AGENDA STATEMENT
CITY COUNCIL MEETING DATE: September 15, 1998
SUBJECT:
Award of Bid - Contract 98-12, San Ramon Road Slope Repair
Report Prepared by: Public Works Director Lee Thompson
ATTACHMENTS:
1)
2)
3)
4)
Resolution of Award ·
Summary of Bids
Budget Change Form
Location Map
RECOMMENDATION:/-~ _ t3/~Cdoot resolution awarding bid to Golden Pacific Construction, Inc.
'~ and approve Budget Change Form
FINANCIAL STATEMENT: Costs for this project are budgeted in the Capital Improvement Budget
through the General Fund.
Construction Budget $170,000
Low Bid 167,705
Proposed Budget 184,500
Although the bid is below the Budget, Staff is recommending that a 10% contingency be
included to cover any unanticipated costs. This will require a Budget Change in the amount
of $14,500 from Unallocated Reserves.
DESCRIPTION: At the City Council meeting of August 18, 1998, the City Council
authorized Staffto solicit bids for Contract 98-12, San Ramon Road Slope Repair. This project is intended
to mitigate the slope failure west of San Ramon Road north of Vomac Road, which was caused by heavy
rains this past winter. The slope will be stabilized by excavating the slide area, installing a subdrain system
and constructing engineered fill.
Notices will be sent prior to the beginning of construction in order to advise residents of the work to be
performed.
A total of five (5) bids were received, with the low bid being submitted by Golden Pacific Construction,
Inc., in the amount of $167,705.00.
Staff has rewewed the low b~dder s propos , checked with references and recommends that the City
Council adopt the resolution awarding Contract 98-12 to Golden Pacific Construction, Inc.
gSmiscprojXsrslope\a~tawrd
COPIES TO: Golden Pacific
ITEM NO.
RESOLUTION NO. -98
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
AWARDING CONTRACT 98-12
SAN RAMON ROAD SLOPE REPAIR
TO GOLDEN PACIFIC CONSTRUCTION, INC.
WHEREAS, the City of Dublin did, on September 8, 1998, publicly open, examine,
and declare all saaled bids for doing the work described in the approved Plans, Specifications, and
Modifications for Contract 98-12, San Ramon Road Slope Repair, authorized by the City Council on
August 18, 1998, which Plans, Specifications, and Modifications are hereby expressly referred to for a
description of said work and for all particulars relative to the proceedings under the request for bids; and
WHEREAS, said bids were submitted to the City Engineer, who has recommended that
the bid hereinafter mentioned is the lowest and best bid for doing said work.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin
does hereby award City of Dublin Contract 98-12 to the lowest responsible bidder therefor, to wit Golden
Pacific Construction, Inc. with a bid of One Hundred Sixty-Seven Thousand Seven Hundred Five Dollars
and No Cents ($167,705.00), the particulars of which bid are on file in the Office of the City Engineer.
PASSED, APPROVED AND ADOPTED this 15th day of September, 1998.
AYES:
NOES:
ABSENT:
ABSTAINING:
Mayor
ATTEST:
City Clerk
g:~rniscproj~rslope[resoawrd
. TTACHMENT
BID RESULTS - SAN RAMON ROAD LANDSLIDE REPAIR, CONTRACT NO. 98-12
BID OPENING DATE - SEPTEMBER 8, 1998 I
I
I · ENGINEER'S ESTIMATE GOLDEN PACIFIC C.V. LARSEN CO.
BID UNIT
ITEM ITEM DESCRIPTION MEASURE QTY UNIT PRICE i TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE
I Mobilization LS 1 $ 1,000.00 $ 1,000.00 I $10,000.00 $ 10,000.00 $ 4,950.75 $ 4,950.75
2 IStripping SF 108,000 $ 0.03 $ 3,240.00 $ 0.25 $ 27,000.00 $ 0.14 $ 15,120.00
2A IStripping Off Haul SF 108,000 $ 0.10 $ 10,800.00 $ 0.05 $ 5,400.00 $ 0.13 $ 14,040.00
3 ISlide Area Excavatio~ CY 13,400 $ 4.00 $ 53,600.00 $ 2.00 $ 26,800.00 $ 4.00 $ 53,600.00
4 ' Bororow Area Excavation CY 2,000 $ 2.00 $ 4,000.00 $ 3.00 $ 6,000.00 $ 1.94 $ 3,880.00
5 Slide Area F CY 14,400 $ 4.00 $ 57,600.00 $ 2.00 $ 28,800.00 $ 4.25 $ 61,200.00
6 I U~_~u~'-~b!e Material Off Haul CY 1,000 $ 5.00 $ 5,000.00 $ 1.25 $ 1,250.00 $ 4.50 $ 4,500.00
7 tVeeDitch LF 294 $ 20.00 $ 5,880.00 $ 40.00 $ 11,760.00 $ 19.16 $ 5,633.04
8 16 Inch Pipe LF 614 $ 15.00 $ 9,210.00 $ 30.00 $ 18,420.0~ $ 19.87 $ 12,077.38
9 18Inch Pipe LF 255 $ 15.00 $ 3,825.00 $ 35.00 $ 8,925.00 $ 4.60 $ 1,173.00
10 112 Inch Pipe LF 177 $ 20.00 $ 3,540.00 $ 50.00 $ 8,850.00 $ 9.68 $ 1,713.36
11 I Drain Structure 1 LS 1 $ 1,500.00 $ 1,500.00 $ 1,500.00 $ 1,500.00 $ 1,921.54 $ 1,921.54
12 IDrain Structure 2 LS 1 $ 1,500.00 $ 1,500.00 $ 1,000.00 $ 1,000.00 $ 2,338.49 $ 2,338.49
13 Drain Structure 3 Modification LS I $ 1,000.00 $ 1,000.00 $ 1,200.00 $ 1,200.00 $ 1,444.32 $ 1,444.32
14 Hydroseed SF 108,000 $ 0.08 $ 8,64D.00 $ 0.10 $ 10,800.00 $ 0.04 $ 4,320.00
TOTAL BID: $170,335.00 $167,705.00 $ 187,911.88 -"--
· ADJUSTED TOTALS A~- ~ =r~ AMOUNTS CORRECTED I
I
REDGWICK CONST. ROYAL SEAL ASPHALT ClMARRON CONST.
BID UNIT UNIT PRICE I
ITEM ITEM DESCRIPTION MEASURE QTY TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE
1 IMobilization LS I $14,400.00 $ 14,400.00 $30,000.00 $ 30,000.00 $10,000.00 I $ 10,000.00
2 Stripping SF 108,000 $ 0.08 $ 8,640.00 $ 0.20 $ 21,600.00 $ 0.15 $ 16,200.00
ZA Stripping Off Haul SF 108,000 $ 0.08 $ 8,640.00 $ 0.16 $ 17,280.00 $ 0.26 $ 28,080.00
3 SlideArea Excavation CY 13,400 $ 6.65 I $ 89,110.00; $ 3.40 $ 45,560.00 $ 2.50 $ 33,500.00
4 Bororow Area Excavation CY 2,000 $ 4.25 I $ 8,500.00 i $ 2.80 $ 5,600.00 $ 3.00 $ 6,000.00
5 Slide Area Fill CY 14,400 $ 2.75 $ 39,600.00 $ 4.00 $ 57,600.00 $ 5.80 $ 83,520.00
6 Unsuitable Materia Off Hau CY 1,000 $ 10.00 $ 10,000.00 $ 14.00 $ 14,000.00 $ 16.00 $ 16,000.00
7 VeeDitch LF 294 $ 35.00 $ 10,290.00 $ 38.00 $ 11,172.00 $ 25.00 $ 7,350.00
8 6Inch Ppe LF 614 $ 20.00 $ 12,260.00 $ 18.00 $ 11,052.00 $ 28.00 $ 17,192.00
181nchPipe LF 255 $ 15.00 $ 3,825.00 $ 33.00 $ 8,415.00 $ 20.00 $ 5,100.00
12 inch Pipe LF 177 S 35.00 $ 6,195.OO $ 32.OD $ 5,664.OD $ 25.00 $ 4,425.00
11 tDrainStructurel LS 1 $ 2,500.00 $ 2,500.00 $ 1,200.00 $ 1,200.00 $ 800.00 $ 800.00
12 tDrainStructure2 LS I $ 2,500.00 $ 2,500.00 $ 1,200.00 $ 1,200.00 $ 800.00 $ 800.00
13 IDrainStructure3Modification LS 1 $ 1,000.00 $ 1,000.00 $ 1,200.00 $ 1,200.00 $ 600.00 $ 600.O0
14 lHydroseed SF 108,000 S 0.04 $ 4,320.00 $ 0.03 $ 3,240.00 $ 0.0~ $ 5,400.00
t
ITOTAL BID: I $ 221,800.00 $ 234,783.00 $ 234,987.O0
T,T'ACHMENT
CITY OF DUBLIN
BUDGET CHANGE FORM
CHANGE FORM #.
New Appropriations (City Council Approval Required):
X
Budget Transfers:
From Unappropriated Reserves From Budgeted Contingent Reserve (1080-799.000)
· Within Same Department Activity
From New Revenues Between Departments (City Council Approval Required)
Other -
Name: Name:
San Ramon Slope Repair $14,500
Account#: Account#: 001-9664-750-050
Name: Name:
Account #: Account #:
Name: Name:
Account #: Account #:
City Manager: Date:
Signature
REASON FOR BUDGET CHANGE ENTRY:
Although the low bid for this project was under budget, the addition of a 10% contingency will increase the
needed budget by $14,500.
Mayor:
Signature
Posted By:
Signature
Date:
Date:
^TTACHME T
NO SCAEE
--PROJECT
DP-,
LOCATi. ON
HIGH
N
CAMP
PARK~
SHANNC
CNTR,
~0
ViC
\
1-580
CITY F1F DUBLIN PUBLIC WORKS DEPARTMENT
APPROVAL
SAN RAHDN ROAD
SLIDE REPAIR PROJECT
i~^VN KAS ICHECKEI) CHK
APPROVAL
LOCATION MAP
8/10/98 SCALE NONE
AITACHi ENT: N,