HomeMy WebLinkAboutItem 4.5 Accept Work No. 88-1A (2) CITY OF DUBLIN
AGENDA STATEMENT
City Council Meeting Date: March 12, 1990
SUBJECT: Acceptance of Work - Contract No. 88-1A (Masonry
Wall) and 88-8 (Wood Wall) Major Arterials Soundwalls
(Report by Public Works Director Lee Thompson
EXHIBITS ATTACHED: None.
RECOMMENDATION: 1) Accept improvements under Phase II of Contract
88-1A (Block Soundwall)
) Accept improvements under Contract 88-8 (Wood
Soundwall)
3) Authorize budget transfer in the amount of
$28,218 from unallocated reserves to the Major
Arterial Soundwalls Capital Improvement Project
4) Authorize final payment and retention to B & B
Concrete in the amount of $16,638.16
FINANCIAL STATEMENT:
Contract 88-8 Wood Soundwall, West Side of San Ramon Road (Gateway
Landscaping)
Original Bid: $175,414.00
Change Orders: 1,679.00
Changes in Field Quantities: (2,160.00)
Liquidated Damages: (1,500.00) (10 days at $150/day)
Final Project Cost: $173,433.00
The change orders amounted to less than one percent of the original bid;
however, due to some reduction in field quantities as compared to bid
quantities and $1,500 in liquidated damages, the final contract cost is
$1,981 less than the bid price.
Contract 88-1A Masonry Soundwall (B & B Concrete)
Original Bid: $510,479.00
Change Orders: 10,748.35
Changes in Field Quantities: 3,987.75
Final Project Cost: $525,215.10
The change orders, including the increase in field quantities, amounted to
less than three percent of the original bid.
Miscellaneous work performed on wood wall project included the following:
1) BSK Associates, soils engineers, performed soils report on a claim from a
resident that his pool deck had separated from the pool because of the
wall construction: $ 200.00
2) City Maintenance (MCE) installed kickboards at the bottom of some of the
fences because of gaps at lots with uneven pads: $3,045.40
Total: $3,245.40
ITEM NO. COPIES TO: B & B Concrete
Gateway Landscape
* * * *
Budget Actual Expenditure
Preparation of Easements,
Right of Way Negotiations,
Design and Inspection: $ 116,500 $ '124,250
Construction 707,500 698,648
Miscellaneous Costs 1,500 3,245
Total: $ 825,500 $ 826,143
Budget vs. Actual Cost History
Budget Actual Difference
Prior Years: $ 82,373 $ 82,373 $ 0
FY 88-89 657,127 629,552 (27,575)
FY 89-90 86,000 114,218 28,218
Total: $ 825,500 $ 826,143 $ 643
The total expenditure is projected to be $643 over budget; however, because
less money than anticipated was expended in FY 88-89, it is necessary to
transfer $28,218 to this project from unallocated reserves.
DESCRIPTION:
This Capital Improvement project consists of two separate contracts. One of
the contracts provided for the construction of a wood soundwall on the west
side of San Ramon Road. The other contract provided for the construction of
a masonry block wall on the east side of San Ramon Road, both sides of
Amador Valley Boulevard east of Village Parkway, and along the west side
Dougherty Road at Arroyo Vista. The San Ramon Road soundwalls were
constructed as noise mitigation for the road widening project. The Amador
Valley Boulevard soundwalls were constructed primarily as a beautification
measure, as these walls replaced the deteriorated wooden fences installed in
the early 1960's by the original subdivider. The Dougherty Road soundwall
provides sound mitigation for Arroyo Vista residents and was financed by the
Housing Authority and Community Development Block Grant funds.
The most significant problem with these projects occurred when the block
wall along San Ramon Road was delayed by a conflict with underground utility
lines that were located too close to the original site for the wall. The
soundwall was originally intended to be built entirely within the public
right-of-way but had to be moved back to the private property line, and
Staff was required to obtain easements from the property owners.
Both projects have now been completed in accordance with the approved plans,
specifications, and modifications, and Staff recommends that the City
Council accept the projects, authorize a budget transfer in the amount of
$28,218 from unallocated reserves, and authorize final payment to B and B
Concrete in the amount of $16,638.16.
- 2 -