HomeMy WebLinkAbout4.04 AdvertiseForBids 94-04 CITY OF DI~LIN
AGENDA STATEMENT
City Council Meeting Date: September 12, 1994
SUBJECT:
Dougherty Road/Sierra Lane Traffic Signal,
Contract 94-04
Report By: Lee Thompson, Public Works Director
EXHIBITS ATTACHED:
RECOMMENDATION:
Plans and Specifications will be available at the
meeting
Authorize Staff to advertise for bids
FINANCIAL STATEMENT:
Preliminary Engineering
(Environmental and Topo)
Design
Inspection/Construction Staking
Construction
Miscellaneous
Estimated
Prior Year 1994-95 Total
Expenditures Budqet Project
$ 41,753 $ -0- $ 41,753
23,656 3,050 26,706
-0- 25,100 25,100
-0- 252,000 252,000
-0- 850 850
TOTAL: $ 65,409 $ 281,000 $ 346,409
From Fund
ISTEA $ 183,291
Developer Contribution 73,116
Gas Tax 85,360
General Fund 4,642
TOTAL: $ 346,409
DESCRIPTION: This project will add a traffic signal at the
Dougherty Road/Sierra Lane intersection and make median and channelization
improvements on Dougherty Road between Sierra Lane and Dublin Boulevard.
A large portion of the construction cost of this project is being funded by a
Federal ISTEA grant, which was obtained in Fiscal Year 1993-94.
Plans and Specifications are complete and have been reviewed by Caltrans. Caltrans,
in turn, has given the City of Dublin authorization to go to bid on this project.
Staff recommends that the city Council authorize Staff to advertise Contract 94-04
for bids.
a:signal~agstauth
.................................. ! CITY CLERK
co i;[ ............