HomeMy WebLinkAbout4.06 Accept Work 93-05 CITY OF DUBLIN
AOSNDA STATEMENT
City Council Meeting Date: June 14, 1993
SUBJECT:
Acceptance of Work - Contract 93-05, Street Subdrains
Report by: Public Works Director Lee Thompson
EXHIBITS ATTACHED: None
Accept improvements constructed under Contract 93-05
Authorize retention payment to Betchart and Norwood in
the amount of $4,626.82
FINANCIAL STATEMENT:
BUDGET ACTUAL COST
Design $ 2,500.00 $ 878.00
Inspection 4,600.00 2,989.00
Improvements 95,215.00 92,536.00
Miscellaneous
(Legal/printing) 180.00 811.00
$102,495.00
$ 97,214.00
DESCRIPTION: On April 12, 1993, the City Council awarded Contract
93-05, the Street Subdrain Project, to Betchart and Norwood.
Subdrains have been placed in locations where water is seeping under the street
sections, causing asphalt pavement failures. The water is originating from median
irrigation and from springs. These subdrains will intercept the water before it
gets under the street and will carry it off to a storm drain system. The result of
installing these subdrains is to extend the life of the street pavement section.
Streets that were included in the project are: Village Parkway (Dublin Blvd. north
to Kimball Avenue), Amador Valley Blvd. (east of York Drive), and Stagecoach Road
(end of median near Stagecoach Park).
The city Engineer has reviewed the work on the project and determined that it is
complete and in accordance with the approved plans and specifications. Staff
recommends tha~ the City Council accept the improvements and authorize retention
payment to Betchart and Norwood in the amount of $4,626.82.
a:subdrains~agstacpt
........... ............................................. 1 .... 'i'T'F---GtiE R K
ITEM NO.~ COPIES TO: Betchart and Norwood IFiLE