HomeMy WebLinkAbout4.02 Dublin Sq Acctp WorkJ !
~~~;~~
~~ ~-~
1 ~~~
CITY CLERK
File # ^~~~-~~
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: January 6, 2009
SUBJECT: Acceptance of Work -Contract Number 08-07,
Dublin Square Demolition
Report prepared by: Herma Lichtenstein, Parks & Facilities
Development Manager
ATTACHMENTS: 1) Resolution accepting the Dublin Square Shopping Center
Demolition Contract 08-07.
2) Change Order #2
RECOMMENDATION: 1) Approve Change Order # 2 for $39,000;
2) Authorize the City Manager to accept the final improvements;
(~ , . 3) Adopt Resolution accepting the Dublin Square Shopping Center
Q/~ Demolition Contract 08-07.
FINANCIAL STATEMENT: Total Base Bid $348,750
10% Contingency $ 34,875
Total Contract $383,625
Approved Change Orders $ 11 650
Pending Change Orders $ 39 000
Amount in Excess of Contingency ($ 15,775)
DESCRIPTION: On June 26, 2008 the City Council awarded the contract for the
demolition of the Dublin Square Shopping Center to Ferma Corporation. At this time Ferma has
completed the majority of the work with the exception of remediation work associated with underground
fuel tanks that were discovered as a result of the demolition. The cost for this work is $39,000 and is in
excess of the City Manager's authority for approval and requires City Council authorization. At this time
there are sufficient funds within the overall project budget for the amount requested to complete the work
as the bid for the work was less than the $600,000 originally budgeted.
As the timing for completion of the remediation will be in advance of the next City Council meeting Staff
is requesting that the City Council authorize the City Manager to accept the final improvements for
Contract No. 08-07 once the remediation work is complete.
COPY TO: Ferma Corporation
Page 1 of c ~_
ITEM NO. •
G:\COIJNCIL\Agenda Statements\2009\1-6 Dub Sq Demo Square Acceptance.doc
r~
RECOMMENDATION: It is the recommendation of Staff that the City Council take the
following action: 1) Approve Change Order #2 for $39,000; 2) Authorize the City Manager to accept the
final improvements; and 3) Adopt Resolution accepting the Dublin Square Shopping Center
Demolition Contract 08-07.
aka
!;~ 3
RESOLUTION NO. -
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
ACCEPTING DUBLIN SQUARE SHOPPING CENTER DEMOLITION
CONTRACT NO. 08-07
WHEREAS, Ferma Corporation entered into a contract with the City of Dublin to complete the
Demolition of the Dublin Square Shopping Center in accordance with plans and specifications on file
with the City Engineer; and
WHEREAS, said improvements have been completed in accordance with said plans and
specifications, and any approved modifications thereof, with the exception of remediation of minor items,
to the satisfaction of said City Engineer of the City of Dublin; and
NOW, THEREFORE BE IT RESOLVED that:
1. The work is completed per plans and specifications with the exception of remediation of
minor items, and the City Manager has the authority to approve and accept the
improvements upon remediation of minor items; and
2. The said original performance bond posted in connection with the work involved in the
construction of said improvements be hereby released upon approval and acceptance of
work by the City Manager.
PASSED, APPROVED AND ADOPTED, this 6th day of January, 2009.
AYES:
NOES:
ABSENT:
ABSTAIN:
ATTEST:
City Clerk
Mayor
ATTACHMENT #1
G`~.~ OF~jDpB~~ ~,,{ ~1i
19 ' } ,ffi 4~'~ /
~~~~~~ CITY OF DUBLIN ~. 100 CIVIC PLAZA, DUBLIN, CALIFORNIA 94568 + (925) 833-6630 + (925) 829-9248 FAX
O~IItpRN~~
CONTRACT CHANGE ORDER NO. 2
PROJECT: Dublin Square Demolition, 11825 Dublin Blvd PAGE 1 OF 1
TO: Ferma Corporation
AGREEMENT DATED June 26, 2008
between Ferma Corporation and the City
of Dublin
You are hereby directed to make the herein described changes from the scope of services or do the following described work not included
in the scope of services on this contract. The description of work to be done, estimate of quantities, and prices to be paid are
complete, accurate and segregate between additional work at contract price, agreed price and force account. Unless otherwise
stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle
time.
NOTE: This change order is not effective until approved by the City Manager
Change requested b :The City of Dublin
The last percentage shown is the net accumulated increase or decrease from the original fee in the Agreement
1. Additional Demolition & Removal of Underground Fuel Tanks and Soil due to unforeseen conditions.
Extension of time: None
SUBMITTED BY:
APPROVAL RECOMMENDED BY
Herma Lichtenstein Date
Parks & Facilities Develop. Manager
COST INCREASE: $39,000
APPROVED BY
Melissa Morton Date Joni Pattillo Date
Public Works Director City Manager
we, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is
approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all
services necessary for the work above specified, and will accept as full payment therefore the prices shown above.
Accepted, Date:
By
Contractor: Ferma Corporation.
Project Manager: Joe Broz
I, the undersigned contractor declare under penalty of perjury under the laws of the State of California, and do personally
certify and attest that: I have thoroughly reviewed the attached request for change order and know its contents, and said
request for change order is made in good faith; that it is supported by truthful and accurate data; that the amount requested
and the additional time requested accurately reflects the allowable expenses that would be incurred, and the time necessary, to
perform the change order; and further, that I am familiar with California Penal Code section 72 and California Government
Code section 12650, et seq., pertaining to false claims, and further know and understand that submission or certification of a
false claim may lead to fines, imprisonment, or other severe legal consequences. If the Contractor does not sign acceptance of
this order, his/her attention is directed to the requirements of the specifications as to proceeding with the ordered work and
filing a written protest within the time therein specified
ATTACHMENT 2
CITY OF DUBLIN v ~ ~°
EXHIBIT "A" CHANGE ORDER FORM
DATE: 1 211 812 0 0 9
PROJECT NAME: Dublin Square Shopping Center Demolition
CIP #: 95557
CONTRACT NO. 08-07
CHANGE ORDER NO. 2
PERCENT COMPLETE: 87%
CONTRACTOR: Ferma Corporation
CONTRACT AMOUNT: $348,750
C.O. AS °/ OF CONTRACT: 15%
ADJUSTED CONTRACT AMOUNT: 5399,400
Original Contract Work Days 90
Added Contract Work Days
ADJUSTED CONTRACT WORK DAYS: 90
CONTRACT CHANGE ORDERS: AMOUNT
CHANGE ORDER #01 Unforseen Grading Requirements $ 11,650
CHANGE ORDER #02 Unforseen underground tank removal 8 remediation $ 39 000
TOTAL OF ALL CHANGE ORDERS: $ 50,650
PROGRESS PAYMENTS MADE:
PAYMENT #01 $ 104,625
PAYMENT#02 $ 85,375
PAYMENT#03 $ 114,463
PAYMENT #04
PAYMENT #OS
PAYMENT #O6
PAYMENT #07
PAYMENT #O8
PAYMENT #09
PAYMENT #10
PAYMENT #11
PAYMENT #12
TOTAL ACTUAL PAYMENTS: S 304,463
ADJUSTED TOTAL CONTRACT: $399,400
REMAINING BALANCE ON CONTRACT: 594,937
Upon execution by representatives authorized to bind the parties, this Change Order will become a part of the contract. The
consideration specified in this Change Order (whether an adjustment of the contract price, an adjustment of time, and/or other
consideration) is the full and sole compensation owed to the contractor as a result of the changes and issues described in this
Change Order. Such consideration includes, but is not limited to, any and all direct and indirect costs incurred by the
contractor as a result of the changes and issues described in this Change Order for any labor, equipment, materials, overhead
(additional, extended, field and home office), profit, or time adjustments. By signing this Change Order the contractor waives
and releases the owner from any and all claims for additional compensation concerning any of the changes and issues
specified in this Change Order.
The undersigned, being the (Title) of the Contractor, by signing this Changer Order
declares under penalty of perjury under the laws of the State of Califomia, and does personnaly certify and attest that: the
undersigned has thoroughly reviewed the attached request for change order and knows its contents, and said request for
change order is made in good faith; that it is supppoded by truthful and accurate data; that the amount requested and the
additional lime requested accurately reflect the allowable expenses that would be inccumed, and the time necessary, to
perform the change order; and further, that the undersigned is familiar with Califomia Penal Code Section 72 and Califomia
Government Code Section 12650 et seq., pertaining to false cliams, and further knows and understands that the submission or
certification of a false claim may lead to fines, imprisonment, or other severe legal consequences.
SIGNATURE:
Supervising Dept. Head City Manager Mayor
RECOMMENDATION:
APPROVED APPROVED APPROVED
DENIED DENIED DENIED