Loading...
HomeMy WebLinkAboutItem 7.1 VilgePkwySidewlkBid CITY CLERK File # D~[QJ[(i]-~ AGENDA STATEMENT CITY COUNCIL MEETING DATE: August 3, 2004 SUBJECT: Authorization to Solicit Bids ~ Contract No. 04-08, Village Parkway Sidewalk Widening & Lighting Improvements Report Prepared by: Melissa Morton, Public Works Director ATTACHMENTS: Plans and Specifications to be available at the City Council meeting RECOMMENDATIO~ FINANCIAL STATEMENT: Authorize Staff to advertise for bids Total Budget & Estimated Costs Design/Constr. Mgmt./Inspection: $ 432,508 hnprovements: $ 889,238 TOTAL: $1,321,746 Budget 2004-2005 $ 63,720 $ 717.370 $ 781,090 Construction of the project will be funded using monies set aside from the City's Downtown/Open Space General Fund Reserve. DESCRIPTION: Staff has completed the plans, specifications and estimates required to carry out the construction of the Village Parkway Sidewalk Widening and Street Lighting Improvements. The proposed capital project would accomplish the following: · Widen existing 5-foot sidewalk to 8 feet from Dublin Boulevard to Amador Valley Boulevard. · Install decorative street lighting spaced approximately 100 feet on center along the new sidewalk with the upper lanterns and pedestrian luminaries lighted with 100 watt and 70-watt light bulbs respectively. · Remove existing cobra head lighting in the median. · Plant street trees in unoccupied tree wells on the new sidewalk. The construction period is estimated at approximately 65 working days. The work has been designed to minimize impacts on businesses along Village Parkway during construction by breaking it down to four work areas to limit the extent of construction impacts as much as possible. Demolition and paving work in the driveway areas will be performed in the night time and vehicular access to the businesses will be preserved during the day time hours. Staff has sent letters to the property owners and businesses --------------------------------------------------------------- COPIES TO: )~~ G:\MISCPROJ\Downtown Streetscape lmprovements\agstauth.doc ITEMNO.~ fY informing them of the project and an invitation was made to them to become involved in a "Committee of Owners" that will provide input to City staff during construction of the project. Once Staffhas met with the interested owners, a communications plan will be developed that will insure that staff is utilizing the best possible communications tools to disseminate information to the affected businesses (i.e. newsletter, e-mail, phone.) Staff will present the list of volunteer committee members to the Council at the approval of the contract award prior to construction. Staff recommends that the City Council authorize solicitation of bids for Contract No. 04-08, Village Parkway Sidewalk Widening and Lighting Improvements. Page 2 D'b~