Loading...
HomeMy WebLinkAboutItem 4.10 Accept Work 88-7 (2) CITY OF DUBLIN AGENDA STATEMENT City Council Meeting Date: March 26, 1990 SUBJECT: Acceptance of Work - Contract No. 88-7 San Ramon Road Phase III Street Reconstruction, Widening, Traffic Signals, Bike Path, and Landscaping (Report by Public Works Director Lee Thompson) EXHIBITS ATTACHED: None. RECOMMENDATION~ 3) Accept improvements under Contract 88-7 Authorize release of securities and retention payment to Gallagher and Burk in the amount of $48,168.22. Authorize a transfer of $94,497.84 from unallocated reserves. FINANCIAL STATEMENT: Total Actual Cost Design, inspection, and resident engineer $ 239,945.31 Traffic engineering 5,617.50 Subtotal 245,562.81 Material testing and misc. professional services Environmental documents DSRSD/Zone 7 (water service fees) Construction Surveying Total Budgeted 240,000.00 6,546.00 10,000.00 6,841.95 7,000.00 11,430.00 11,500.00 963,364.36 1,000,000.00 27,985.24 30,000.00 Total: $1,261,730.36 $1,298,500.00 Actual Costs for 1989-90 Budgeted for Fiscal 1989-90 Design, inspection and resident Engineer Construction $ 5,461.40 $ 10,000.00 99,036.44 When the last CIP update was prepared (April-May 1989), it was assumed that the Contractor would be completed by the end of Fiscal Year 1988-89 and that only final project reporting would carry over into this fiscal year. As it happened, the Contractor did not complete his final "punch" list of defic- iencies until recently, which caused his 10% contractor retention to be paid in this fiscal year~ It is, therefore, necessary to authorize a transfer from unallocated reserves to complete this project. ITEM NO.~ COPIES TO: Gallagher & Burk, Inc. Construction contract as completed with all change orders: $ 963,364.36 Construction contract as awarded to Gallagher & Burk 927,797.90 Engineer's estimate of construction costs: 1,339,576.80 Completed construction cost including change orders vs. award of contract cost difference: +$35,566.46 or 3.7% over original bid Completed construction cost including change orders vs. engineer's estimate: (-$376,212.44) or 39.1% under engineer's estimate. Actual total project cost: Budgeted total project cost (FY89-90): $1,261,730.36 $1,298,500.00 Difference between actual and budgeted cost is (-$36,769.64) or (-2.8%)~ Financing General Fund (not including purchase of FAU funds) Federal Aid Urban funds: Tri-Valley City of San Luis Obispo *purchased with $262,256.00 of General Fund money Total: $412,055.69 500,000.00 349,674.67* $1,261,730.36 DESCRIPTION: In August, 1988, the City Council awarded Contract 88-7 San Ramon Road Improvements Phase III to Gallagher and Burk, Inc. This project widened San Ramon Road from Vomac Road to the City Limit at Alcosta Boulevard and included a new traffic signal at Vomac Road, a landscaped median, and a lighted and landscaped bike/pedestrian path. This was the third of four phases of San Ramon Road Improvements. The City Engineer has reviewed the work on the project and determined that it is complete and in accordance with the approved plans, specifications, and modifications. Staff recommends that the City Council accept the improvements and authorize release of securities and a retention payment to Gallagher and Burk in the amount of $48,168.22. The total project is $36,769~64 under the budget approved on the last tIP update; however, due to the carryover of the Contractor's retention on this project, a budget transfer is necessary to make up the deficit for that budgeted in this 1989-90 fiscal year. - 2 -