HomeMy WebLinkAboutItem 4.12 AccptWorkCon01-12 CITY CLERK AGENDA STATEMENT CITY COUNCIL MEETING DATE: April 20, 2004 SUBJECT: Acceptance of Work - Contract No. 01-12 Interstate 580/Tassaj ara Road Interchange Improvement Project Report Prepared by: Melissa Morton, Public V~orks Director ATTACHMENTS: 1) Change Order Summary together with Contract Change Orders 35, 38 and 39 2) Budget Change Form RECOMMENDATION: //1) Approve Contract Change Orders 35, 38 and 39  /7 ~ /~/ 2) Accept improvements under Contract No. 01-12, and approve release of retention after 35 days if there are no subcontractor claims ) Approve budget change in the amount of $55,630.14 FINANCIAL STATEMENT: DeSilva Gates Construction's total project cost is $8,075,598 which includes the cost increase of Change Orders 1 through 39 totaling $991,703 (Attachment 1). The breakdown of project costs is shown as follows: Budget Estimated Actual Construction $ 8,019,968 $ 8,075,598 Salary/Benefits $ 72,447 $ 72,447 Design/ProjectMgrnt. $ 1,891,615 $ 1,891,615 Construction Mgmt. $ 1,256,700 $ 1,256,700 Miscellaneous $ 15,675 $ 15,675 TOTAL: $11,256,405 $11,312,035 Several Eastern Dublin developers advanced a total of $12,935,691 for the design and construction of this project. It is anticipated that the remaining balance will be returned to the developers pursuant to the City's agreement with the developers upon reimbursement of federal and state grant funds exchanged with project funds. A final accounting of the project will be made and rebates returned to the developers as soon as the grant monies are reimbursed. COPIES TO: DeSilva Gates Construction g:hmiscproj\i-580/Tassajara\agst_accept [~) ~ ITEM NO. ~/~ DESCRIPTION: At its meeting of March 5, 2002, the Dublin City Council awarded Contract No. 01-12, Interstate 580/Tassajara Road Interchange Improvements project, to DeSilva Gates Construction, LP. The 1-580/Tassaj ara Road Interchange Improvement project included the following improvements: Demolished the existing two-lane northbound Tassajara Road overcrossing · Constructed a new three-lane northbound Tassajara Road overcrossing · Constructed an auxiliary lane along eastbound 1-580 from the eastbound Santa Rita Road on-ramp to the E1 Charro Road off-ramp · Widened the westbound 1-580 off-ramp from one lane to two lanes and provided a 400-meter (1,312- foot) auxiliary lane in advance of the exit · Widened the eastbound off-ramp to provide a second left-turn lane at the ramp terminus at the intersection of Santa Rita Road and Pimlico Drive · Lengthened the left-turn lane on southbound Tassajara Road approaching the Pimlico Drive intersection · Narrowed the existing median along westbound Pimlico Drive to provide a four-lane approach at the Santa Rita intersection · Reconstructed the westbound 1-580 loop on-ramp · Widened the diagonal westbound 1-580 on-ramp from one lane to two lanes · Modifications to existing traffic signals at the ramp intersections · Modifications to ramp metering, ramp entrance lighting, and intersection lighting The project was completed at a total cost of $8,075,598, which is $55,630 over the approved budget for the project. A total of 39 contract change orders in the amount of $991,703 were required to complete the project of which three change orders still require approval. These three change orders are as follows: 1. Change Order No. 35: In lieu of performing plant establishment work for 250 working days, the Contractor's plant establishment work will terminate on December 31, 2003, for a credit of $1,340.00. The remaining plant establishment work through September 30, 2004, will be performed by City of Dublin/MCE forces. 2. Change Order No. 38: Additional work to install a custom-made trash rack, install a metal beam guardrail on the westbound off ramp shoulder, additional street median island work, relocate electrolier foundations, median landscaping irrigation, relocate roadside sign, install rock slope protection, furnish mulch for landscaped area, and furnishing roadside panels~ all in the amount of $21,191.49. 3. Change Order No. 39: Additional work to modify drainage inlet, install pavement delineation, install delineation at all new metal beam guardrail, and relocate existing electrical conduit, all in the amount of $6,509.32. ~ Caltrans has accepted the project as complete except for the landscaping portion of the project, which will be reviewed by Caltrans after the termination of the plant establishment work in September 2004. Staff recommends that the City Council approve Contract Change Orders 35, 38, and 39, accept the improvements under Contract 01-12, and release of retention after 35 days if there are no subcontractor claims. Staff further recommends that the Council approve the budget change in the amount of $55,630.14. Page2 ~ ~t,~ CHANGE ORDER SUMMARY DATE: April 7, 2004 PROJECT NAME: 1-580/Tassajara Road Interchange Improvement ProJect CIP #: 96420 CONTRACT NO: 00-12' CONTRACTOR: De Silva Gates Construction PERCENT COMPLETED: 99% CONTRACT AMOUNT: ~ $7,054,198.00 APPROVED BUDGET AMT: $8,019,968 (includes project contingency of $965,770) CHANGE ORDERS: ESTIMATED FINAL CHANGE ORDER #1 $5,000.00 $294.00 CHANGE ORDER #2 $7,974.00 $7,974.90 CHANGE ORDER #3 $6,640.00 $6,583.74 CHANGE ORDER fl4 $6,212.00 $6,212.00 CHANGE ORDER #5 $21,992.94 $21,992.94 CHANGE ORDER #6 $4,645.00 2,645.00 CHANGE ORDER #7 $4,189.45 $4,189.45 CHANGE ORDER #8 $18,650.03 $18,650.03 CHANGE ORDER #9 ($1,204.00) ($1,204.00) CHANGE ORDER #10* $41,956.89 $40,502.51 CHANGE ORDER #11 $2,095.00 $2,095.00 CHANGE ORDER #12 $1,31 8.26 $1,318.26 CHANGE ORDER #13 $245,000.00 $245,000.00 CHANGE ORDER #14 ($t6,650.50) ($18,650.50) CHANGE ORDER #15 $5,000.00 $6,342.29 CHANGE ORDER #16 $3,500.00 $3,500 CHANGE ORDER #17* $2,196.84 $2,196.84 CHANGE ORDER #18 $75,846.92 $75,846.92 CHANGE ORDER #19 $21,808.46 $21,808.46 CHANGE ORDER #20 $5,540.26 $5,540.26 CHANGE ORDER #21 $1,298.07 $1,298.07 CHANGE ORDER #22 $194,495.51 :I $194,495.51 Page 1 of 3 ...... CHANGE ORDER #23 $72,000.00 $67,687.50 CHANGE ORDER #24 $15,540.00 $15,540.00 CHANGE ORDER #25 $8,297.21 $8,297.21 CHANGE ORDER #26 $19,814.35 $19,814.35 CHANGE ORDER #27 $6,925.22 $6,925.22 CHANGE ORDER #28 $24,612.08 $24,612.08 CHANGE ORDER #29 $3,229.42 $3,229.42 CHANGE ORDER #30 $16,214.90 $16,214.90 CHANGE ORDER #31 $15,500.00 $15,500.00 CHANGE ORDER #32 $6,624.00 $6,624.00 CHANGE ORDER #33 $84,150.29 $84,150.29 CHANGE ORDER #34 $20,430.65 $20,430.65 CHANGE ORDER #35 ($1,340.00) ($1,340.00) CHANGE ORDER #36 $12,777.52 $12,777.52 CHANGE ORDER #37 $14,907.40 $14,907.40 CHANGE ORDER #38 $21,1 91.49 $21,191.49 CHANGE ORDER #,39 $6,509.32 $6,509.32 TOTAL OF CHANGE ORDERS: $1,004,888.98 $991,703.03 *Note: Change Order # 10 and #17are being reimbursed by Koll Development Co. and Intermountain Rigging respectively PROJECT COST SUMMARY: Contract Amount: $7,054,198.00 Item Underrun: ($10,739.t8) Final Item Cost: $7,043,458.82 Addition: Incentive Payment $70,000.00 Change Orders $991,703.03 Deductions: Late lane closure penalty ($24,300.00) Asphalt Concr. Out of Spec. ($878.50) Restaking back charges ($3,638.51) PCC thickness ($746.70) Sub-Total ($29,563.71) Total Project Cost: $8,075,598.14 Budget: $8,019,968.00 Requested Budget Change: $55,630.14 Page 2 of 3 PROGRESS PAYMENTS MADE: F~AYMENT #1 $122,392.50 PAYMENT #2 $346,304.00 PAYMENT #3 $690,383.20 PAYMENT #4 $650,903.00 PAYMENT #5 $322,915.00 PAYMENT #6 $1,372,198.00 PAYMENT #7 $928,869.00 PAYMENT #8 $555,172.20 PAYMENT #9 $119,545.73 PAYMENT #10 $454,340.40 PAYMENT #11 $125,979.11 PAYMENT #12 $305,032.05 PAYMENT #13 $247,810.80 PAYMENT #14 $450,337.27 PAYMENT #15 $537,581.37 PAYMENT #16 $196,878.05 PAYMENT #17 $263,752.39 PAYMENT #18 $123,724.11 'PAYMENT #19 $166,436.00 ITOTAL PROGRESS I PAYMENTS: $7,980,554.18 RF:GOMMENDATION: APPROVI=D APPROVED APPROVfiD DENIED DENIED DENIED SIGNATURES: Public Works Director City Manager Mayor Page 3 of 3 RECIEIVE CONTRACT CHANGE ORDER NO. 35 JAN 0 2004' PROJECT/ROAD: Interstate 580 / Tassajara Road Interchange Improvements CONTRACT NO. City Project No. 01-12, Federal Aid Project No. RSTPL-5432 (011) FIELD OFFICE TO: DeSilva Gates Construction LP You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract. NOTE: This change order is not effective until approved by the Public Works Director. Description of work to be done, estimate of quantities, and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless othe~rwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. Change requested by: Engineer . The last percentage shown is the net accumulated increase or decrease from the original quantity in the Engin~e~_~t~&t~.[:r D Reduce duration of plant establishment period. Plant establishment period to end on December 31, 2003. JAN 2 ADJUSTMENT OF COMPENSATION AT AGREED LUMP SUM CREDIT ~O~ASSA.~ARA PROJECT In lieu of performing plant establishment work for 250 working days the Contractor's plant establishment work will terminate on December 31, 2003. Effective January 1, 2004, the remaining plant establishment work will be performed by City of Dublin forces. For this change the City of Dublin will receive a lump sum credit of $1,340.00 TOTAL COST DECREASE: $ 1~340.00 BY REASON OF THIS ORDER, THE TIME OF COMPLETION WILL BE ADJUSTED 0 WORKING DAYS /5~mes ~ Date i"~erdinand Del Rosario lJate / ~T~ .~e ........ q-h^,..,,~,,,,~.__:_ Date Resident Engineer Sr. Civil Engineer Public Works Director We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the Work above specified, and will accept as full payment therefor the prices shown above. Accepted: Date / /?~_ff__/2001./. Contractor: DeSilva Gates Construction LP · ' ~' un'egents of .J~t~%~fi~actor ~toes' not sign acceptance of this order, his attention is directed to me req ' the specifications as to Cprdceeding with the ordered work and filing a written protest within the time therein specified. CITY DUBLIN Received C7 NOV 1 7 2003 CONTRACT CHANGE ORDER NO. 38 De Silva Gates PROJECT/ROAD: Interstate 580 / Tassajara Road Interchange Improvements PAGE 1 OF 8 PAGES CONTRACT NO. City Project No. 01-12, Federal Aid Project No. RSTPL-5432 (011) TO: DeSilva Gates Construction LP You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract. NOTE: This change order is not effective until approved by the Public Works Director. Description of work to be done, estimate of quantities, and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. Change requested by: Engineer The last percentage shown is the net accumulated increase or decrease from the original quantity in the Engineer's Estimate. Perform miscellaneous extra work as required by Caltrans and as described below. Adjust compensation for roadside signs, the CCTV high mast pole and revised work performed under CCO #13. EXTRA WORK AT AGREED LUMP SUM PRICES Fabricate, furnish and install a custom made trash rack adjacent to the westbound auxiliary lane at 31.5 m LT BSM 107+60. The Trash rack shall be installed as shown on pages 6 through 8 of _this change order. Materials used to fabricate the custom made trash rack shall conform to Section 10-1.68 "Miscellaneous Iron and Steel" of the Special Provisi0ns~ For this work, the Contractor will be paid the lump sum amount of $3,680.00. This amount constitutes full compensation, including markups, for the work of this change. Agreed Lamp Sum Price = $3,680.00 Furaish and install metal beam guard rail on the westbound offramp shoulder from Station TR1M 301+76.8 to TRIM 302+03.9 as shown on pages 4 through 5 of this change order. Fumishand install a Type ET terminal section at Station TR1M 302+03.9 and a Type SFT terminal anchor assembly at Statioa TRIM 301+76.8. The Type ET terminal section shall conform to the details shown on Standard Plan A77M. The terminal anchor assembly (Type SFT) shall conform to the details shown on Standard Plan A77G. For this work, the Contractor will be paid the lump sum amount of $4,715.00. This amount constitutes full compensation, including markups, for the work of this change. Agreed Lump Sum Price = $4,715.00 Seal cobblestone paved median islands with two coats ofmasom'y sealer. Masonry sealer shall be Burke's or equal in .accordance with City of Pleasanton Standard Specifications. For this work, the Contractor will be paid the lump sum amount of $1,300.00. This amount constitutes full compensation, including markups, for the work of this change. Agreed Lump Sum Price = $1,300.00 Total of Agreed Lump Sum Prices = $ 9,695.00 ~' CONTRACT CHANGE ORDER NO. 38 (~ ~0 ['3 PROJECT/ROAD: Interstate 580 / Tassajara Road Interchange Improvements PAGE 2 OF 8 PAGES CONTRACT NO. City Project No. 01-12, Federal Aid Project No. RSTPL-~432 (011) Recehted To: DeSilva Gates Construction, LP NOV 1 ? 21XI3 De Silva Gates EXTRA WORK AT FORCE ACCOUNT Relocate three electrolier foundations adjacent to the TRIM line and conflicting with the as~phalt concrete ditch alignment Regrade the ditch flowIine to maintain positive drainage and conform to field conditions. Pave the regraded ditch with asphalt concrete as shown on plan sheet C-8. Asphalt concrete shah conform to the requirements o£ Section 10-1.48 "Asphalt Concrete" of the Special Provisions and Section 39-7.01 "Miscellaneous Areas" of the Standard Specifications. Force Account Cost = $7,329.74 Provide manual watering of the median landscaping on Tassajara Road during the time period between planting and the installation of the PG&E meter at the controller. Watering shall be performed as directed by the Engineer. Force Accotmt Cost = $ 906.79 Install battery operated controller for irrigation control valve A-3 to control water flow from existing Caltrans irrigation lines to newly installed plants located between the eastbound diagonal on-ramp and the mainline and east of abutment 1. Force Account Cost = $ 631.88 Longitudinally relocate roadside signs along the westbound auxiliary lane as requested by the Caltrans Oversight Engineer. Force Account Cost = $ 883.89 Furnish and install rock slope protection adjacent to the drMnag¢ inlets ld and 1 f located at 9.6 m Lt TR4M 500+38.4 and 9.6m Lt TR4M 501+07 respectively. Rock slope protection shall conform to the requirements Section 72-2 '~Rock Slope Protection" of the Standard Specifications. Force Account Cost = $ 521.37 Furnish and place eight (8) cubic meters of mulch along the planting area along the left shoulder of the westbound offramp between TRIM 300+00 to TRM1 300+40. Mulch shall conform to the requirements of Section 10-2.04 "Highway Planting" of the Special Provisions. Perform minor regrading of the edges adjacent to the roadway and curbs to accommodate additional mulch. Force Account Cost = $1,062.82 Total Force Account Cost = $11,336.49 :' CONTRACT CHANGE ORDER NO. 38 W ~ ~'~ PROJECT/ROAD: Interstate 580 / Tassajara Road Interchange Improvements PAGE ~ OF 8 PAGES CONTRACT NO. City Project No. 01-12, Fede~ral AidProject No. RSTPL-5432 (011) Recei~'ec~ To: ,.Snva C:a Co,, uetio , NOV 1. ? 2003 De Silva Gates ADJUSTMENT OF COMPENSATION AT AGREED LUMP SUM PRICES Contractor agrees to provide credit to the City of Dublin for the following change to the 18.2 meter high mast CCTV pole. Section 86-2.04, "Standards, Steel Pedestals and Posts" of the Standard Specifications, shall be mended as follows: * Longitudinal welds in steel tubular sections will be tested and shall pass a "Fit for Purpose" load test, in lieu of the requirements of California Test 664. · In accordance with section 4-1.03C "Changes in Character of Work" of the Standard SPecifications, the contractor agrees to credit the State the lump sum of $505,00, due to the aforementioned change. Agreed Lump Sum Credit = - $ 505.00 Contractor agrees to credit thc City of Dublin $1,000.00 for utilizing class 3 aggregate base class in lieu of asphalt treated permeable base and the elimination of edge dra_in.q installed under contract change order #13. AgreedLump Sum Credit = - $1,000.00 Provide compensation to contractor for furnishing roadside sign panels as required by Section 10-1.57 '~Roadside Signs" of the Special Provisions. Contact change order 14 eliminated all of the sign panels to be furnished by the contractor. Only the Ovedaead sign panels should have been eliminated by CCO #14. The roadside sign panels are neeessary to complete the work as required by the contract plans. Agreed Lump Sum Price = + $1,665.00 Net Total Adjustment of Compensation + $ 160.00 TOTAL COST INCREASE: $ 21,191.49 BY.REASON OF THIS ORDER, THE TIME OF COMPLETION WILL BE ADJUSTED 0 WORKING DAYS SUBMII'IiEDBY.' ~ ~~' APPRO VALRE~ED B Y: APPROVEDB Y: /'~(rmes E~o~ Date ~Fjrdinand Del Rdsario Da~e / T ~, o ~n. ...... Date ,,~"Resident Engineer gr. CiVil Engineer P~li~ We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all m~_ t..erials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as ~ payment therefor the prices shown above. Accepted: Date 1 2.. / ! /2003 Conlractor. DeSilva Gates Construction LP By:. Title: ~C~ If/fla. eA2o~o~xa~t sign acceptance of this order, his attention is directed to the requirements of the specifications as t~ ~phfe~-eeding with the ordered work and filing a written protest within the time therein specified. I REVISED BYCA!-CULATED! OAT FATE OF CAUFOflNIA DEPARIMENT OF I'RANgKIllTAT,~ DE~IGN OYER ~ MAY KU.e SEE SHEET L-3 SEE SHEET ........ : ' ' . '~' ~ ' ii i~ ~ ~ ' "~ · ~ i~ ~, , ............ rr'-' · ~g,~ ~J j :.,~~.. i i . , = ie~i~ I1 Il. .. o ,- ~ F~ ~ ) , ~ i , ~ SE[ SHEET L-5 [q~FILE~ P~\gBlO5PSE\Chonge Or~ers\Fleld Revlew\?~sLO4. dgn NORMAN gONSALVES CHECKED BY HO J DATE REVISED ' SEE SHEET D-4 'ATE OF CALIFORNIA - DEPARII~dJT OF TRAN.~RTATION D£s:o. ov~$:o~ ¢~LCUt. AT~D/I pAT ...... ~ CHECKED BY t I t DATE REVISED DRAINAOE PLAN SHEET NO. 750 m 900 ~ . 450 ~ o- 600 m 750 ~ ALIERNATIVE 900 ~ ALTERNATIVE CLASS I CONCRETE (BOX CULVERT) BAR RE I NFORC I NO STEEL (2,01 ~ THICK) · 900 ~ CSff INLET (2,01 m THICK) PIPE JT CLASSIFICATION (MINOR STRUCTURES) ~MINOR CONCRETE (MI SC. CONSTRUCTION) MISC. IRON AND STEEL FRAME, ORATE, AND COVER HEIOHT OF INLET "H" MAXIMUM COVER INLET MANHOLE CULVERT o FLARED END SECTION CULVERT (450 ~ TO 900 ~) Received CITY OF DUBLIN NOV 17 2003 CONTRACT CHANGE ORDER NO. 38 'De Silva Gates PROJECT/ROAD: Interstate 580 / Tassajara Road Interchange Improvements PAGE I OF 8 PAGES CONTRACT NO. City Project No. 01-12, Federal Aid Project No. RSTPL,5432 (011) TO: DeSilva Gates Construction LP You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract. NOTE: This change order is not effective until approved by the Public Works Director. Description of work to be done, estimate of quantities, and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. Change reqUeSted by: Engineer The last percentage shown is the net accumulated increase or decrease from the original quantity in the Engineer's Estimate. Perform miscellaneous extra work as required by Caltrans and as described below. Adjust compensation for roadSide signs, the CCTV high mast pole and revised work performed under CCO #13. EXTRA WORK AT AGREED LUMP SUM PRICES Fabricate, furnish and install a custom made trash rack adjacent to the westbound auxiliary lane at 31.5 m LT BSM 107+60. The Trash rack shah be installed as shown on pages 6 through 8 of this change order. Materials used to fabricate the custom made trash rack shall conform to Section 10-1.68 "Miscellaneous Iron and Steel" of the Special Provisions. For this work, the Contractor will be paid the lump sum amount of $3,680.00. This amount constitutes full compensation, including markups, for the work of this change. Agreed Lump Sum Price = $3,680.00 Furnish and install metal beam guard rail on the westbound offramp shoulder from Station TRIM 301+76.8 to TR1M 302+03.9 as shown on pages 4 through 5 of this change order. Furnish and install a Type ET terminal section at Station TR1M 302+03.9 and a Type SFT terminal anchor assembly at Station TRiM 301+76.8. The Type ET terminal section shall conform to the details shown on Standard Plan A77M. The terminal anchor assembly (Type SFT) shall conform to the details shown on Standard Plan A77G. FOr this work, the Contractor will be paid the lump sum amount of $4,715.00. This amount constitutes full compensation, including markups, for the work of this change. ~ Agreed Lump Sum Price = $4,715.00 Seal cobblestone paved median islands with two coats of masonry sealer. Masonry sealer shall be Burke's or equal in accordance with City of Pleasanton Standard Specifications. For this work, the Contractor will be paid the lump sum amount of $1,300.00. This amount constitutes full compensation, including markups, for the work of this change. Agreed Lump Sum Price = $1,300.00 Total of Agreed Lump Sum Prices = $ 9,695.00 PROJECT/ROAD: Interstate 580 / Tassajara Road Interchange Improvements PAGE 2 OF 8 PAGES CONTRACT NO. City Project No. 01-12, Federal Aid Project No. RSTPL-S432 (011) Received To: DeSilva Gates Construction, LP NOV i 7 2003 De Silva Gates EXTRA WORK AT FORCE ACCOUNT Relocate three electrolier foundations adjacent to the TRIM line and conflicting with the asphalt concrete ditch alignment. Regrade the ditch flowline to maintain positive drainage and conform to field conditions. Pave the regraded ditch with asphalt concrete as shown on plan sheet C-8. Asphalt concrete shall conform to the requirements of Section 10-1.48 "Asphalt Concrete" of the Special Provisions and Section 39-7.01 "Miscellaneous Areas" of the Standard Specifications. Force Account Cost = $7,329.74 Provide manual watering of the median landscaping on Tassajara Road during the time period between planting and the installation of the PG&E meter at the controller. Watering shall be performed as directed by the Engineer. Force Account Cost = $ 906.79 Install battery operated controller for irrigation control valve A-3 to control water flow from existing Caltrans irrigation lines to newly installed plants located between the eastbound diagonal on-ramp and the mainline and east of abutment 1. Force Account Cost = $ 631.88 Longitudinally relocate roadside signs along the westbound auxiliary lane as requested by the Caltrans Oversight Engineer. Force Account Cost = $ 883.89 Furnish and install rock slope protection adjacent to the drainage inlets ld and 1 f located at 9.6 m Lt TR4M 500+38.4 and 9.6m Lt TR4M 501+07 respectively. Rock slope protection shall conform to the requirements Section 72-2 "Rock Slope Protection" of the Standard Specifications. Force Account Cost = $ 521.37 Furnish and place eight (8) cubic meters of mulch along the planting area along the left shoulder of the westbound off ramp between TRIM 300+00 to TRM1 300+40. Mulch shall conform to the requirements of Section 10-2.04 '~I-Iighway Planting" of the Special Provisions. Perform minor regrading of the edges adjacent to the roadway and curbs to accommodate additional mulch. Force Account Cost = $1,062.82 Total Force Account Cost -- $11,336.49 PROJECT/ROAD: Interstate 580 / Tassajara Road Interchange Improvements PAGE ~ OF 8 PAGES CONTRACT NO. City Project No. 01-12, Federal Aid Project No. RSTPL-5432 (011) To: DeSilva Gates Construction, LP Received NOV i 7 2003 ADJUSTMENT OF COMPENSATION AT AGREED LUMP SUM PRICES De Silva Gates Contractor agrees to provide credit to thc City of Dublin for thc following change to thc 18,2 meter high mast CCTV pole. Section 86-2.04, "Standards, Steel Pedestals and Posts" of the Standard Specifications, shall be amended as follows: · Longitudinal welds in steel tubular sections will be tested and shall pass a "Fit for Purpose" load test, in lieu of the requirements of California Test 664. In accordance with section 4-1.03C "Changes in Character of Work" of the Standard Specifications, the contractor agrees to credit the State the lump sum of $505.00, due to the aforementioned change. Agreed Lump Sum Credit = - $ 505.00 Contractor agrees to credit the City of Dublin $1,000.00 for utilizing class 3 aggregate base class in lieu of asphalt treated permeable base and the elimination of edge drains installed under contract change order #13. Agreed Lump Sum Credit = - $1,000.00 Provide compensation to contractor for furnishing roadside sign panels as required by Section 10-1.57 "Roadside Signs" of the Special Provisions. Contact change order 14 eliminated all of the sign panels to be furnished by the contractor. Only the Overhead sign panels should have been eliminated by CCO #14. The roadside sign panels are necessary to complete the work as required by the contract plans. Agreed Lump Sum Price = + $1,665.00 Net Total Adjustment of Compensation + $ 160.00 TOTAL COST INCREASE: $ 21,191.49 BY REASON OF THIS ORDER, THE TIME OF COMPLETION WILL BE ADJUSTED 0 WORKING DAYS SUB~/~Y~ APPROV,A~ ~9~ED BY: APPROVED BY: /J~fies E. S/trot/~, Date F~dinand Del Rdsario lJatd / Lee S. Thompson Date Engineer ~/Resident Sr. Civil Engineer Public Work~ Director We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefor the prices shown above. Accepted: , Date [2., /. /_ /2003 Contractor: DeSilva Gates Construction LP -//(// ~--~~' ' of the as tO I t~_~..0n~r c]oes~ot sign acceptance of this order, his attent, ion is d'.n-ected to ~e requirements specifications proceeding with the ordered work and filing a written protest within the time therein specil~ea. CITY OF DUBLIN · CONTRACT CHANGE ORDER NO. 39 PROJECT/ROAD: Interstate 580 / Tassajara Road Interchange Improvements PAGE 1 OF 1 PAGES CONTRACT NO. City Project No. 01-12, Federal Aid Project No. RSTPL-5432 (011) TO: DeSilva Gates Construction LP You' are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract. NOTE: This change order is not effective until approved by the Public Works Director. Description of work to be done, estimate of quantities, and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. Change requested by: Engineer The last percentage shown is the net accumulated increase or decrease from the original quantity in the Engineer's Estimate. Perform m~scellaneous extra work as described below. EXTRA WORK AT AGREED LUMP SUM PRICES Modify drainage inlet 32b to match the depth of the storm drain pipe installed in the landscaped areas between the median islands on Tassajara Road. The overall height of the inlet was increased to match the depth of the storm drain pipe that was lowered to maintain a minimum structural section over the pipe. For this work, the Contractor will be paid the Lump Sum Price of $500.00. This amount constitutes full compensation, including markups, for the work of this change. Install additional pavement delineation at various locations on the project as directed by the Engineer. For this work, the Contractor will be paid the Lump Sum Price of $1700.00. This amount constitutes full compensation, including markups, for the work of this change. EXTRA WORK AT FORCE ACCOUNT Install delineation at all new metal beam guard rail locations as directed by the Engineer and requested by Caltrans. Force Account Cost = $ 882.95 Relocate existing electrical conduit to avoid conflict with the installation of the foundation for overhead sign structure 'F'. Force Account Cost = $ 3,426.37 TOTAL COST INCREASE: $ 6,509.32 BY REASON OF THIS ORDER, THE TIME OF COMPLETION WILL BE ADJUSTED 0 WORKING DAYS  MITTED BY: APPRO~::A'I~ RECOMMENDED BY: APPROVED BY: C~.,.~James E. Scott Date F~rdinand Er61 P~osario D/~t~ Melissa Morton Date Richard Ambrose Date Resident Engineer Sr. Civil Engineer Public Works Director City Manager We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above; and perform all services necessary for the work above sDecified, and will accept as full payment therefor the prices shown above. Accepted: Date g-/ / t /2004 Contractor: DeSilva Gates Construction LP By: Title: Co~¥~ ~'~ o.,, /r'f~Oee_~not s. ign_acce, p_ta..nce of this order, his attention is directed to the requirements of the specifications as to l~i~~dered work and filing a written protest within the time therein specified. CITY OF DUBLIN I'~C~0 t'7 BUDGET CHANGE FORM CHANGE FORM # New Appropriations (City Council Approval Required): Budget Transfers: X__ From Unappropriated Reserves From Budgeted Contingent Reserve (1080-799.000) (If Other than General Fund, Fund No.- '~ O C~ Within Same Department Activity From New Revenues Between Departments (City council Approval Required) Other Name: Name: 1-580/Tassajara Road Interchange $55,630.14 ' improvements - Improvements Account #: Account #: 300-96420-750-050 Name: Name: Account #: Account #: Name: Name: Account #: Account #: Name: Name: Account #: Account#: Name: Name: Account #: Account #: ASD/FinMgr ~~ ~_,._-~/M.~ Date: t.~ ~ '\~\O'~ Signature REASON FOR BUDGET CHANGE ENTRY: This budget change will add $55,630.14 to the. construction budget to pay for the total project cost of the. 1-580/Tassajara Road Interchange Improvement Project (Contract No. 01-12), including Contract Change Order Numbers 35, 38 and 39. As approved at the City Council Meeting on: Date: Mayor: Date: Signature Posted By: Date: Signature H:ICC-FORMSIFORM-budget change, doc