Loading...
HomeMy WebLinkAbout4.04 Consulting Svcs Agmt Amend~~~ \ . ~~. ~.. \\V/~' CITY CLERK File # ^^~O ^~ Q-^3 AGENDA STATEMENT CITY COUNCIL MEETING DATE: June 16, 2009 SUBJECT: Amendments To Existing Consulting Services Agreements Report Prepared by.• Melissa Morton, Public Works Director ATTACHMENTS: 1) December 2008 Consumer Price Index 2) Resolution Approving Amendments to Agreements, together with Amendments: Exhibit "A," Kimley-Horn & Associates Exhibit "B," Omni-Means, LTD Exhibit "C," TJKM Transportation Consultants Exhibit "D," Berlogar Geotechnical Consultants Exhibit "E," BSK Associates Exhibit "F," Cal Engineering & Geology, Inc. Exhibit "G," RBF Consulting Exhibit "H," SNG & Associates, Inc. Exhibit "I," Mark Resolve, Inc. RECOMMENDATION: Adopt the Resolution approving the Amendments to the Agreements with Kimley-Horn & Associates, Omni-Means, LTD, TJKM .~ Transportation Consultants, Berlogar Geotechnical Consultants, BSK Associates, Cal Engineering & Geology, Inc., RBF Consulting, SNG & Associates, Inc., and Mark Resolve, Inc. FINANCIAL STATEMENT: Under the existing Agreements, the consultants provide services to the City based on individual adopted rate schedules. Types of services performed are of four types: 1) Traffic Engineering; 2) Geotechnical (Soils) Engineering; 3) General Engineering; and 4) Construction Conflict Resolution. Services provided for private development are paid for by developers, or budgeted within each CIP project for the City's Capital Improvement Program (CIP). COPY TO: Consultants Page 1 of 4 ITEM NO. G:\CONSLTL.TANTS\agstamend 9 consultants 09-10.doc Section 2.9 of each Consulting Services Agreement specifies that the Consumer Price Index (CPI) for Urban Wage Earners for the San Francisco-Oakland Bay Area shall be used to govern rate increases requested by the consultant. The December 2008 CPI registered a negative 0.2%. Section 2.9 also states that the consultants' adjusted rates cannot be less than the initial rates (contained in Exhibit "B" of each consultant's Agreement). None of the consultants are requesting rate increases for Fiscal Year 2009-2010. DESCRIPTION: The City of Dublin's Public Works Department currently contracts with 13 consulting firms. Each of the Agreements is for atwo-year term, with 9 of these Agreements expiring on June 30, 2009. Staff believes it is prudent to continue contracting for the services of these consulting firms; therefore, Amendments to the Agreements are necessary to extend the terms for another two years. The remaining four Agreements will not expire until June 30, 2010, and Staff will return to the City Council at that time for approval to extend those Agreements. Following are the major categories of the consulting services provided and a summary for each consultant in that category. TRAFFIC ENGINEERING Kimley-Horn & Associates has contracted with the City since 2001 to provide traffic engineering services, primarily in the area of preparing traffic studies and other traffic-related services associated with private development projects, as well as traffic studies for CIP projects. The most current Agreement was approved on July 5, 2005, for atwo-year term, which expired June 30, 2007. The term of the Agreement was then extended for an additional two years to June 30, 2009, and a rate increase was allowed per Section 2 for the second year of the Agreement in Fiscal Year 2008-2009. Omni-Means, LTD, has provided traffic engineering services to the City since 1996. These services have primarily been in the area of peer review, preparing private development traffic studies, and other traffic- related services associated with private development projects. These services are paid for by developers. The most current Agreement was approved on June 21, 2005, and was for atwo-year term, which expired June 30, 2007. The term of the Agreement was then extended for an additional two years to June 30, 2009, and a rate increase was allowed per Section 2 for the second year of the Agreement in Fiscal Year 2008-2009. TJKM Transportation Consultants has contracted with the City since 1983 to provide traffic engineering services to the City. Types of services performed are typically private development traffic studies, which are paid for by developers at TJKM's standard rates, and general traffic engineering work, which is paid from the City's operating budget and is billed at rates that are reduced from TJKM's standard rates. Work on Capital Projects is at standard rates. TJKM provides a specific per-task estimate for each project and obtains written authorization from the City before proceeding. The most current Agreement was approved on June 21, 2005, and was for atwo-year term, which expired June 30, 2007. The term of the Agreement was then extended for an additional two years to June 30, 2009, and a rate increase was allowed per Section 2 for the second year of the Agreement in Fiscal Year 2008-2009. GEOTECHNICAL ENGINEERING Berlogar Geotechnical Consultants has provided geotechnical engineering services to the City since 1996. Services provided have typically been in the areas of peer review for private development projects and Page 2 of 4 Staff support and testing services. Staff typically obtains anot-to-exceed proposal from the consultant for each project. Costs for development-related projects are paid for by developers, and costs for CIP-related projects are budgeted within each specific project. The current Agreement was approved on July 19, 2005, and was for atwo-year period, which expired June 30, 2007. The Agreement was then extended for an additional two years to June 30, 2009. The consultant did not request a rate increase for Fiscal Year 2008-2009, which was the second year of the extended term of the Agreement. BSK Associates has provided general materials and soils testing and geotechnical services since 1995, primarily in the area of testing for City CIP projects and geotechnical peer review for private development projects. The consultant provides specific per-task estimates for each project and obtains written authorization from the City before proceeding. The cost related to CIP projects is budgeted within each project, and the cost related to private developments is paid for by developers. The most current Agreement was approved on July 5, 2005, and was for atwo-year term, which expired June 30, 2007. The term of the Agreement was then extended for an additional two years to June 30, 2009, and a rate increase was allowed per Section 2 for the second year of the Agreement in Fiscal Year 2008-2009. Cal Engineering_& Geology, Inc. entered into a Consulting Services Agreement with the City on April 18, 2006, to provide geotechnical engineering services. The firm is currently performing peer review for the Fallon Village project, with costs for the work being paid for by private developers. On June 19, 2007, the most current Agreement was extended for atwo-year term, which expired June 30, 2009, and a rate increase was allowed per Section 2 for the second year of the Agreement in Fiscal Year 2008-2009. GENERAL ENGINEERING RBF Consulting has provided general civil engineering and land surveying services to the City since 2003. This work is primarily associated with active land development and Capital Improvement Program (CIP) projects in the City, which is either paid for by developers or budgeted within individual CIP projects. The most current Agreement was approved on July 5, 2005, and was for atwo-year term, which expired July 19, 2007. The term of the Agreement was then extended for an additional two years to June 30, 2009, and a rate increase was allowed per Section 2 for the second year of the Agreement in Fiscal Year 2008-2009. SNG & Associates, Inc., has contracted with the City since 2002 for engineering services to perform private development review, planchecking and project close-out. These services are paid for by developers. The most current Agreement was approved on June 21, 2005, and was for atwo-year term, which expired June 30, 2007. The term of the Agreement was then extended for an additional two years to June 30, 2009, and a rate increase was allowed per Section 2 for the second year of the Agreement in Fiscal Year 2008-2009. CONSTRUCTION CONFLICT RESOLUTION Mark Resolve, Inc., entered into an Agreement with the City on September 4, 2007, to provide schedule analysis and construction conflict resolution. These services are a preventative measure to insure the City is protected against potential construction claims on larger CIP projects, such as the Dublin/Dougherty Intersection Improvements Project and the I-580/Fallon Road Interchange Improvements Project. This consultant did not request a rate adjustment for Fiscal Year 2008-2009, the second year of the Agreement. Page 3 of 4 RATE ADJUSTMENT FOR FISCAL YEAR 2009-2010 The work performed to date by these consultants has been satisfactory, professional and competitive. Each of these consultants has indicated the desire to extend the Agreement for an additional two-year period. The CPI for December 2008, which is the marker specified in Section 2.9 to govern the amount a consultant can request for an adjustment of its rates, registered as a negative 0.2% (Attachment 1). Section 2.9 states, "In no case shall the adjusted rates be less than the initial rates as set forth in Exhibit B." Therefore, the rates contained in Exhibit "B" of each consultant's most recent Amendment will continue to prevail in this Agreement for Fiscal Year 2009-2010. The four consultants who are in the second year of their Agreements have also stated they are not requesting a rate adjustment for Fiscal Year 2009-2010. RECOMMENDATION: Staff recommends that the City Council adopt the Resolution approving the Amendments to the Agreements with Kimley-Horn & Associates, Omni-Means, LTD, TJKM Transportation Consultants, Berlogar Geotechnical Consultants, BSK Associates, Cal Engineering & Geology, Inc., RBF Consulting, SNG & Associates, Inc., and Mark Resolve, Inc. Page 4 of 4 IMPORTANT NOTICE: As of April 1, 2008, subscribers will no longer receive paper copies of the Pacific Cities CPI Summary in mail. The Pacific Cities CPI summary will continue to be available on the Internet at http://www.bls.gov/ro9/pachist.htm. a ~~ A - 1,500,000 population and over Release date January 16, 2009. scheduled for March 18, 2009. '"~, ~ Anchorage (907) 271-2770 -~ Honolulu (808) 541-2808 ~ ~ "„' - „'°° ° ~°~~ ~~ NvNuiauv~i UaSn (-) = NOI HV8118DIe. The next monthly and semi-annual releases are scheduled to be issued on February 20, 2009. The next bi-monthly releases are Los Angeles (310) 235-6884 Portland (503) 326-5818 Phoenix (480) 503-9075 San Diego (619) 557-6538 This card is available on the day of i ~' questions, please contact us at BLSi --~. ~ "'~„ • CONSUMER PRICE INDEXES PACIFIC CITIES AND U. S. CITY AVERAGE DECEMBER 2008 ALL ITEMS INDEXES rd QR9_AA-4rlfl .. nl........aa.....a.... _ a_~~ All Urban Consumers (CPI-U) Urban Wage Earners and Clerical Workers (CPI-W) Percent Chan a Percent Chan e MONTHLY DATA Indexes Year 1 Month Indexes Year 1 Month endin endin endin endin Dec. Nov. Dec. Nov. Dec. Dec. Dec. Nov. Dec. Nov. Dec. Dec. 2007 2008 2008 2008 2008 2008 2007 2008 2008 2008 2008 2008 U. S. City Average ................................ 210.036 212.425 210.228 1.1 0.1 -1.0 205.777 207.296 204.813 0 7 -0 5 -1 2 (1967=100) ...................................... 629.174 636.332 629.751 - - - 612.948 617.472 610 075 . - . - . _ Los Angeles-Riverside-Orange Co...... 219.373 222.229 219.620 1.0 0.1 -1.2 212.282 214.083 . 211.007 0.6 -0 6 -1 4 (1967=100) ...................................... 648.124 656.562 648.854 - - - 627.357 632.681 623 591 - . - . _ West ..................................................... 214.733 217.113 214.685 1.0 0.0 -1.1 209.488 210.870 . 208.088 0.6 -0 7 -1 3 (Dec. 1977 = 100) .......................... 347.103 350.952 347.027 - - - 337.054 339.278 334 801 - . - . _ West - A* .............................................. 218.020 220.925 218.698 1.3 0.3 -1.0 211.095 213.143 . 210.637 0.9 -0 2 -1 2 (Dec. 1977 = 100) .......................... 355.512 360.248 356.618 - - - 341.722 345.037 340 980 - . - . _ West - B/C"`(Dec. 1996=100) .............. 130.481 131.440 129.725 0.7 -0.6 -1.3 130.309 130.684 . 128.641 0.3 -1.3 -1.6 All Urban Consumers (CPI-U) Urban Wage Earners and Clerical Workers (CPI-W) Percent Chan a Percent Chan e BI-MONTHLY DATA Indexes Year 2 Months Indexes Year 2 Months endin endin endin endin Dec. Oct. Dec. Oct. Dec. Dec. Dec. Oct. Dec. Oct. Dec. Dec. 2007 2008 2008 2008 2008 2008 2007 2008 2008 2008 2008 2008 San Francisco-Oakland-San Jose........ 218.485 225.824 218.528 3.6 0.0 -3.2 214.204 221.192 213.685 3.8 -0 2 -3 4 (1967=100) ...................................... 671.683 694.247 671.815 - - - 652.270 673.547 650 689 - . . _ Seattle-Tacoma-Bremerton ................... 218.966 225.915 222.580 3.4 1.7 -1.5 214.024 220.687 . 216.424 3.6 1 1 -1 9 (1967=100) ...................................... 667.495 688.676 678.511 - - - 634.795 654.557 641.914 - . - . _ uc tlistribution. Just go to www.bls.g or (415)625-2270. San Francisco (415) 625-2270 Seattle (206) 553-0645 sign up ror the tree on-line ~w` Iv Z~2~ RESOLUTION NO. - 09 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN APPROVING AMENDMENTS TO AGREEMENTS FOR ENGINEERING SERVICES WITH KIMLEY-HORN & ASSOCIATES, INC., OMNI-MEANS, LTD, TJKM TRANSPORTATION CONSULTANTS, BERLOGAR GEOTECHNICAL CONSULTANTS, BSK ASSOCIATES, CAL ENGINEERING & GEOLOGY, INC., RBF CONSULTING, SNG & ASSOCIATES, INC., AND MARK RESOLVE, INC. WHEREAS, the City of Dublin ("the City") and the firms of KIMLEY-HORN & ASSOCIATES, INC., OMNI-MEANS, LTD, TJKM TRANSPORTATION CONSULTANTS, BERLOGAR GEOTECHNICAL CONSULTANTS, BSK ASSOCIATES, CAL ENGINEERING & GEOLOGY, INC., RBF CONSULTING, SNG & ASSOCIATES, INC., AND MARK RESOLVE, INC. ("the Consultants"), have previously entered into two-year Agreements ("the Agreements") whereby the Consultants have agreed to provide certain engineering services on an as-needed basis; and WHEREAS, the City and the Consultants now desire to extend the terms of the Agreements an additional two years until June 30, 2011; and WHEREAS, the rate schedule contained in each Consultant's most current Amendment shall remain in effect for Fiscal Year 2009-2010 as allowed by Section 2.9 of the Agreement; and WHEREAS, the attached Amendments to the Agreements have been reviewed and approved as to form by the City Attorney's Office; NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby approve the Amendments, attached hereto as Exhibits "A" through "I". BE IT FURTHER RESOLVED that the Mayor is authorized to execute the Amendments on behalf of the City. PASSED, APPROVED AND ADOPTED this 16th day of June, 2009, by the following vote: AYES: NOES: ABSENT: ABSTAIN: ATTEST: Mayor City Clerk ATTACHMENT Z. 3 ~Z~ EXHIBIT "A" OF RESOLUTION -09 AMENDMENT TO AGREEMENT BETWEEN CITY OF DUBLIN AND KIMLEY-HORN AND ASSOCIATES, INC. FOR TRAFFIC ENGINEERING SERVICES WHEREAS, the City of Dublin (hereinafter referred to as "CITY") and Kimley-Horn and Associates, Inc. (hereinafter referred to as "CONSULTANT"), entered into atwo-year agreement on July 5, 2005, to provide traffic engineering services to CITY; and WHEREAS, on July 3, 2007, said agreement was subsequently extended for an additional two-year term to June 30, 2009; and WHEREAS, CITY and CONSULTANT wish to extend the term of the agreement for an additional two years, terminating June 30, 2011; and WHEREAS, CONSULTANT will maintain the rate schedule previously adopted June 17, 2008; NOW, THEREFORE, the parties hereto agree as follows: Section 1. Extension of Term The term of the agreement shall be extended from July 1, 2009, to June 30, 2011. Should a new agreement or amendment to agreement to extend the contract not be entered into by June 30, 2011, then this agreement will automatically extend until a new agreement or amendment to agreement is entered into or CITY gives written notice of termination. Section 2. Rate Schedule The rate schedule attached hereto as Exhibit 1 shall be in effect for Fiscal Year 2009-2010. CITY OF DUBLIN Tim Sbranti, Mayor ATTEST: City Clerk KIMLEY-HORN ANA-ASSOCIATES, INC. Randy Du~nberger, Vice Date: ~/Z ~ ~U ~ G:\CONSiJLTANTS\Kimley-Hom\amendment 09-10.doc EXHIBIT ~ ~2t~ KIMLEY-HORN 2009-2010 FEE SCHEDULE 2009-2010 CLASSIFICATION RATE Al-A3 Senior Support Staff $ 84 A4 Senior Support Staff 118 A5 Senior Professional 1 205 C1-C3 Support Staff 78 C4-C6 Senior Support Staff 83 C03-C04 CADD Operator 102 C05-C06 Senior CADD Operator 107 D7 Designer 118 D8 Senior Designer 129 E1-E4 Principal 215 P Professional 97 P1 Professional 1 113 P2 Professional 2 118 P3 Professional 3 129 P4 Professional 4 140 P5 Senior Professional 1 162 P6 Senior Professional 2 182 P7 Senior Professional 3 194 P8 Principal 215 T1-T2 Technician/Draftsman 1-2 75 T3-T5 Technician/Draftsman 3-5 97 T6-T7 Senior Technician 107 G:\CONSULTANTS\Kimley-Horn\Exhibit 1 new agreement 09-10.doc ~~ao EXHIBIT "A" OF RESOLUTION -09 AMENDMENT TO AGREEMENT BETWEEN CITY OF DUBLIN AND OMNI-MEANS, LTD FOR TRAFFIC ENGINEERING SERVICES WHEREAS, the City of Dublin (hereinafter referred to as "CITY") and Omni-Means, LTD (hereinafter referred to as "CONSULTANT"), entered into atwo-year agreement on June 21, 2005, to provide traffic engineering services to CITY; and WHEREAS, on June 19, 2007, said agreement was subsequently extended for an additional two-year term to June 30, 2009; and WHEREAS, CITY and CONSULTANT wish to extend the term of the agreement for an additional two years, terminating June 30, 2011; and WHEREAS, CONSULTANT will maintain the rate schedule previously adopted June 17, 2008; NOW, THEREFORE, the parties hereto agree as follows: Section 1. Extension of Term The term of the agreement shall be extended from July 1, 2009, to June 30, 2011. Should a new agreement or amendment to agreement to extend the contract not be entered into by June 30, 2011, then this agreement will automatically extend until a new agreement or amendment to agreement is entered into or CITY gives written notice of termination. Section 2. Rate Schedule The rate schedule attached hereto as Exhibit 1 shall be in effect for Fiscal Year 2009-2010. CITY OF DUBLIN Tim Sbranti, Mayor ATTEST: City Clerk G:\CONSiJLTANT5lomni-means\amendment 09-10.doc OMNI-MEA LTD ~--- ~-LS H. Ross Ai sworth, President Date: 5'24 (09 EXHIBIT ~ Tn +hA RACnIi itinn c~~zo OMNI-MEANS 2009-2010 CHARGE RATE FEE SCHEDULE 2009-2010 CLASSIFICATION RATE Consultant (Branch Manager) $ 192 Traffic Engineer 3 126 Technician 3 ~ 100 G:\CONSULTANTS\omni-means\exhibit 1 amendment 08-09 Omni.doc ~~ LD EXHIBIT "A" OF RESOLUTION -09 AMENDMENT TO AGREEMENT BETWEEN CITY OF DUBLIN AND TJKM TRANSPORTATION CONSULTANTS FOR TRAFFIC ENGINEERING SERVICES WHEREAS, the City of Dublin (hereinafter referred to as "CITY") and TJKM Transportation Consultants (hereinafter referred to as "CONSULTANT"), entered into atwo-year agreement on June 21, 2005, to provide traffic engineering services to CITY; and WHEREAS, on June 19, 2007, said agreement was subsequently extended for an additional two-year term to June 30, 2009; and WHEREAS, CITY and CONSULTANT wish to extend the term of the agreement for an additional two years, terminating June 30, 2011; and WHEREAS, CONSULTANT will maintain the rate schedule previously adopted June 17, 2008; NOW, THEREFORE, the parties hereto agree as follows: Section 1. Extension of Term The term of the agreement shall be extended from July 1, 2009, to June 30, 2011. Should a new agreement or amendment to agreement to extend the contract not be entered into by June 30, 2011, then this agreement will automatically extend until a new agreement or amendment to agreement is entered into or CITY gives written notice of termination. Section 2. Rate Schedule The rate schedule attached hereto as Exhibit 1 shall be in effect for Fiscal Year 2009-2011. CITY OF DUBLIN Tim Sbranti, Mayor TJKM TRANSPORTATION CONSULTANTS ~~~~~ Chris D. Kinzel, President ATTEST: City Clerk G:\CONSULTANTS\TJKM (see new address amendment 09-10.doc Date: 'L ~ 'Z Do ~ EXHIBIT C. Tn tha Racnli itinn ~ ~~zo 2009-2010 CHARGE RATE FEE SCHEDULE TJKM TRANSPORTATION CONSULTANTS 2009-2010 Standard (a) Reduced (b) CLASSIFICATION TJKM Rate City of Dublin Principal $231 $209 Principal Associate 209 194 ITS Director/Modeler 204 182 Senior Associate 204 182 Associate 166 154 Senior Traffic Engineer 154 144 Traffic Engineer 139 122 Contracts Director 132 105 Assistant Traffic Engineer 127 102 Assistant Planner 94 72 Senior Designer 105 100 Graphics Designer 105 100 Designer 89 77 Technical Staff 82 72 Technical Staff II 33 33 Administrative Staff 89 59 Production Staff 56 49 (a) These rates shall apply to capital improvement design work and private development review as indicated in the master agreement. (b) These rates are typically reduced from TJKM's standard rates, and shall apply to general traffic engineering services, excluding capital improvement design and review. G:\CONSULTANTS\TJKM (see new address)\exhibit 1 amendment 09-10 TJKM.doc ~ Sao EXHIBIT "A" OF RESOLUTION -09 AMENDMENT TO AGREEMENT BETWEEN CITY OF DUBLIN AND BERLOGAR GEOTECHNICAL CONSULTANTS FOR GEOTECHNICAL ENGINEERING SERVICES WHEREAS, the City of Dublin (hereinafter referred to as "CITY") and Berlogar Geotechnical Consultants (hereinafter referred to as "CONSULTANT"), entered into a two-year agreement on July 19, 2005, to provide geotechnical engineering services to CITY; and WHEREAS, on June 19, 2007, said agreement was subsequently extended for an additional two-year term to June 30, 2009; and WHEREAS, CITY and CONSULTANT wish to extend the term of the agreement for an additional two years, terminating June 30, 2011; and WHEREAS, CONSULTANT will maintain the rate schedule adopted on June 19, 2007; NOW, THEREFORE, the parties hereto agree as follows: Section 1. Extension of Term The term of the agreement shall be extended from July 1, 2009, to June 30, 2011. Should a new agreement or amendment to agreement to extend the contract not be entered into by June 30, 2011, then this agreement will automatically extend until a new agreement or amendment to agreement is entered into or CITY gives written notice of termination. Section 2. Rate Schedule The rate schedule attached hereto as Exhibit 1 shall be in effect for Fiscal Year 2009-2010. CITY OF DUBLIN Tim Sbranti, Mayor ATTEST: City Clerk G:\CONSLTLTANTS\berlogazlamendment 09-10.doc BERLOGAR GEOTECHNICAL CONSULTANTS Fr rlog President ~` 7G Ol Date: "- EXHIBIT ~ Tn the RP~nlution I~sblD BERLOGAR GEOTECHNICAL CONSULTANTS 2009-2010 FEE SCHEDULE 2009-2010 CLASSIFICATION RATE Principal Engineer $ 193 Principal Geolgogist 193 Associate Engineer 163 Associate Geologist 163 Senior Engineer 144 Senior Geologist 144 Staff Engineer 132 Staff Geologist 132 Supervising Technician 134 Laboratory Technician 100 Senior Engineering Technician 100 Engineering Technician 91 Draftsman 90 Word Processor 61 Clerical 43 G:\CONSULTANTS\berlogar\Exhibit 1 fee schedule 09-10.doc ~~~~o EXHIBIT "A" OF RESOLUTION -09 AMENDMENT TO AGREEMENT BETWEEN CITY OF DUBLIN AND BSK ASSOCIATES FOR GEOTECHNICAL ENGINEERING SERVICES WHEREAS, the City of Dublin (hereinafter referred to as "CITY") and BSK Associates (hereinafter referred to as "CONSULTANT"), entered into atwo-year agreement on July 19, 2005, to provide geotechnical engineering services to CITY; and ' WHEREAS, on June 19, 2007, said agreement was subsequently extended for an additional two-year term to June 30, 2009; and WHEREAS, CITY and CONSULTANT wish to extend the term of the agreement for an additional two years, terminating June 30, 2009; and WHEREAS, CONSULTANT will maintain the rate schedule previously adopted June 17, 2008; NOW, THEREFORE, the parties hereto agree as follows: Section 1. Extension of Term The term of the agreement shall be extended from July 1, 2009, to June 30, 2011. Should a new agreement or amendment to agreement to extend the contract not be entered into by June 30, 2011, then this agreement will automatically extend until a new agreement or amendment to agreement is entered into or CITY gives written notice of termination. Section 2. Rate Schedule The rate schedule attached hereto as Exhibit 1 shall be in effect for Fiscal Year 2009-2010. CITY OF DUBLIN Tim Sbranti, Mayor ATTEST: City Clerk G:\CONSULTANTS\bsk\amendment 09-10.doc BSK ASSOCIATES Elizabeth A. Levi, Branch Manager Date: EXHIBIT ~• Tn tha RPCnIi itinn 12 s~ Z~ BSK ASSOCIATES 2009-20010 FEE SCHEDULE CLASSIFICATION PROFESSIONAL: Senior Principal Principal Associate Principal Senior Professional Project Professional II Project Professional I Staff Professional Junior Professional 2009-2010 RATE $ 161 150 140 129 118 107 97 85 FIELD TECHNICAL: Supervisor $ 97 Inspector 80 Technician 80 OFFICE AND LABORATORY TECHNICAL: Supervisor $ 97 Technician 65 Draftsman 65 Word Processor 43 General Typist/Office Aide 32 G:\CONSULTANTS\bsk\exhibit 1 amendment 09-10 BSK.doc ~3~ 20 E~BIT "A" OF RESOLUTION -09 AMENDMENT TO AGREEMENT BETWEEN CITY OF DUBLIN AND CAL ENGINEERING AND GEOLOGY, INC. FOR GEOTECHNICAL ENGINEERING SERVICES WHEREAS, the City of Dublin (hereinafter referred to as "CITY") and Cal Engineering and Geology, Inc. (hereinafter referred to as "CONSULTANT"), entered into an agreement on April 18, 2006, to provide geotechnical engineering services to CITY; and WHEREAS, on June 19, 2007, said agreement was subsequently extended for an additional two-year term to June 30, 2009; and WHEREAS, CITY and CONSULTANT. wish to extend the term of the agreement for an additional two yeazs, terminating June 30, 2011; and WHEREAS, CONSULTANT will maintain the rate schedule previously adopted June 3, 2008; NOW, THEREFORE, the parties hereto agree as follows: Section 1. Extension of Term The term of the agreement shall be extended from July 1, 2009, to June 30, 2011. Should a new agreement or amendment to agreement to extend the contract not be entered into by June 30, 2011, then this agreement will automatically extend until a new agreement or amendment to agreement is entered into or CITY gives written notice of termination. Section 2. Adjustment of Rates The rate schedule attached hereto as Exhibit 1 shall be in effect for Fiscal Yeaz 2009-2010 CITY OF DUBLIN Tim Sbranti, Mayor ATTEST: City Clerk CAL ENGINEERING AND GEOLOGY, INC. itchell D. Wolfe, P ' cipal Geologist Date• S'7u - D~ G:ICONSULTANTSCaIEng&Geonamendment 09-10.doc EX H I B I T ~. To the Resolution ~ ~t~ a~ CAL ENGINEERING AND GEOLOGY, INC. 2009-2010 FEE SCHEDULE 2049-2010 CLASSIFICATION RATE Principal Engineer or Geologist $ 171.00 Associate Engineer or Geologist 149.00 Senior Engineer or Geologist 123.00 Project Engineer or Geologist .96.00 Technician 80.00 G:\CONSITLTANTS\CalEng&Geol\Exhibit 1 fee schedule 09-10.doc 1 ~~ 2'~' EXHIBIT "A" OF RESOLUTION -09 AMENDMENT TO AGREEMENT BETWEEN CITY OF DUBLIN AND RBF CONSULTING FOR ENGINEERING SERVICES WHEREAS, the City of Dublin (hereinafter referred to as "CITY") and RBF Consulting (hereinafter referred to as "CONSULTANT"), entered into atwo-year agreement on April 19, 2005, to provide engineering services to CITY; and WHEREAS, on June 19, 2007, said agreement was subsequently extended for an additional two-year term to June 30, 2009; and WHEREAS, CITY and CONSULTANT wish to extend the term of the agreement for an additional two years, terminating June 30, 2011; and WHEREAS, CONSULTANT will maintain the rate schedule previously adopted June 3, 2008; NOW, THEREFORE, the parties hereto agree as follows: Section 1. Extension of Term The term of the agreement shall be extended from July 1, 2009, to June 30, 2011. Should a new agreement or amendment to agreement to extend the contract not be entered into by June 30, 2011, then this agreement will automatically extend until a new agreement or amendment to agreement is entered into or CITY gives written notice of termination. Section 2. Rate Schedule The rate schedule attached hereto as Exhibit 1 shall be in effect for Fiscal Year 2009-2010. CITY OF DUBLIN Tim Sbranti, Mayor ATTEST: City Clerk RB 'ON3TJLTIN i Garrett Gritz, Vice President Date: ~ ` ~~'ap G:ICONSULTANTS~RBF\amendment 09-10.doc EXHIBIT Gam. Tn the Rocnli i+inn i~~~2o RBF CONSULTING EFFECTIVE THROUGH JUNE 30, 2010 OFFICE PERSONNEL / Hr. Senior Principal $236.98 Principal 214.86 Project Director 192.90 Project Manager 167.53 Structural Engineer 167.53 Electrical Engineer 147.69 Senior Engineer/Senior Planner 148.80 Landscape Architect 135.57 Project Engineer/Project Planner 127.84 Environmental Specialist 123.45 Corrosion Engineer 123.45 Design Engineer/Senior Designer/Mapper 119.03 Designer/Planner 103.61 GIS Analyst 99.20 Graphic Artist 88.17 Environmental Analyst/Staff Planner 88.17 Design Technician 85.97 Assistant Engineer/Planner 81.58 Engineering Aid/Planning Aid 66.14 FIELD PERSONNEL 2-Person Survey Crew $225.96 1-Person Survey Crew 159.82 Licensed Surveyor 161.15 Field Supervisor 152.10 CONSTRUCTION MANAGEMENT PERSONNEL Construction Manager $165.33 Resident Engineer/Project Manager 137.51 Senior Construction Inspector 108.01 Construction Inspector 115.13 Field Office Technician 99.20 Construction Technician 85.97 OTHER SERVICES AND FEES Permit Processor $104.71 Clerical/Word Processing 55.11 Consultation Relative to Legal Actions 297.61 Vehicle Mileage 0.66/mile Note: Blueprinting, reproduction, messenger service and other direct expenses will be charged as an additional cost plus 15%. ASub-consultant Management Fee of fifteen-percent (15%) will be added to the direct cost of all sub-consultant services to provide for the cost of administration, sub-consultant consultation and insurance. G:\CONSULTANTS\RBF\exhibit 1 amendment 09-10.doc ~~a~ ~ ~ EXHIBIT "A" OF RESOLUTION -09 AMENDMENT TO AGREEMENT BETWEEN CITY OF DUBLIN AND SNG & ASSOCIATES, INC. FOR ENGINEERING SERVICES WHEREAS, the City of Dublin (hereinafter referred to as "CITY") and SNG & Associates, Inc. (hereinafter referred to as "CONSULTANT"), entered into atwo-year agreement on June 21, 2005, to provide engineering services to CITY; and WHEREAS, on June 19, 2007, said agreement was subsequently extended for an additional two-year term to June 30, 2009; and WHEREAS, CITY and CONSULTANT wish to extend the term of the agreement for an additional two years, terminating June 30, 2011; and WHEREAS, CONSULTANT will maintain the rate schedule previously adopted June 17, 2008; NOW, THEREFORE, the parties hereto agree as follows: Section 1. Extension of Term The term of the agreement shall be extended from July 1, 2009, to June 30, 2011. Should a new agreement or amendment to agreement to extend the contract not be entered into by June 30, 2011, then this agreement will automatically extend until a new agreement or amendment to agreement is entered into or CITY gives written notice of termination. Section 2. Rate Schedule The rate schedule attached hereto as Exhibit 1 shall be in effect for Fiscal Year 2009-2010. CITY OF DUBLIN Tim Sbranti, Mayor ATTEST: City Clerk G:\CONSULTANTS\SNG\amendment 09-10.doc SNG & ASSOCIATES, INC. Nanda Gottiparthy, P.E. Date: ~ 2. ~ 2 c~ ~ ~ EXHIBIT To the Resolution l~~~ SNG & ASSOCIATES. INC. 2009-2010 CHARGE RATE FEE SCHEDULE 2009-2010 CLASSIFICATION RATE Principal Engineer $ 122 Senior Engineer 116 Associate Engineer 100 Clerical 44 G:ICONSULTANTS\SNG\exhibit 1 amendment 09-10.doc EXHIBIT "A" OF RESOLUTION -09 AMENDMENT TO AGREEMENT BETWEEN CITY OF DUBLIN AND MARK RESOLVE, INC. FOR SCHEDULE ANALYSIS AND CONSTRUCTION CONFLICT RESOLUTION SERVICES WHEREAS, the City of Dublin (hereinafter referred to as "CITY") and Mark Resolve, Inc. (hereinafter referred to as "CONSULTANT"), entered into an agreement on September 4, 2007, to provide schedule analysis and construction conflict resolution services to CITY; and WHEREAS, CITY and CONSULTANT wish to extend the term of the agreement for an additional two years, terminating June 30, 201 l; and WHEREAS, CONSULTANT will maintain the rate schedule previously adopted September 4, 2007; NOW, THEREFORE, the parties hereto agree as follows: Section 1. Extension of Term The term of the agreement shall be extended from July 1, 2009, to June 30, 2011. Should a new agreement or amendment to agreement to extend the contract not be entered into by June 30, 7.011, then this agreement will automatically extend until a new agreement or amendment to agreement is entered into or CITY gives written notice of termination. Section 2. Rate Schedule The rate schedule attached hereto as Exhibit 1 shall be in effect for Fiscal Year 2009-2010. CITY OF DUBLIN Tim Sbranti, Mayor ATTEST: City Clerk G:\CONSULTANTS1Mark Resolvelamendarent 09-10.doc OLVE, IN _ ~ i" Thomas so, Principle Date: EXHIBIT ~. Tn the RPCnIi itinn i, ~~ 8031 Sauthpark Circle Suite 100 Littleton, CO 80120 Phone:303-339-6651. Fa~c:303-339-6656 Emvlovee . Caruso, Thomas Giannecchini, Mark Rice, Angie Halvorson, Pam . . Hendershot, Lee Gravley, Melissa. Ti e Prinapal Principal Manager Senior Consultant Consultant. Associate Rates $325/hr. $285/hr . $240/hr $185/hr $160/hr $145/hr $60 /hr Project Assistants