HomeMy WebLinkAboutItem 4.04 Fire Station Acoustic CITY CLERK
File # 0600-35
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: February 15, 2000
SUBJECT:
Acceptance of Improvements, Contract 99-12A Fire Station
Acoustic Improvement
Report Prepared by: Lee S. Thompson, Public Works Director
ATTACHMENTS:
None
RECOMMENDATION: Accept improvements constructed under Contract 99-12A and
/~/t _~authorize payment to LJ Interiors in the amount of $5,171, less
t/ x~ v4 retention to be paid 35 days following contract acceptance if no
' claims are received.
FINANCIAL STATEMENT: BUDGET
ACTUAL COST
Design and administration
Legal and printing
Construction
$1,000.00 $ 0.00
$ 100.00 $ 286.96
$8,,500.00 $5,171.00
$9,600.00 $5,457.96
This project was completed within funds budgeted. The cost is to be paid from the City' s General Fund.
DESCRIPTION: This project installed acoustic ceiling tile and acoustic wall panels in
the dining/training area of the Donohue Drive fire station. The work was done to reduce the sound echo
that occurred because of the hard surface walls. The echo was particularly detrimental to training
activities. Acoustic conditions are noticeably improved as a result of this work.
The work has been completed satisfactorily and in accordance with project specifications. Staff
recommends that the City Council accept the improvements and authorize payment to LJ Interiors in the
amount of $5,171, less 10% retention to be paid in 35 days if no claims are received.
g:~mis cproj~fsacousfic\agstacpt
COPIES TO:
LJ Interiors
ITEM NO.