HomeMy WebLinkAboutItem 4.6 Sierra Ct Southerly Extension (2) CITY OF DUBLIN
AGENDA STATEMENT
City Council Meeting Date: June 9, 1986
SUBJECT: Sierra Court Southerly Extension
Contract 86-7
EXHIBITS ATTACHED: Plans and specifications will be available at the City
Council meeting.
�Jx`
RECOMMENDATION• Authorize Staff to advertise Contract 86-7 for bids
FINANCIAL STATEMENT: Project funds budgeted: $ 588,000
Estimated project cost:
Design/inspection 63,000
Construction 525,000
Total: 588,000
DESCRIPTION:
This project provides for the extension of Sierra Court through the Dublin
Sports Grounds to provide access to the Civic Center site. The project includes
street improvements, street lighting, and utilities. It also includes reconstruction
of those playfields which are displaced, additional Sports Grounds parking areas,
park restrooms, relocation of a park storage facility, and drainage facilities.
During Fiscal Year 1985-86, the City purchased 10 acres adjacent to the Dublin
Sports Grounds for the construction of a Civic Center. Optimum access to the
property requires an extension of Sierra Court through the Dublin Sports Grounds. The
City has agreed to a number of conditions imposed by the Dublin San Ramon Services
District in order to extend the road across the Sports Grounds.
This project will be funded from the proceeds of the City's $11,968,000
Certificate of Participation issue for the Civic Center facility. Construction is
scheduled to begin following the Little League season and conclude prior to the
beginning of the rainy season. Details of the land exchange will be finalized during
the bidding process.
-------------------------------------------------------------------------------------
ITEM N0. 44 COPIES TO: