRIPTION: The 2020-2025 Capital Improvement Program (CIP) includes the Civic Center HVAC and Roof Replacement project, CIP No. GI0119 (Project). The Project is a multiphase and multiyear project to improve the Civic Center, including the east wing (administration wing) and the future Cultural Arts Center. The first phase of the Project provides for the design and construction of the flat roof assembly replacement, interior parapet wall weather proofing, seven roof mounted exhaust fans, and seven roof mounted HVAC units. The Project also includes a new fire alarm system, data drop locations, a multi-split system for the second floor Information Systems closet, new HVAC controls, installation of four-inch thick polyisocyanurate (polyiso) roof insulation, replacement of portions of dropped ceiling, and interior patch and paint work. In addition, to help combat against COVID-19 and other airborne pathogens, the Project includes: air filters with higher filtration rate (minimum efficiency reporting value (MERV) 14 filters versus the current MERV 10 filters), HVAC controls and economizers to allow up to 100% outside air during various heating and cooling settings, and ultraviolet Page 3 of 5 germicidal coil irradiation systems using UV-C lamps. These upgrades are recommended by various HVAC and mechanical engineering trade organizations to improve air quality within buildings. Design-Build Project Delivery There are several project delivery methods for an owner to consider when proceeding with a construction project. Each project delivery method has benefits and limitations depending upon several factors, including but not limited to, budget, construction type, schedule, and complexity. Most City of Dublin construction projects are delivered using a Design-Bid-Build delivery method, in which the City design team produces complete plans and specifications for the project, solicits bids from qualified contractors, and then awards a construction contract to the lowest responsive bidder. Design-Bid-Build is the traditional project delivery methods for public projects in the United States. For the Civic Center HVAC and Roof Replacement Project, Staff chose an alternative project delivery method, Design-Build in order to fast-track the design and construction and to take advantage of the combined experience of the builder and designer to deliver a project that meets performance standards versus prescriptive specifications of a Design-Bid-Build project. Design-Build projects are awarded based on the owner’s determination of best value, rather than lowest bid. The Design-Build method allows for a single point of accountability and eliminates change orders that are the result of deficiencies in or incompleteness of the design. Some other Design-Build advantages include opportunities for innovation, concurrent design and construction which reduces schedule duration, and the builder and designer benefiting from expanded site investigation to tailor the design to fit the existing conditions. Some limitations or disadvantages of Design-Build are that the owner must be willing to allow the Design-Build team handle design details and the o wner must make sure the project performance standards are thorough to avoid costs to reconcile inconsistent standards. On March 6, 2020, a Request for Qualifications of Design -Build Entities was released. Five qualification packages were received by April 16, 2020. Staff reviewed the qualifications packages and identified four of the five firms as qualified to submit proposals for the design and construction of the Project. On June 2, 2020 the City issued the Request for Proposals from Pre-qualified Design-Build Entities for the Project. A total of three proposals were received by July 1, 2020. The three proposals received were evaluated and ranked as follows based on best value: 1. ADC Construction Management, Inc. 2. Saarman Construction LTD. 3. Matrix HG, Inc. The best value proposal was provided by ADC Construction Management, Inc. at a base proposal cost of $3,693,895. Included in the Request for Proposals were five bid alternative items in addition to the base proposal: : Page 4 of 5 1. Window Film Replacement 2. Additional Cat6e Data Drop Installation 3. Variable Air Volume (VAV) Boxes with Electric Heat and Controls 4. New Rectangular Light Fixtures 5. New Round Light Fixtures At this time, Staff recommends including add alternative item 1, priced at $142,936, for the removal and replacement of the exterior window film. The new window film will provide for the reduction of solar heat gain through the glazing, block 99% of UV light, and allow approximately 70% visible light transmittance. The existing window film is at the end of its useful life and is showing signs of wear in the higher traffic areas. The inclusion of the window film at this time allows for the HVAC system, heating , and cooling loads to be accounted for, to take advantage of the added energy properties of the composite glazing and new window film. The combination of the window film and properly sized HVAC zones will result in long term energy savings. The addition of add alternative item 1 brings the total design/builder agreement to $3,836,831. To facilitate the approval of contract change orders and to avoid construction delay, it is recommended that the City Manager or designee be authorized to approve change orders up to a contingency amount of $500,000, as included in the attached Resolution. Comparison with Original Estimate The cost of the proposed work is $1,387,366 higher than the original budget for the Project. One component of the cost increase relates to impacts from the COVID-19 pandemic. The Design-Build Entity is required to comply with new County and State Health Orders, which require additional trained personnel to monitor the construction site and strict cleaning of the work site and equipment, resulting in reduced production during a standard work shift. In addition, the supply chain for materials and raw products has been disrupted and suppliers are having difficulty securing products , resulting in increased prices as demand increases. With the increased cost of acquiring the raw materials, the manufacturers and associated supply chains are also incurring additional costs to market in order to comply with the various health and safety regulations, which lead to those costs being passed onto the consumer. Finally, the design of the HVAC system was upgraded during the proposal phase to provide for better air filtration, more outside air with controls and added set points, and the addition of UV-C germicidal coil irradiation systems, all of which resulted in added costs to the project. Deferring the replacement of the HVAC system and roof in hopes of obtaining a reduced project cost is not advisable. The roof is beyond its useful life and the building has experienced minor leaks, which if left unchecked or unnoticed could result in more costly repairs in the future. Similarly, the HVAC system is at the end of its useful life and considerable costs are expended annually to keep the system functional. Additionally, with the installation of the new HVAC system and roof, the operating costs will be reduced and the energy savings at the Civic Center will be realized sooner. To account for the increased costs, Staff recommends approval of a Budget Change of $1,387,366 from the following sources: Page 5 of 5 1. Internal Services Fund - Facilities Replacement Payment - $887,366 2. General Fund Reserve for Non-Streets Capital Improvement Program - $500,000 (current balance is $2.5 million) Staff expects the project to begin in August 2020 and anticipates it to be completed in April 2021. This project is exempt under Section 15301 (Existing Facilities) of the CEQA Guidelines. STRATEGIC PLAN INITIATIVE: None. NOTICING REQUIREMENTS/PUBLIC OUTREACH: A copy of this staff report was sent to ADC Construction Management, Inc. ATTACHMENTS: 1. Resolution Approving a Design/Builder Agreement to ADC Construction Management, Inc. for the Civic Center HVAC and Roof Replacement, CIP No. GI0119 2. GI0119 - Civic Center HVAC and Roof Replacement 3. Budget Change Form ATTACHMENT 1 RESOLUTION NO. XX- 20 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN * * * * * * * * * AWARDING A DESIGN/BUILDER AGREEMENT TO ADC CONSTRUCTION MANAGEMENT, INC. FOR THE CIVIC CENTER HVAC AND ROOF REPLACEMENT, CIP NO. GI0119 WHEREAS, the City of Dublin did, on March 6, 2020 issued a request for qualifications of Design-Build Entities for the Civic Center HVAC and Roof Replacement, CIP No. GI0119 (“Project”). The project includes the replacement of the flat roof assembly, roof mounted HVAC equipment, modifications to the existing HVAC duct system, HVAC controls, minor structural upgrades, fire alarm panel and ancillary devices, and the installation of 168 Cat6e ethernet data cable drops within the City Hall building of the Civic Center; and WHEREAS, the City of Dublin did, on July 1, 2020, receive Proposals from the Pre- qualified Design-Build Entities for the Project; and WHEREAS, the City of Dublin evaluated the three Proposals received for the Project and determined the Best Value Proposal was submitted by ADC Construction Management, Inc.; and NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin hereby award a Designer/Builder Agreement to ADC Construction Management, Inc. for the Civic Center HVAC and Roof Replacement Project, Project No. GI0119, for the base proposal plus add alternate 1, and a five-hundred thousand dollar ($500,000) contingency, for a total proposal of four-million three-hundred thirty-six thousand eight hundred thirty-one dollars ($4,336,831), the particulars of which proposal are on file in the Office of the Public Works Director. BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby authorize the City Manager or her designee to execute the Design/Builder Agreement with ADC Construction Management, Inc. and to approve Contract Change Orders based on the appropriated funds designated for the Project up to the contingency amount of five-hundred thousand dollars ($500,000). BE IT FURTHER RESOLVED that the City Manager or designee is authorized to execute the Designer/Builder Agreement with ADC Construction Management, Inc. PASSED, APPROVED AND ADOPTED this 21st day of July 2020, by the following vote: AYES: NOES: ABSENT: ABSTAIN: ATTACHMENT 1 ________________________________________ Mayor ATTEST: _____________________________ City Clerk Number GI0119ProgramGENERALESTIMATED COSTSPRIOR YEARS 2019-2020 BUDGET2020-2021 2021-2022 2022-2023 2023-2024 2024-2025 FUTURE YEARS TOTALS9100 $151 $88,949 $54,280$143,3809200$440,900 $347,000$787,9009400$2,465,000 $200,000 $1,137,358$3,802,3589500$5,000 $5,000$10,0009600$700,000$700,000$151 $3,699,849 $200,000 $1,543,638$5,443,638FUNDING SOURCEPRIOR YEARS 2019-2020 BUDGET2020-2021 2021-2022 2022-2023 2023-2024 2024-2025 FUTURE YEARS TOTALS1001$2,000,000$2,000,0006605$200,000$200,0006205 $151 $1,699,849 $1,543,638$3,243,638$151 $3,699,849 $200,000 $1,543,638$5,443,638ANNUAL OPERATING IMPACTMiscellaneousEquipment2020-2025 CAPITAL IMPROVEMENT PROGRAMCIVIC CENTER HVAC AND ROOF REPLACEMENTTOTALIT FundTOTALGeneral FundInternal Service Fund - Facilities ReplacementSalaries & BenefitsContract ServicesImprovementsPROJECT DESCRIPTIONThis project provides for the design and replacement of the heating, ventilation, and air conditioning (HVAC) system and controls, roof replacement, associated building modifications, and code compliance upgrades for City Hall and the Cultural Arts Center within the Civic Center complex. The existing HVAC and roof systems are at the end of their useful life and are due for replacement. A new HVAC system and controls will be more energy efficient and have a greater ability to be adjusted. With the roof replace, the project will also upgrade communications infrastructure for new data connections to offices, workstations, and conference rooms. The project will be completed in several phases to minimize disruption to the public and to Staff working within the buildings. This project is funded by $2 million in a General Fund Reserve set aside for this purpose in addition to the Internal Service Fund for Facilities Replacement.ANNUAL OPERATING IMPACT: NoneMANAGING DEPARTMENT: Public Works Budget Change Reference #: From Un-Appropriated Reserves X Budget Transfer Between Funds From Designated Reserves x Other Account Amount Account Amount GI0119.9400.9401 (Improvements - Not Building)$1,257,366 GI0119.9200.9201 (Contract Services General)$130,000 3300.9301.49999 (Transfer In)$1,387,366 GI0119.6205 (6205.9301.89101) - ISF Fund - Facilities Transfer Out $887,366 GI0119.1001 (1001.9301.89101) - General Fund Transfer Out $500,000 7/21/2020 Posted By:Date: As Presented at the City Council Meeting **********Finance Use Only********** CITY OF DUBLIN Higher than anticipated project costs based on solicitation of proposals from prequalified design-build entities, added costs for compliance with County Health Orders during construction, and imacts to the supply and manifacturing chains due to the COVID- 19 pandemic. REASON FOR BUDGET CHANGE FISCAL YEAR 2020-21 BUDGET CHANGE FORM City Council's Approval Required EXP: HVAC and Roof Replacement (GI0119) ATTACHMENT 3