HomeMy WebLinkAbout4.4 Acceptance of Work, Project #98-10 Civic Center Fountain Pump ReplacementCITY CLERK
File # ❑���-❑2
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: October 6, 1998
SUBJECT:
EXHIBITS ATTACHED:
Acceptance of Work, Project #98-10 Civic Center Fountain Pump
Replacement
Report Prepared by: Lee S. Thompson, Public Works Director
None
RECOMMENDATION: ,/ Accept work performed by Paco Pumps and authorize payment in
the amount of $9,955.49.
4
FINANCIAL STATEMENT:
Design/Project Management
Advertising
Construction
Total funds budgeted:
This project was completed within funds budgeted.
$ 300.00
200.00
9.955.49
$10,455.49
$11,575,00 (all General Fund)
DESCRIPTION: On September 1, 1998, the City Council awarded a purchase order
for C.I,P. Project #98-10 to Paco Pumps. This project replaced the pump in the Civic Center's Plaza
Fountain with a lower horsepower pump. The old pump motor had failed and presented the opportunity
to install a more efficient motor.
The work has been completed satisfactorily, and the fountain is now operational.
Staff recommends that the City Council accept the work and authorize payment to Paco Pumps.
---------------------------------------------------------------
COPIES TO: Paco Pumps
ITEM NO. ��
G.\miscproj\ftnpu►np\agstacpt