HomeMy WebLinkAboutItem 4.02 Mech Bldg Swim Cntr CITY CLERK File # 0600-35 AGENDA STATEMENT CITY COUNCIL MEETING DATE: March 7, 2000 SUBJECT: Swim Center Mechanical Building Renovation (Contract 00-03) Report Prepared by Paul McCreary, Recreation Supervisor ATTACHMENTS: Summary of Bid Results Resolution Budget Change Form RECOMMENDATION: 1. Adopt resolution awarding contract to Zovich Construction in the amount of $220,000 for the renovation of the mechanical building at the Dublin Swim Center. Approve the budget change form to appropriate $43,075 from reserves to Capital Improvement Project No. 95071. FINANCIAL STATEMENT: Budget $198,925 Low Bid $220,000 The base bid plus a 10% contingency is $242,000 which exceeds the funds budgeted for the improvements by $43,075. In order to award the bid, an additional appropriation in this amount from the Unappropriated General Fund Reserve is required. DESCRIPTION: At its meeting on January 18, 2000, the City Council authorized Staff to advertise Contract 00-03 for bids. This project provides for the renovation and expansion of the mechanical building, the installation of new pool heaters, as well as the painting of the exterior of the Swim Center. The project was advertised in accordance with the City's ordinance and six bids were received by the bid opening on February 24, 2000 at 2:00 P.M. Staff has prepared a summary of the six bids received (see Attachment 1). The low bidder was Zovich Construction with a bid of $220,000. Staff recommends including a 10% contingency, which brings the total funds needed to $242,000. The total budget for project is $198,925 which would result in a funding shortfall in the amount of $43,075 if the bid is awarded. The City's pool consultant Arch Pac, Inc prepared the estimated cost of the project for budgeting purposes. Since the budget was prepared, a soils report was completed that recommended additional excavation and fill for the building foundation. Staff does not believe that substantial cost savings could be achieved by rebidding the project. If the project were rebid, the new heaters could not be installed for the upcoming swim season. The existing heater at the Swim Center is not currently operating and does not appear to be serviceable. G:\COUNCILX37mechbldgagree.doc COPIES TO: Zovich Construction ITEM NO. ~taff has reviewed the low bidder's proposal and license status. Staff also checked the contractor's references and received no negative comments. Therefore, Staff recommends that the City Council adopt the resolution awarding Contract 00-03 to Zovich Construction. Further, it is recommended that the City Council approve the Budget Change Form in Attachment 3 that will provide for an additional appropriation from the Unappropriated General Fund Reserve for $43,075. The project is expected to take 60 working days to complete. Therefore, Staff anticipates that the project will be finished in early June. 0 ~ o add, oo 000000000 0 00[00000 00000iO 000 0 00!00000 0 ~ ~ooooooooo ~ ~oooiooool ~ 000000000 I ~ 0000000 000000000 0 ~~000 d · o o o o o o o o o ~ ~ ~ o o olo o o o o o z ~ ~oolooooooo I ioooo~ooooo  000000000 ~ ~~~0 ~ 000000000 0 000000000 0 ~ ~~~ o ooooooooo o ~ ~ ~ o~o~oo~ ~ ~ ooooooooo o z ~ o -- = ~ ~ooooooooo ¢ ~§ooo~oo ~ ~ ~ 0000000;00 0000 0 0 · ~dddddddldd 0 ~ddddddddd Z ~ ~ 0 ~ 0 ~ 0 0 ~i~ ~ ~ 0 0 0 0 0 0 0 0 0 ATTACHMENT 1 RESOLUTION NO. - 2000 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN AWARDING CONTRACT NO. 00-03 DUBLIN SWIM CENTER MECHANICAL BUILDING RENOVATION PROJECT TO ZOVICH CONSTRUCTION WHEREAS, the City of Dublin did, on February 24, 2000, publicly open, exarfiine, and declare all sealed bids for doing the work described in the approved Specifications for Contract No. 00-03, which Specifications are hereby expressly referred to for a description of said work and for all particulars relative to the proceedings under the request for bids; and WHEREAS, said bids were submitted to the City Engineer, who has reviewed the bids to determine the lowest bid which was responsive to the requirements of the bid documents; and NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby award Contract No. 00-03 to the lowest responsible bidder therefor, to wit, Zovich Construction, at a base bid of Two Hundred Twenty Thousand Dollars and no cents ($220,000.00), the particulars of which bid are on file in the office of the City Engineer. PASSED, APPROVED AND ADOPTED this 7th day of March, 2000. AYES: NOES: ABSENT: ABSTAIN: ATTEST: Mayor City Clerk G:\COUNCILk37mechbldgreso. doc ATTACHMENT 2 CITY OF DUBLIN BUDGET CHANGE FORM CHANGE FORM # New Appropriations (City Council Approval Required): Budget Transfers: X Required) From Unappropriated Reserves From New Revenues From Budgeted Contingent Reserve (1080-799.000) Within Same Department Activity Between Departments (City Council Approval Other DECREASE BUDGET ACCOUNT :AMOUNT INCREASE BUDGET ACCOUNT AMOUNT Name: Name: Improvements $43,075 Account #: Account #: 00D95071~750-050 Name: Name: Account #: Account #: Name: Name: Account #: Account #: Name: Name: Account #: Account #: City Manager: Date: SignatUre REASON FOR BUDGET CHANGE.ENTRY: In order to award the bid for the Dublin Swim Center Mechanical Building Renovation project, an additional appropriation is needed. Mayor: Posted By: Date: Signature ATTACHMENT 3