HomeMy WebLinkAboutItem 4.05 Demolition of Illegal Bldgs San Ramon Rd (2) AGENDA STATEMENT
CITY COUNCIL MEETING DATE: February 24 , 1986
SUBJECT: Demolition of Illegal Buildings and
Structures at 7360 San Ramon Road
EXHIBITS ATTACHED: 1) Bid from Anamac Inc .
2 ) Bid from Peeters-Mayflower
3 ) Bid from Amador Worldwide Moving
and Storage
RECOMMENDATION: 1) Direct City Attorney to prepare a
contract to remove materials and
r►� personal property from buildings to
�J be demolished.
2 ) Award contract to the low
bidder.
3 ) Authorize the MCE Corporation to
remove the buildings on a time and
material basis .
FINANCIAL STATEMENT: $50, 000 has been appropriated for
demolition of the building. The
Judgement provides that all costs to the
City in performing the abatement be
charged to .and paid by the owner.
DESCRIPTION: This involves five buildings and
structures which were built prior to the incorporation
without necessary permits from the county.
No. 1 is a 19 ' x60 ' addition at the rear of the main
building. This was built in April, 1977 .
No. 2 is a 17 'x90 ' addition on the South side of the main
building. This was built in November, 1980 .
No. 3 is a 16 'x30 ' storage shed.
No. 4 is a 8 'x12 ' storage shed.
No. 5 is an uncovered storage rack.
The date of construction of buildings #3, #4 , and #5 are
unknown but were built prior to 1977 .
On October 8, 1984 , the City Council directed the City
Attorney to commence action to abate the building and zoning
violations at the address . This action resulted in The
Stipulation for Entry of Judgement.
The Stipulation for Entry of Judgement set forth a series of
steps which would result in the construction of the
buildings to code or the construction of a new building and
the abatement of the illegal buildings within one year. It
also provided that if the owner failed to accomplish the
steps within the time .specified that the City was authorized
to do whatever necessary to remove the illegal buildings and
structures .
Simply stated the owner has to:
1 . Discontinue outdoor display of wares and merchandise
except for plant materials (for the plant nursery
operation) authorized by Section 8-48 . 2 of the Dublin
Zoning Ordinance by July 17, 1985 .
2 . Remove all excess signage by July 17 , 1985 .
3 . Remove the office trailer by August 16, 1985 .
4 . Submit an application for" a Site Development Review
(for the illegal additions or for a building to replace
them) by September 15, 1985 .
5 . Submit complete plans and an application for a building
permit 90 days after the approval of the Site
Development Review.
6 . Remove the buildings and structures 60 days after the
issuance of a building permit, or by June 15, 1986
whichever occurs first.
-----------------------------------------------------------------
ITEM NO. COPIES TO: John Nichandros
7360 San Ramon Rd.
If items #1, #2 or #3 were not accomplished in the time
specified the City was authorized to demolish the buildings
and structures .
On January 13 , 1986 the City Council authorized advertising
for bids for demolition and removal of the illegal building
and structures and obtain bids for moving material and
personal property from the buildings prior to demolition.
These bids were obtained from moving and storage as follows :
1 . ANAMAC MOVING $4, 661 . 50
2 . PEETERS-MAYFLOWER $12, 750 . 00
3 . AMADOR -WORLDWIDE MOVING & STORAGE $20, 068 . 80
It has subsequently been determined that an incomplete
application for a Planned Development rezoning did satisfy
the requirement of item number 4 ,above . Therefore,
abatement cannot proceed until June 16, 1986 . In light of
past actions it is unlikely that the owner will have
complied with the Judgement by that time .
Notice to Contractors was sent to all six demolition
contractors listed in the local phone directory. No bids
were received on the demolition contract.
It is recommended that the contract be awarded to the low
bidder for the removal of material and personal property
from the buildings and structures and that MCE Corporation
be authorized to do the required demoliton on a time and
material basis . Work is to begin June 16, 1986 .
ANAMAC MOVING
Febraury 11 , 1986
City Council
City of Doublin
State of California
Ref : Seal Bid Proposal .
This Bid cover the services cost of Local Moving , Packing and
storing of merchandise , wares , landscaping material , supplies ,
equipment and personal property placed at 7360 San Ramon Road
Dublin , Ca .
COST OF SERVICES .
Local Moving $ 2 , 704 . 00
Packing 1 , 112 . 50
Storage and Insurance per one Month 845 . 00
$ 4 , 661 . 50
WORK TO BE DONE .
Remove all merchandise , wares , landscaping material , equipment
supplies , personal property from building labeled A . B . C . D . E.
by the City Council of Dublin , State of California from the
the premises located at 7360 San Ramon Rd . Dublin .
CONTRACT TERM AND CONDITIONS .
1 . The City of Dublin will pay the cost of store and insurance
from the first month , after that the owner will be paying
for it .
2 In the event the City cancels the Contract , liquidated
damages will be 10% of the Bid .
3 . Payment will be made by the City of Dublin approximately
30 days after completion .
If you have any questions please contact ANAMAC MOVING (415)
449-7911 or 449-8209 .
Sincerely ,
Steve McGuigan �''y
THIS IS NOT A CONTRACT
PROBAU'"' Lc' COST OF S11'1"VOICES
ANAA"C INC.
3996 MT. RAINIER CT. PLEASANTON, CALIF. 94566
Phone: (415) 8$i>f,
*y 9-2111
NAME Phone No.W •Q,? 2Date
Moving From X?.11,0,),9.41 �i� ,(�✓ 4& j//.f! Region❑ Date of Packing
Moving To Region❑ Date of Moving
Charge To (Corporation) Delivery Requested
Shipper requests advice of weiqht and charges ❑ yes ❑ no. Contact Address Phone
SERVICES REQUESTED: DISTANCE MOVE ❑ HOURLY MOVE ❑ PIECE MOVE❑
No.of articles to be moved No.of rooms to be moved Total No.of packing containers to be supplied by carrier
Approximate Weight Total cu.ft. (from Table of Measurements)_@ 7 lbs.per cu.ft. lbs.
LONG DISTANCE MOVING LOCAL MOVING
Tariff Total Cu. Ft. Miles Estimate of Hours: Load rive(x2)—LUnload
Released valuation to be not exceeding Total�Hrs.
9 cents per lb.per article Moving Estimated/r/„/_ hours for �yan and
Est.Weight lbs.at per 100 lbs.$ men at 1r U�cl�per hour $C2
No. Flights/Long Carry at per 100 lbs.$ Piano,type 7 No. Flights )$
Hoisting/Lowering . . . . . . . . . . . . . . . . . . . . . $ Bridge or Ferry Tolls (Estimated) . $
Extra pick up—Delivery (circle one) . $ Hoisting/Lowering . . , . . , . , . , , $
Haul to—from storage in transit hours . . . . $ OTHER SERVICES $
Storage and Warehouse handling lbs.@ $ OVERTIME RATES:
Piano,type organ,type $ Valuation Charge . . . . . . . . . $
Appliances to service $
Other Services . . . . . . . . . . . . . . . . . . . . . . . . . . $ Released valuation at 60 cents per pound per article or the
• $
Valuation Charge . . . . . . . . . . lump sum value declared by the shipper$.. . . . . . . . . . . . . $
S.I.T. Valuation Charge . . . . . . STORAGE. . . . . . . . . . . . . . $ Probable Cost$
ESTIMATED RATE PER MONTH Cwt.or
If this shipment is subject to distance rates, and a mini- Open Space Storage,estimated cubic ft.$
mum charge (greater than otherwise applicable) is to
apply,the following statement must be completed: Cwt.or
Charges shall be computed on the actual weight of the Pallet Storage cubic ft.$
shipment or on a weight of pounds, Piano$ Upholstered Furniture$ $
whichever produces the higher charge. Rugs$ Vault Storage$ Drapes$ $
PACKING AND UNPACKING Probable Cost $— Insurance$ at per$100.00 $
LABOR,Pack at residence, Estimated packers PRELIMINARY SERVICES (Apply to First Month Only)
hours,at ..'�> per man hour$ � [w Mothtreating and Wrapping for Storage (estimated) . $
Unpack,estimated packers hours at Warehouse Labor, . , . . . . , . . . $
per man hour . . . . . . . . . . . . . $ Probable First Month Inc.Storage$
Delivery of packing material . . . . . . . . . . . . . . . . . . $ MAILING ADDRESS:
MATERIAL Quantity Charge per unit
Dish packs or barrels . . . $ LOCAL MOVING . . . . . . . . . . . . . . . . . . . . . . . . $
Cartons over 1%2 cu.ft. $ STORAGE . . . . . . . . . . . . . . . . . . . . . . $
Cartons over 3 cu.ft. $ LONG DISTANCE MOVING . . . . . . . . . . . . . . . . $
Cartons over 4%2 cu.ft. ,/_S�[� 1 $ /�`�`cZJ PACKING AND/OR UNPACKING . . . . . . . . . . . . . . $,/ff'7..S�j'
Cartons over 6 cu.ft. $ Valuation . . . . . . . . . . . . $
Wardrobes . . . . . . . . . $ CHARGES TO BE PAID BY: TOTAL PROBABLE COSTS S�O
Mattress ctn.single . . . . $ Cash ❑ Certified Check ❑ M.O. ❑ Credit Card ❑ Personal Check ❑
Mattress ctn.double . . . $ REMARKS:
Mattress ctn.queen $
Mattress ctn. king . . . . $
Mattress ctn.crib . . . . . $
Glass Packs t J'
cra=wo!. $ '92Y•�U
Probable Cost$
IMPORTANT This probable cost document covers only the articles and services listed on the Basis for Carriers Probable Cost o
NOTICE: Services document. IT IS NOT A GUARANTEE THAT THE ACTUAL CHARGES WILL NOT EXCEED THE
AMOUNT OF THE PROBABLE COST. No guarantee can be made as to specific dates of pickup or delivery unless you make special
arrangements with the carrier.for expedited service for which an additional chortle will normally he made.
NOTICE TO ESTIMATOR: It is mandatory to use cubic footage for each article as shown on the Table of Measurements and the total cubic footage be
multiplied by not less than seven to determine the total approximate weight. I have provided the shipper with a copy of this document.
Informational material entitled "IMPORTANT INFORMATION FOR SHIPPERS OF HOUSEHOLD GOODS(within Califor-
nia),”and "IMPORTANT NOTI TO S�HII OF H USEHOLD GOODS (Loss and Damage)" given to shipper ❑
Estimator's Signature Date
Form 220 R STOCK PRI NG CORP.—1220 Maple Ave., Los Angeles,California 90015
..�,.vaN' .",i'.it e.!`'...5::`..F�'--=+�.:t�::3.ei..:t:••••.a'••w^. ....:asm'x.::,'ra'tLerrr:.'?e°,••,•.r:se.�xr.,:ause:ci�s�xv:.itr.s'•ss`c+.w;rtu7:'.sruarvruw�t'uwy.�^.n:�ar�w.m.v::;.vwevx�;es'.NSaars'ot„tuuar�cnt:.:. :.:,,s.:;..:e.a �x:nux...,......,...
;rste�, R.c +k
M ” A ' uer.�
YWRLD.IMDE�MOVING,.,,�•
PEETERS MAYFLOWER
PEETERS VAN&STORAGE / 6967 SIERRA CT. l DUBLIN, CA 94568 / (415)828-6020
February 12, 1986
Mr. Victor L. Taugher
Building Official
City of Dublin
6500 Dublin Blvd.
Dublin, CA. 94568
Dear Mr. Taugher:
Thank you for the opportunity to present our bid for
moving services from 7630 San Ramon Rd. , Dublin to
our storage facilities in Dublin.
The bid price to complete all moving services per
specification No 02-86 is $12,750.00. Our carrier
liability for this bid is .30� per lb. per article,
unless a specific valuation is declared.
Should the bid be cancelled within 5 working days of
commencement of the move, our liquidated charges would
be 207 of the bid package.
We look forward to being of service to the City of Dublin
and if you have any questions, please call me at 828-6020.
Jim Ha "art
Sincerely,
gg
Office and Industrial Consultant
JH/sc
y
MEMBER MAYFLOWER WAREHOUSEMEN'S ASSN. AGENT FOR AERO MAYFLOWER TRANSIT CO.. INC.
I C.C.NO.MC—1934
y
Amador Worldwide Moving & Storage ;A
lei)
6500 Sierra Court, Dublin, California 94568 415/828-8210 ;
Outside California 800/227-0752 • In California 800/621-6201
February 3 , 1986
City of Dublin C'.`�
P . O. .Box 2340
Dublin , CA 94568 ,
Attn : Victor L. Taugher , Building Official
re : Specification #02-86
Dear Sir :
With regard to the removal of merchandise , i:rares , building materials ,
landscaping materials , supplies , equipment and personal property
at 7360 San Ramon Road , Dublin , California and storing said materials
in a safe and secure manner , our bid is as follows :
Cartons required for packing 3420 @ 1 . 00 each = $3420 . 00
Packing labor 315 manhours @ 28 . 85 per manhour= 9087 . 75
Moving goods into storage(only)
83 hours for a van and 2 men @64 . 35per hour= 5341 . 05
Flat charge for first month ' s storage = 810 . 00
Flat charge warehouse handling(one-time) = 810 . 00
Liquidated damages in event City of Dublin should
cancel contract-consulting time 8 hrs . @$75. 00 hr . = 600 . 00
Total Bid $20 , 068 . 80
Each subsequent month of storage(30-day period will be chargeable
at rate of first month . This amount is not included in the above total .
Should the City of the owner require access to the . goods once they
are in the storage warehouse , an appointment must be made in advance
and a labor charge of $25 . 00 per manhour shall be assessed . This
amount is not included in the above total .
The released valuation of the goods will be calculated on the basis
of 60 cents per pound based on a constructive weight of 7 lbs . per
cubic foot of space . Additional coverage is available at $1 . 00 per
each $1000 . 00 of declared value per month .
If there are any additional questions regarding this bid , please
address them to myself or Carey Swiers .
Respectfully ubmitted ,
6--�Bryan Grether