HomeMy WebLinkAbout4.06 Accept Work 93-03 CITY OF DUBLIN
AGENDA STATEMENT
City Council Meeting Date: June 28, 1993
SUBJECT:
Acceptance of Work, Contract 93-03 Annual Sidewalk Safety
Repair (Remove and Replace)
Report by: Public Works Director Lee Thompson
EXHIBITS ATTACHED: None
Accept improvements constructed under Contract 93-03 and
authorize final payment in the amount of $2,958.82 to Ambo
Engineering, for a total contract amount of $29,588.15.
FINANCIAL STATEMENT:
Design/Survey/
Inspection/Misc.
Construction
Budgeted Amount
$10,000.00
40,000.00
Sidewalk Repair
Remove/Replace:
Grinding Contr.:
Actual cost
$ 6,500.00 (est.)
27,115.03 (Ambo)
9,903.00 (est.)
Total: $50,000.00 $43,518.03
Cost is paid from General Fund monies. The cost of design and inspection is
shown as an estimate at this time, as the separate Grinding contract is not
fully complete. The estimated cost of the grinding contract is shown for
informational purposes. Acceptance of the grinding work will be placed on a
future agenda.
Community Pool Handicap Access Ramp and Bike Pad
Bid Price
Actual Cost
$2,473.12 $2,473.12
Cost of the work at the Community Pool is paid from community Development
Block Grant (CDEG) and Parkland Dedication funding under the Dublin swim
Center Bathhouse Renovation (#9507) Capital Improvement Project. The
breakdown of charges is $1,023.12 from CDEG and $1,450 from Parkland
Dedication funds.
DESCRIPTION: On April 26, 1993, the City Council awarded Contract 93-03,
the Annual Sidewalk Safety Repair Program (Remove and Replace) to Ambo Engineering.
The annual sidewalk program replaces offset sidewalks which may become tripping
hazards.
This year, the annual sidewalk repair budget was divided between the traditional
replacement program and the new concrete grinding project. Offsets which were
caused by root damage and excessive ground movement were replaced, and the remaining
sidewalk offsets were ground level through Contract 93-0'7, which is with Central
Coast Surface Grinding.
The sidewalk repair project, which is now complete, also replaced a sidewalk at the
Community Swimming Pool to provide handicapped access and installed a new concrete
slab for bicycle racks.
The City Engineer has reviewed the work on the project and determined that it is
complete and in accordance with the approved specifications. Staff recommends that
the City Council accept the improvements and authorize final payment to Ambo
Engineering in the amount of $2,958.82.
a:~sidewalk~agstacpt
ITEM NO. ~ ~ COPIES TO: Ambo Engineering