HomeMy WebLinkAbout4.07 AdvertiseForBids 98-9CITY CLERK
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: AUGUST4, '1998
SUBJECT:
Authorization To Solicit Bids for Contract 98-09, Shannon Center
Subdrain Project.
Report Prepared by: Lee S. Thompson, Public Works Director
EXI-IIBITS ATTACHED:
1)
2)
Map of Project Location
Plans and Specifications will be available at the
City Council meeting
RECOMMENDATION: ir~N!~-~Authorize Staffto advertise for bids
FINANCIAL STATEMENT: BLTDGET
Shannon Center
Subdrain Pro' el.~.~
Surveying (Topographic)
Design/Inspection/Field Staking
Construction
Miscellaneous (Legal, Printing)
$1,500
4,100
7,500
4O0
TOTAL $13,500
This project is budgeted from General Fund moneys.
DESCRIPTION: The east end of the Shannon Center parking lot has suffered accelerated wear and
tear due to water infiltration of the base material. This excess water comes from an underground spring
which surfaces in the east end of the parking lot. In order to maintain a parking surface that will survive
to a reasonable life expectancy, a subdrain system is necessary to intercept and remove the excess water.
This project will install a subdraln along the affected areas of the lot which will intercept underground
water and direct it to the nearby creek.
Plans and specifications have been prepared for bidding. Staff recommends that City Council authorize
Staffto advertise for bids on this Capital Improvements Project.
g:misepr oj~shnndrn~agstaut h
COPEES TO:
.: .:. ITEM NO,.