HomeMy WebLinkAboutItem 6.1 Award of Bid 84-2 (2)AGENDA STATEMENT
MEETING DATE: February 27, 1984
SUBJECT:
Award of Bid - Contract 84-2
Sidewalk Replacement Program
EXHIBITS ATTACHED:
Summary of Bids
RECOMMENDATION:
1) Award bid to Ambo Concrete
in the amount of $66,288.50
2) Authorize Mayor to execute contract
on behalf of City
FINANCIAL STATEMENT:
Low bid received - $66,288.50
Tota~ budgeted for contract - $89,000
DESCRIPTION: This project was approved mid-year as an
addition to the 1983-84 Capital Improvement Budget.
Subsequently, the City Council authorized Staff to advertise
for bids on this project. The City received bids (see
attached). The lowest bid was received from Ambo Concrete,
Inc. in the amount of $66,288.50
The total amount approved for this project in the 1983-84
budget was $100,000, and is broken down as follows:
Contract $89,000
Engineering & Inspection 11,000
Total $100,000
The contract quantities were based on estimated quantities
of work. We expect actual measured quantities to differ
slightly and that additional locations will surface during
construction.
It is estimated that construction will begin in about one
month and extend an additional 3 to 4 months.
ITEM NO. ~' / COPIES TO: Bidders
Item
Description
CONTRACT 84-2
SIDEWALK REPLACEMENT PROGRAM
Breakdown of Bids received 2/22/84
Engineer Ambo MCE
Est. Concrete Corp.
P & F Maker
Constr. & Sons
2.
3.
4.
5.
TOTALS
Sidewalk Remove and
Replace
Curb and Gutter Remove
and Replace
Asphalt Concrete
Saw cut Sidewalk
Trench and Root Shield
$71,240
$50,005.00
$58,225.00
$60,417.00 $58,225.00
2,000 684.00 1,900.00 800.00 2,000.00
2,300 2,127.50 1,955.00 2,530.00 3,450.00
9,900 10,800.00 12,420.00 17,352.00 19,008.00
$88,840.00 $66,288.50 $77,900.00 $83,549.00 $85,783.00
3,400 2,672.00 3,400.00 2,450.00 3,100.00