HomeMy WebLinkAboutItem 7.6 Contract 84-6 SR Rd Improvements Phase I (2)AGENDA STATEMENT
CITY COUNCIL MEETING DATE: August 13, 1984
SUBJECT:
Contract 84-6 $_~n Ramon Road
.Im~rov~m~nt~__.(Pha~e I) and Median Break-
Silvergate Drive/Silvertree Lane
EXHIBITS ATTACHED:
RECOMMENDATION:
FINANCIAL STATEMENT:
Plans and specifications will be
available at the City Council meeting.
Authorize staff to advertise Contract
84-6 for bids
Total funds budgeted - $92,000
DESCRIPTION: This contract consists of two separate
projects which were approved by the City Council as part of
the 1984-85 annual budget. The projects are similar in
nature, and have been combined for reasons of economy of
scale.
San Ramon Road Improvements (Phase I) provides one
additional traffic lane for motorists traveling north bound
on San Ramon Road through the intersection of Amador Valley
Boulevard. This project will require pavement widening,
restriping and the relocation of signal equipment at the
northeast corner of the intersection.
The Silvergate Drive/Silvertree Lane Median Break project
would provide for the modification of the existing raised
median on Silvergate Drive to permit direct access to
Silvertree Lane from Silvergate Drive.
The budget estimates for these projects are broken down as
follows:
San Ramon Road
Silvergate Drive
Design, Inspection $ 9,000 $ 4,000
Construction 66,000 13,000
Subtotals $75,000 $17,000
Total Project
$92,000