HomeMy WebLinkAboutItem 4.05 Award of Bid 93-02 (2) CITY OF BUBLIN
AOENDA STATEMENT
City Council Meeting Date: March 22, 1993
SUBJECT:
Award of Bid - Contract 93-02
Annual Street Overlay, North Avenue Bike Path
Report by Public Works Director Lee Thompson
EXHIBITS ATTACHED:
l)
2)
Resolution of Award
Summary of Bids
RECO~4F-/~DATION:
1)
2)
3)
Adopt resolution awarding bid to Les McDonald
Construction.
Authorize Mayor to execute agreement.
Authorize a change in funding sources for the
Annual Overlay as indicated below.
FINANCIAL STATEMENT:
Overlay/Repair
Bike Path
TOTAL
Low Bid
Received
$386,325.95
53,340.00
$439,665.95
BID RESULTS
Engineer's
Estimate
$431,874.25
55,107.50
$486,981.75
Budgeted for
Construction
$423,200
56,000
$479,200
BUDGETS
Street Overlay Project:
Budgeted
Expenditures
Budget By
Fund Source
*Fund Source
Revised
(add'l SB300)
Preliminary Engr. $ 5,000 General Fund CIP $ 27,106 $ 0
Design 3,500 Measure "B" 138,086 130,717
Inspection 20,000 SB300/140 34,808 69,283
Improvements (Overlay) 331,200 General Fund
Repair for Slurry Sts. 92,000 Oper. Budget 160,000 150,000
Misc. (Printing, Legal) 300 Gas Tax Oper.
Budget 92,000 92,000
Totals: $452,000 $452,000 $442,000
* Funding source revisions due to additional SB300 monies and a $10,000 reduction in
striping.
North Avenue Bike Path
Budgeted
Expenditures
Budget By
Fund Source
Preliminary Engineering $ 8,000
Design 4,000
Inspection 4,000
Improvements 56,000
Misc. 3,000
TDA (Article 3) $75,000
TOTAL $75,000
DESCRIPTION: At its meeting of February 22, 1993, the City Council
authorized Staff to advertise for bids for Contract 93-02, the Annual Street
Overlay/North Avenue Bike Path. The annual overlay program consists of placing at
least a 1 1/2" asphalt overlay on streets that are in a deteriorated condition. A
special pavement fabric will also be placed over the travelway prior to the asphalt
ITEM NO.~ J COPIES TO: Les McDonald Construction
overlay. This fabric helps bridge the existing minor pavement cracks and prevents
the reflection of cracks through the new asphalt. Before installing the overlay,
the pavement failures are dug out to the base rock and replaced with a new section
of asphalt. Repair is also done to the streets scheduled for the spring slurry seal
program.
The overlay program will receive funds from the State-Local Transportation
Partnership Program (SB140 Gas Tax).
The North Avenue Bike Path is also included in the Overlay Project because of the
cost savings generated by doing two asphalt-related programs together. This project
will construct a bike path from Dougherty Road northwest along the old railroad
right-of-way to tie into the proposed bike path at Dublin Meadows. The bike path is
funded by a grant from the Transportation Development Act (TDA).
Streets to be overlaid are:
Aldea Street
Larkdale Avenue
Callan Street
Burnham Way
Mansfield Avenue
Emerald Avenue
Burton Street
Ann Arbor Way
Lancaster Road
Ebensburg Lane
Sunwood Drive
Hillrose Drive
(Brighton Drive to Tamarack Drive)
(Bristol Road to Aldea Street)
(Brighton Drive to Burnham Way)
Callan Street to Tamarack Drive)
Burnham Way to Brighton Drive)
Tamarack Drive to Amador Valley Blvd.)
Tamarack Drive to Amador Valley Blvd.)
Amador Valley Blvd. to Lancaster Road)
Penn Drive to York Drive)
Clark Avenue to Maple Drive)
Gardella Drive to Landale Avenue)
Donohue Drive to Starward Drive)
Village Parkway/Clark Avenue Loop (South of Dublin Blvd.)
Regional Street (South of Dublin Blvd.)
Sierra Court (North of Trinity Court)
Trinity Court
Notices will be sent out prior to the beginning of work in order to advise the
residents and businesses that construction will take place on their street.
The City received a total of thirteen (13) bids (see attached summary) for this
project. The bids ranged from a low of $439,665.95 to a high of $553,621.55. The
low bidder was Les McDonald Construction with a bid of $439,665.95. Les McDonald
Construction has done a number of projects for the City in the past, including
overlay projects and the Dublin Blvd. Extension.
Staff recommends that the City Council adopt the resolution awarding the bid to Les
McDonald Construction and authorize the Mayor to execute the agreement.
a:(projects) loverlay~agstawrd
Page 2
RESOLUTION NO. -93
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
AWARDING CONTRACT 93-02,
AN~U3AL STREET OVERLAY/NORTH AVENUE BIKE PATH
TO LES MCDONALD CONSTRUCTION.
WHEREAS, the City of Dublin did on March 16, 1993, publicly open examine, and
declare all sealed bids for doing the work described in the approved Plans,
Specifications, and Modifications for Contract 93-02 Annual Street Overlay/North
Avenue Bike Path, authorized by the city Council on February 22, 1993, which Plans,
Specifications, and Modifications are hereby expressly referred to for a description
of said work and for all particulars relative to the proceedings under the request
for bids; and
WHEREAS, said bids were submitted to the City Engineer, who has reviewed the
bids to determine the lowest bid which was responsive to the requirements of the bid
documents;
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin
does hereby award Contract 93-02 to the lowest responsible bidder therefor, to wit,
Les McDonald Construction, at a bid of Four Hundred Thirty-Nine Thousand Six Hundred
Sixty-Five Dollars and Ninety-Five Cents ($439,665.95), the particulars of which bid
are on file in the office of the City Engineer.
PASSED, APPROVED AND ADOPTED this 22nd day of March,
AYES:
NOES:
ABSENT:
1993.
Mayor
ATTEST:
City Clerk
a: (projects) \overlay\resoawrd
1993 A~NUAL BTRBET OVERLAY/NORTH A ~E BIKE PATH, CONTRACT 93-02
STREET OVERLJ~Y
ITEM
DESCRIPTION
£NGR'S ESTIMATE
UNIT UNIT TOTAL
MEAS 0TY PRICE PRICE
PLANE AC pVMT 6' WIDE LF 36,185 .65 23,520.25
PVMT FAILURE REPAIR (4") SF 143,000 1.27 181,610.00
PVMT FAILURE REPAIR (10") SF 420 3.00 1,260.00
PV~T FAILURE REPAIR (18") SF 360 5.00 1,800.00
PVMT REINFORCING FABRIC SY 44,531 .75 33,398.25
INSTALL 1 1/2" AC OVERLAY SF 652,200 .26 169,572.00
ADJUST MONUMENTS TO GRADE EA 45 160.00 7,200.00
ADJ. STORM DP~IN MANHOLE EA 1 300.00 300.00
INST. SIGNAL DETECTOR LPS EA 25 250.00 6,250.00
8" SOLID LINE LF 290 .90 261.00
DOUBLE YELLOW CTRLINE LF 1,610 .90 1,449.00
12" SOLID LINE LF 1,915 1.65 3,159.75
ARROW, TYPE IV EA 4 60.00 240.00
STOP EA 21 70.00 1,470.00
REFLECTIVE pVMT MARl(ERS EA 96 4.00 384.00
TOTAL OVERLAY
$431.874.25
~Q. AV~NU~ BIK~ PST~ ENGR'S ESTIMATE
ITEM UNIT UNIT TOTAL
NO. DESCRIPTION M~AS OTY PRICE PRICE
16. CLEAR ANO GRUB LS 1 2,500.00 2,500.00
17.F EARTHWORK CY 335 3.50 1,172.50
18.F AC & AB BIKE PATH SECTION SF 18,000 1.00 18,000.00
19. ROADWAY SECTION 5F 12,000 2.00 24,000.00
20. CATCH BASIN/21"RCP LS 1 1,500.00 1,500.00
21. ASPHALT CONCRETE CURB LF 1,050 5.10 5,355.00
22. BIKE PATH & STOP SIGNS EA 4 120.00 480.00
23. BIKE CROSSING SIGNS EA 4 150.00 600.00
24. BIKE PATH STRIPING LS i 1,200.00 1,200.00
25. TYPE III BARRICADE LS 1 300.00 300.00
TOTAL BIKE PATH
TOTAL PROJECT
LES MC DONALD EAST BAY EXCAVATING
UNIT TOTAL UNIT TOTAL
PRICE pRICE PRICE PRICE
.65 23,520.25
1.00 143,000.00
3.00 1,260.00
4.00 1,440.00
.70 31,045.70
.25 163,050.00
150.00 6,750.00
280.00 280.00
205.00 5,125.00
1.50 435.00
1.00 1,610.00
2.00 3,630.00
75.00 300.00
200.00 4,200.00
5.00 480.00
$$~6.325.95
LES MC DONALD
UNIT TOTAL
PRICE pRICE
2,500.00 2,500.00
20.00 6,700.00
.60 10,800.00
2.20 26,400.00
2,000.00 2,000.00
2.80 2,940.00
120.00 480.00
180.00 720.00
i00.00 100.00
700.00 700.00
$53.340.00
$4391665.95
.58 20,987.30
.96 137,280.00
6.40 2,688.00
6.96 2,505.60
.72 31,932.72'
.25 163,050.00
167.00 7,515.00
416.00 416.00
240.00 6,150.00
.83 240.70
.83 1,336.30
2.08 3,983.20
73.00 292.00
73.00 1,533.00
5.20 499.20
$~0,409.02
EAST BAY EXCAVATING
UNIT TOTAL
PRICE PRICE _
654.00 654.00
19.52' 6,540.00
.33 5,940.00
3.43 41,160.00
1,830.00 1,830.00
3.38 3,549.00
166.40 665.60
230.00 920.00
4,100.00 4,100.00
$~,44~.60
$4461850.62*
~STREET OVER~Ay GRANITE CONST. REDGWICK CONST.
iTEM UNIT UNIT TOTAL UNIT TOTAL
NO. DESCRIPTION MEAS QTY PRICE PRICE PRICE PRICE
1. PLANE AC P¥~T 6' WIDE LF 36,185 .60 21,711.00 .57 20,625.45
2. PVMT FAILURE REPAIR (4") SF 143,000 1.00 143,000.00 1.06 151,580.00
3. PVMT FAILURE REPAIR (10") SF 420 3.00 1,260.00 5.75 2,415.00
4. PVMT FAILURE REPAIR (18") SF 360 4.00 '1,440.00 5.50 1,980.00
5. PVMT REINFORCING FABRIC SY 44,531 .70 31,045.70' .68 30,158.68
6. INSTALL 1 1/2" AC OVERLAY SF 652,200 .26 169,572.00 .26 169,572.00
7. ADJUST MONUMENTS TO GRADE EA 45 135.00 6,075.00 160.00 7,200.00
8. ADJ. STORR DRAIN MANHOLE EA 1 300.00 300.00 500.80 500.00
9. INST. SIGNAL DETECTOR LPS EA 25 275.00 6,875.00 195.00 4,875.00
10. 8" SOLID LINE LF 290 .80 232.00 1.00 290.00
11. DOUBLE YELLOW CTRLINE LF 1,610 .80 1,268.00 .65 1,046.50
12. 12" SOLID LINE LF 1,915 2.00 3,830.00 2.75 5,266.25
13. ARROW, TYPE IV EA 4 70.00 280.00 52.00 208'00
14. STOP EA 21 70.00 1,470.00 90.00 1,890.00
15. REFLECTIVE PVMT MARRERS EA 96 5.00 480.00 3.00 288.00
TOTAL OVERLAY $]~8.858.70' 8397.894.88
MC OUIBE & HESTER
UNIT TOTAL
PRICE PRICE
.88 31,842.80
1.00 143,000.00
5.00 2,100.00
8.00 2,880.00
.90 39,915.90
.29 189,138.00
140.00 6,300.00
360.00 360.00
210.00 5,250.00
1.00 290.00
.70 1,127.00
2.80 5,362.00
210.00 840.00
100.00 2,100.00
3.00 288.00
5430.793.70
NO. AVENUE BIKE PATH GRANITE CONST. REDGWICK CONST.
ITEM UNIT UNIT TOTAL UNIT
NO. DESCRIPTION MEAS OTY PRICE PRICE pRICE
16. CLEAR AND GRUB LS 1 14,176.30 14,176.30 400.00
17.F EARTHWORK CY 335 20.00 6,700.00 19.00
18.F AC & AB BIKE PATH SECTION SF 18,000 .55 9,900.00 .55
19. ROADWAY SECTION SF 12,000 3.00 36,000.00 4.75
20. CATCH BASIN/21"RCP LS 1 1,500.00 1,500.00 3,000.00
21. ASPHALT CONCRETE CURB LF 1,050 5.00 5,250.00 3.50
22. BIKE PATH & STOP SIGNS EA 4 200.00 800.00 175.00
23. BIKE CROSSING SIGNS EA 4 200.00 800.00 175.00
24. BIKE PATH STRIPING LS 1 4,000.00 4,000.00 180.00
25. TYPE III BARRICADE LS 1 1,000.00 1,000.00 1,040.00
TOTAL BIKE PATH $~Q,126.30 082.960.00
TOTAL PROJECT $468.905.00* $450.854.88
MC GUIRE & BESTER
TOTAL UNIT TOTAL
PRICE PRICE PRICE
400.00 2,700.00 2,700.00
6,365.00 28.00 9,380.00
9,900.00 .90 16,200.00
57,000.00 2.20 26,400.00
3,000.00 2,500.00 2,500.00
3,675.00 3.00 3,150.00
700.00 180.00 720.00
700.00 180.00 720.00
180.00 200.00 200.00
1,040.00 500.00 500.00
STREET OVERLAy GALLAGHER & BURK
ITEM USIT UNIT TOTAL
NO. D$$CRIPTION MEAS QTY PRICE PRICE
1. PLANE AC PVMT 6' WIDE LF 36,185 .65 23,520.25
2. pVMT FAILURE REPAIR (4") SF 143,000 1.20 171,600.00
3. PVMT FAILURE REPAIR (10") SF 420 3.00 1,260.00
4. PVMT FAILURE REPAIR (18") SF 360 5.40 1,944.00
5. PV~T REINFORCING FABRIC SY 44,531 .75 33,263.25
6. INSTALL I 1/2" AC OVERLAY SF 652,200 .26 169,572.00
7. ADJUST MONUMENTS TO GRADE EA 45 175.C0 7,875.00
8. ADJ. STORR DRAIN Fu~NHOLE £A 1 450.00 450.00
9. INST. SIGNAL DETECTOR LPS £A 25 315.00 7,875.00
10. 8" SOLID LINE LF 290 .90 261.00
11. DOUBLE YELLOW CTRLINE LF 1,610 .90 1,449.00
12. 12" SOLID LINE LF 1,915 2.10 4,021.50
13. ARROW, TYPE IV EA 4 80.00 320.00
14. STOP EA 21 80.00 1,680.00
15. REFLECTIVE PVMT MARKERS EA 96 5.50 528.00
TOTAL OVERLAY $425.619.00
NO. AVENUE BIKE PATH GALLAGHER & BURK
ITEM UNIT UNIT TOTAL
NO. DESCRIPTIO~ MEAS OTY PRICE PRICE
16. CLEAR ANO GRUB LS 1 5,000.00 5,000.00
17.F EARTHWORK CY 335 10.00 3,350.00
18.F AC & AB BIKE PATH SECTION SF 18,000 .75 13,500.00
19. ROADWAY SECTION SF 12,000 3.70 44,400.00
20. CATCH BASIN/21"RCP LS 1 1,750.00 1,750.00
21. ASPHALT CONCRETE CURB LF 1,050 3.65 3,832.50
22. BIKE PATH & STOP SIGNS EA 4 175.00 700.00
23. BIKE CROSSING SIGNS EA 4 250.00 1,000.00
24. BIKE PATH STRIPING LS 1 4,335.00 4,335.00
25. TYPE III BAKRICADE LS 1 1,145.00 1,145.00
TOTAL BIKE PATH
$79,012.50
JOE CARONE
UNIT TOTAL
PRICE PRICE
.70 25,329.50
1.15 164,450.00
6.00 2,520.00
8.00 2,880.00
.70 31,045.70
.26 169,572.00
160.00 7,200.00
350.00 350.00
275.00 6,875.00
1.50 435.00
.75 1,207.50
1.50 2,872.50
75.00 300.00
175.00 3,675.00
4.50 432.00
$419.144.20
JOE CARONE
UNIT TOTAL
PRICE PRICE
5,000.00 5,000.00
16.00 5,360.00
.92 16,560.00
4.50 54,000.00
1,200.00 1,200.00
6.50 6,825.00
150.00 600.00
175.00 700.00
3,148.00 3,148.00
800.00 800.00
OLIVER DE SILVA
UNIT TOTAL
PRICE PRICE
.80 28,948.00
1.07 153,010.00
8.30 3,486.00
8.80 3,168.00
.73 32,376.23
.29 189,138.00
160.00 7,200.00
450.00 450.00
240.00 6,000.00
.80 232.00
.80 1,288.00
2.00 3,830.00
70.00 280.00
70.00 1,470.00
5.00 480.00
$431.356.23
OLIVER DE SILVA
UNIT TOTAL
p~IC~ PRICE
500.00 500.00
23.00 7,705.00
.85 15,300.00
4.30 51,600.00
3,400.00 3,400.00
3.75 3,937.50
160.00 640.00
220.00 880.00
3,940.00 3,940.00
1,040.00 1,040.00
$~8,942.50
ANNUAL STREET OVERLAY/NORTH AVENUE BIKE PATS, CONTRACT 93-02
STREET OVERLAY
VINTAGE GRADING
ITEM UNIT UNIT TOTAL
NO. DESCRIPTION MEAS OTY PRICE PRICE
1. PiJ%NE AC PVMT 6' WIDE LP 36,185 .63 22,796.55
2. pVMT FAILURE REPAIR (4") SF 143,000 1.22 174,460.00
3. PVMT FAILURE REPAIR (10") SF 420 7.25 3,045.00
4. PV~T FAILURE REPAIR (18") SF 360 10.00 3,600.00
5. pVMT REINFORCING FABRIC SY 44,531 .68 30,158.68
6. INSTALL i 1/2" AC OVERLAY SF 652,200 0.253 165,006.60
7. ADJUST MONUMENTS TO GRADE EA 45 160.00 7,200.00
8. ADJ. STOP, M DRAIN MANHOLE EA 1 400.00 400.00
9. INST. SIGNAL DETECTOR LPS EA 25 195.00 4,875.00
10. 8" SOLID LINE LF 290 .80 232.00
11. DOUBLE YELLOW CTRLINE LF 1,610 .80 1,288.00
12. 12" SOLID LINE LF 1,915 2.00 3,830.00
13. AP, ROW, TYPE IV EA 4 70.00 280.00
14. STOP EA 21 70.00 1,470.00
15. REFLECTIVE PV~T MAP~KERS F,A 96 5.00 480.00
TOTAL OVERIJ%Y $419.121.83
O.C. JONES O'GRADY PAVING
UNIT TOTAL UNIT TU']'AL
PRICE PRICE PRICE PRICE
.73 26,415.05 .60 21,711.00
1.30 185,900.00 4.40 207,350.00
7.80 3,276.00 5.00 2,100.00
9.60 3,456.00 11.00 3,960.00
.68 30,158.68 .77 34,150.27
.27 176,094.00 .28 182,616.00
150.00 6,750.00 150.00 6,750.00
400.00 400.00 500.00 500.00
195.00 4,875.00 215.00 5,375.00
1.50 435.00 .90 261.00
.75 1,207.50 .90 1,449.00
1.50 2,872.50 2.20 4,213.00
75.00 300.00 80.00 320.00
175.00 3,675.00 80.00 1,680.00
4.50 432.00 6.00 576.00
5446.246.73 $473,011.27
~Q. AVENUE BIKE PATH VINTAGE GRADING O.C. JONES O'GRADY PAVING
ITEM UNIT UNIT TOTAL UNIT TOTAL UNIT ~u,AL
NQ, DESCRIPTION MEAS OTY PRICE pRICE PRICE PRICE PRICE PRICE
16. CLEAR AND GRUB LS 1 20,500.00 20,500.00 6,700.00 6,700.00 6,000.00 6,000.00
17.F EART}{WOP~ CY 335 20.77 6,957.95 17.50 5,862.50 6.00 2,010.00
18.F AC & AB BIKE PATH SECTION SF 18,000 1.05 18,900.00 .90 16,200.00 .85 15,300.00
19. ROADWAY SECTION SF 12,000 4.35 52,200.00 3.40 40,800.00 3.00 36,000.00
20. CATCH BASIN/21"RCP LS 1 1,500.00 1,500.00 5,000.00 5,000.00 2,000.00 2,000.00
21. ASPHALT CONCRETE CURB LF 1,050 4.60 4,830.00 2.50 2,625.00 5.00 5,250.00
22. BIKE PATH & STOP SIGNS EA 4 160.00 640.00 700.00 2,800.00 175.00 700.00
23. BIKE CROSSING SIGNS EA 4 220.00 880.00 700.00 2,800.00 240.00 960.00
24. BIKE PATH STRIPING LS i 3,940.00 3,940.00 800.00 800.00 4,000.00 4,000.00
25. TYPE III BAP~RICADE LS 1 1,040.00 1,040.00 800.00 800.00 1,000.00 1,000.00
TOTAL BIKE PATH 5111.387.95 $84,387.50 $73.220.00
TOTAL PROJECT $530,509.78 ~530~634.23 $546.231.27
STREET OVERLAY JARES RIOLO MERIDIAN PAVING
ITEM UNIT UNIT TOTAL UNIT TOuAL
NO. DESCRIPTION MEAS QTY PRICE pRICE PRICE PRICE
1. pLANE AC pVMT 6' WIDE LF 36,185 .80 28,948.00 .70 25,329-50
2. PVMT FAILURE REPAIR (4") SF 143,000 .88 125,840.00 1.40 200,200.00
3. pVMT FAILURE REPAIR (10") SF 420 7.00 2,940.00 3.40 1,428.00
4. PUMT FAILURE REPAIR (18") SF 360 7.00 2,520.00 16.00 5,760.00
5. pVMT REINFORCING FABRIC SY 44,531 .80 35,480.80 .80 35,480.80*
6. INSTALL 1 1/2" AC OVERLAY SF 652,200 .30 195,660.00 .27 176,094.00
7. ADJUST MONUMENTS TO GRADE EA 45 100.00 4,500.00 130.00 5,850.00
8. ADJ. STORM DRAIN MANHOLE EA 1 200.00 200.00 500.00 500.00
9. INST. SIGNAL DETECTOR LPS EA 25 500.00 12,500.00 220.00 5,500.00
10. 8" SOLID LINE LF 290 .10 29.00 1.65 478.50
11. DOUBLE YELLOW CTRLINE LF 1,610 .10 161.00 .80 1,288.00
12. 12" SOLID LINE LF 1,915 2.40 4,596.00 1.65 3,159.75
13. AP, ROW, TYPE IV EA 4 70.00 280.00 82.00 328.00
14. STOP EA 21 80.00 1,680.00 200.00 4,200.00
15. REFLECTIVE pVMT MARKERS EA 96 3.00 288.00 5.00 480.00
TOTAL OVERLAY ~4~5,622.80 $466,076.55*
~0. AVENUE BIKE PATH JAMES RIOLO MERIDIAN pAVING
ITEM UNIT UNIT TOTAL UNIT TO'I'AL
NO. OESCRIPTION MEAS OTY pRICE pRICE PRICE PRICE
16. CLEAR A-ND GRUB LS 1 5,000.00 5,000.00 9,600.00 9,600.00
17.F EARTHWOPd< CY 335 80.00 26,800.00 30.00 10,050.00
18.F AC & AB BIKE PATH SECTION SF 18,000 1.20 21,600.00 .65 11,700.00
19. ROADWAY SECTION SF 12,000 5.30 63,600.00 4.00 48,000.00
20. CATCH BASIN/21"RCP LS 1 4,700.00 4,700.00 2,000.00 2,000.00
21. ASPHALT COHCRETE CURD LF 1,050 4.00 4,200.00 3.70 3,885.00
22. BIKE PATH & STOP SIGNS EA 4 300.00 1,200.00 175.00 700.00
23. BIKE CROSSING SIGNS EA 4 300.00 1,200.00 240.00 960.00
24. BIKE PATH STRIPING LS 1 6,000.00 6,000.00 100.00 100.00
'--~5. TYPE III BAP~ICAOE LS i 200.00 200.00 550.00 550.00
TOTAL BIKE PATH $~34.500.00 ~~7'545'00
TOTAL PROJECT ~550.122.80 ~5~3~621.55'
* AMOUNTS REVISED AFTER VERIFICATION