HomeMy WebLinkAboutItem 7.2 VillagePrkwaySidewalk CITY CLERK
File#. AIoI-J JJoI
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: March 16, 2004
SUBJECT: Village Parkway Sidewalk Widening and
Lighting Improvements - Design Alternatives
Report Prepared by: Melissa Morton, Public Works Director
ATTACHMENTS: 1) Project Site Map
2) Sidewalk Alternatives
3) Lighting Detail
4) Project photos
RECOMMENDATION: 1) Approve replacement of the sidewalk, and if approved, seleCt
a sidewalk alternative
· 2) Approve recommended lighting proposal
FINANCIAL STATEMENT: Capital Cost:
All preliminary budget projections were based on the assumption
that the City would receive a Housing Incentives Program Grant.
The FY 2003-2004 budget for construction of the sidewalk and
lighting improvements is as follows:
Federal Housing Incentives Program Funds: $359,264
General Fund: $ 84,644
Total construction budget: $443,908
Preliminary construction cost estimates .are as follows:
Sidewalk Widening/Reconstruction: $389,620
Street Lighting: $327,750
Project Total: $717,370
Additional funds required: $273,462
The City was awarded a grant by the Metropolitan Transportation
Commission (MTC) of $1.306 million of Housing Incentive
Program (HIP) funds, which is subject to the construction of high
density housing in the proposed Dublin Transit Center. It is required
COPIES TO:
g:hniscproj~Downtown Streetscape Imps~S VPW Sidewalk Alternatives 10~)~""- ITEM NO. ~
L
that the high density housing project break ground by May 30, 2004,
in order to receive these funds.
Uncertain market conditions have impacted the timing of submittals
by the three residential developers now active in the Dublin Transit
Center project, and Staff will be requesting from the Metropolitan
Transportation Commission (MTC) a new deadline of August 2005
for the commencement of the Transit Center housing project. In
addition, Staff will request an extension for construction of
improvements to September 2005. Preliminary discussions with
MTC staff indicate an unwillingness to extend the deadlines for the
grant. The housing component of the funding deadline cannot be
met so the City is not likely to receive the HIP grant unless an
extension is granted. If MTC denies this extension request and/or
the new deadline is missed, the construction of the above projects
will have to be deferred or fimded from other sources, such as the
City's Downtown/Open Space General Fund Reserve.
The HIP funds are intended to be used for the Village Parkway
sidewalk/lighting project, as well as the Gateway Monument at the
northeast comer of Dublin Boulevard and Village Parkway and the
Gateway Archway over St. Patrick Way. Based on the latest
construction cost estimates, an additional $273,462 of federal funds
would need to be allocated to the sidewalk/lighting project to make
it fully funded. If the City receives federal funds, this will result in a
shortfall in grant funding for the remaining Downtown Improvement
projects.
There are three alternatives for the sidewalk widening/reconstruction
which are discussed below and all of their preliminary cost estimates
are the same. Consequently, the choice of a sidewalk alternative is
an aesthetic choice, not a budgetary one.
Operating Cost:
The lighting portion of the project will cost the City-Wide Lighting
District the following annual costs over the existing baseline lighting
provided on Village Parkway:
1. Power cost: $11,800
2. Maintenance cost: $ 5,330
3. Replacement cost: $ 5,800
Total: $22,930
This will result in a potential increase of individual property owner's
street lighting assessment up to approximately $1.74 per household.
For commercial properties the increase could be up to $1.74 x 5.5 x
acreage of the property.
Page2 ~~-
DESCRIPTION: In November 1999, the City Council directed Staff to prepare three
Specific Plans for various portions of the downtown area of Dublin in order to guide the development and
revitalization of the West Dublin BART, Downtown Core and Village Parkway areas. The Specific Plans
were adopted by the City Council on December 19, 2000.
The Dublin Streetscape Implementation Plan described the area of Village Parkway between Dublin
Boulevard and Amador Valley Boulevard as a "unique business enclave distinct from the downtown" due
to its location on the east side of 1-680. The existing streetscape was described as "a missed opportunity
for identity and a quality statement." As part of the implementation of the Specific Plan for Village
Parkway, gateway monuments, sidewalk widening from 4.5 feet to 8 feet, and the installation of
decorative streetlights were proposed to provide continuity and unifying elements in order to establish a
positive image in the Downtown area.
As part of the approval of the Capital Improvement Program and budget for Fiscal Year 2003-2004,
the City Council directed Staff to complete the sidewalk improvements and new streetlights on Village
Parkway between Dublin Boulevard and Amador Valley Boulevard. The design of the sidewalk widening
and lighting for Village Parkway was begun by the City's consultant, Permco Engineering, under an
existing on-call contract with the City.
Public Outreach
Every business property owner within the project limits were informed of the proposed construction by
letter. In addition, photographs were provided (see Attachment 4) of each property owner's frontage
showing the extent of the sidewalk widening and indicating which existing improvements (utility boxes,
trees, etc.) would remain. The City was contacted by three of the property owners who expressed
concern over existing improvements, primarily landscaping and irrigation. The property owners were
assured that any irrigation lines affected by the work would be relocated and that, prior to commencing
construction, the City would meet with each property owner to locate and mark the existing items
requiring relocation.
The property owners also expressed concern about being kept informed of the progress of the work and
minimizing the impact on the business activities of the lessees. Staff assured the owners that notices will
be provided as the construction schedule is finned up. In addition, the City will take steps to minimize the
impacts on the businesses by limiting the work area to one side of one block at a time and constructing
driveways at night in order to minimize impacts to vehicular access during the day.
In addition to the property owners, the City's consultant met with the proprietors of virtually every
business on Village Parkway to review the proposed work, along with the potential short-term impacts of
the construction. The business owners were concerned about the construction impacts of the project on
trade. Staff assured these business owners that the City would take every possible measure to minimize
any inconveniences during construction.
Sidewalk Widening
The original intent of this portion of the work was to widen the existing sidewalk from 4.5 feet to 8 feet.
This widening would locate the back of sidewalk at the street right-of-way line and would not require the
acquisition of additional right-of-way.
Page 3c~ ~'~
After much consideration, Staff is recommending that the existing sidewalk be removed in its entirety and
a new 8-foot sidewalk be installed for the following reasons:
1) The existing sidewalk is generally in poor condition, with numerous cracks and areas
of heaving due to the proximity of existing trees.
2) Widening the sidewalk by adding a small strip of concrete to the back of the old
sidewalk will not be aesthetically pleasing and will not project the desired
"DOwntown'' image.
3) The existing sidewalk runs through numerous sloped driveway approaches along the
street. This is not considered an accessible path of travel under the Americans with
Disabilities Act (ADA). The driveway approaches will have to be removed and
reconstructed to provide a 4-foot-wide accessible path around each driveway.
4) Removal of the existing sidewalk would allow the installation of most street lighting
conduits in the sidewalk area, rather than in the street, thereby reducing costs and
traffic impacts on Village Parkway.
The recommended replacement of the entire sidewalk offers the City the opportunity to construct a much
more inviting streetscape. In addition, Staff has reviewed oPPortunities to incorporate green building
practiCes. When incorporating fly ash into concrete, the set up times are longer, so concrete with recycled
content could not be used for the driveways into businesses. However, for sidewalk areas that Will be
limited to pedestrian traffic, Staff will incorporate the use of recycled materials into the specifications. If
the City Council approves of this recommendation, Staff has prepared three alternatives for the City
Council's consideration (please see Attachment #2.):
Alternative I
Plain concrete, broom finish, with 18" wide colored and scored bands. The scoring would match the
recently completed Village Parkway/Lewis Avenue intersection improvement and the suggested color for
all alternatives is Schofield "Coachella Sand". The color o£the newly paved bulb outs at the intersection
of Village Parkway and Lewis Avenue is "San Diego buff' and it would be stained to match the suggested
"Coachella Sand" color for consistency.
Alternative 2
Scored concrete to match the Village Parkway/Lewis Avenue intersection scoring, with 18" wide colored
bands with a salt finish. Also included is an 8" wide concrete band along the rear of sidewalk and around
tree wells.
Alternative 3
Plain concrete, either broom or salt finish, with 18" colored bands with stamped finish. Also included is
an 8" wide concrete band along the rear of sidewalk and around tree wells. The stamped finish could
either be: a) fishscale cobblestone pattern; b) random slate pattern; or c) diagonal slate tile pattern.
Street Lighting
The existing street lighting on Village Parkway is comprised of twin 100-watt, high pressure sodium
cobraheads mounted on poles approximately .178 feet apart in the median island. This lighting, which is
mainly for roadway illumination, provides only half of the desirable illumination in the sidewalk area, and
pedestrians are faced with dark zones that are not inviting for walking after dark. Illumination studies
were performed, both with and without the existing streetlights, using the Lumec luminaire previously
chosen by the City Council in the'Dublin Streetscape Implementation Plan (Attachment 3). The studies
Page 4 %~''-~
determined that in order to reach acceptable illumination and uniformity levels, the new luminaires would
need to be spaced at 195 feet with the existing lighting and 142 feet without.
While all of the above scenarios provide the required illumination levels and uniformity, the proposed
spacing makes the lighting strictly utilitarian and does not provide the ambiance necessary to attract
pedestrian traffic after dark. Therefore, in order to provide a pleasing streetscape, Staff recommends that
the streetlights be spaced every 100 feet and the upper lanterns and pedestrian luminaries be lighted with
100-watt and 70- watt light bulbs respectively. The spacing of existing driveways along Village Parkway
tends to lend itself to a spacing of approximately 100 feet which will require a total of 34 poles (as
apposed to 24 in the 142-foot spacing). Staff further recommends that the existing cobrahead median
lighting be removed as the proposed 100-foot spacing will significantly increase the illumination levels on
both the roadway and sidewalk areas.
RECOMMENDATION:
Staff recommends that the City Council: 1) approve replacement of the sidewalk, and if approved, select
a sidewalk altemative; and 2) approve recommended lighting proposal.
,L~'I'IVA . [~
Z ~ ~
0
Z
~ -~
z
o
~ I ~0~
0
0
~ z
z
0
0
x
u.I ~
0'~
o~ I z$
c) ,'71,,
-~o8 .;.~
~ ~
EXISTING BRADFORD
EXISTING -
CURB &
GUTTER
i: 8":
4" AB BASE DECOMPOSED GRANITE
OF EXISTING SIDEWALK
4" THICK REINFORCED CONCRETE
CONCRETE: BROOM FINISH, UNCOLORED EDGE WHERE
OR PATTERENED BANDS WITH COLOR INDICATED
TYPICAL CROSS SECTION @ TREE
SCALE: 3/4" = 1 '-0"
SIDEWALK RENOVATION - ALT. 1,2 & 3
VILLAGE PARKWAY
CITY OF DUBLIN
DUBLIN, CALIFORNIA
ARBEGAST NEWTON & GRIFFITH - LANDSCAPE ARCHITECTS
1647 HOPKINS STREET, BERKELEY, CA, 94707
"~0~;.' .~;~;.~';~, ~,~,, PRESENTATION
Tek (45(3)430-7040
Fax: (450}430-1453
20'-11" Luminous Center ~- f--
FRONT VIEW SIDE VIEW
-Dublin Village Parkway
LMS