HomeMy WebLinkAbout4.07 AuthChangeOrder#1 96-2 CITY CLERK File # ~-][-~]~-'-1-[-~--'][~] AGENDA STATEMENT CITY COUNCIL MEETING DATE: May '14, 1996 SUBJECT: Change Order No. 1 to Add the Overlay of Dougherty Road. and Dublin Boulevard to the 1995/96 Annual Street Repair and Overlay, Contract 96-02 Report Prepared By: Lee S. Thompson, Public Works Director EXHIBITS ATTACHED: 1) 2) 3) Resolution Authorizing Change Order Change Order Form Location Maps RECOMMENDA:'I'ION: Authorize Change Order No. 1 incorporating the overlay of Dougherty Road (south of Amador Valley Boulevard) and Dublin Boulevard (between Hansen Drive and Donlon Way) into the 1995/96 Annual Overlay Project, Contract 96-02 .... FINANCIAL STATEMENT: This change order for $70,000 is within funds budgeted for the annual overlay program. The existing overlay contract was awarded for $70,000 less than budgeted to allow for the overlay of Dougherty road to be bid and constructed with the Dougherty Road ISTEA project. This change order will move the overlay for Dougherty Road, as well as a short section of Dublin Boulevard, to this year's Annual Overlay Program. By approv'mg this change order, the C~'oy will receive an additional $5,686 in SB 300 grant funds. DESCRIPTION: On March 26th, the City Council awarded the Annual Overlay Project, Contract 96-02 to O'Grady Paving. At that time, the overlay of Dougherty Road was taken out of this project scope with the intention of completing the work under the Dougherty Road Widening, which is to be funded by ISTEA and private Developer Fees. It now appears that delays to the Dougherty Road Widening project will put the award of the bid past the end of this fiscal year. SB300 funding terms mandate that work on these streets be contracted prior to the end of the current fiscal year in order to be eligible for matching funds. Staffis recommending that the repair and overlay of these streets be reassigned back to the current Overlay Project. g:\overlay\overlayLagstchng COPIES TO: O'Grady Paving ITEM NO. The Change Order to the City's existing contractor, O'Grady Paving, will be up to $70,000. This is over the City Manager's approval limit of up to 5% of the bid price, or not to exceed $25,000 (whichever is greater). Staffrecommends that Council adopt the Resolution authorizing the execution of Change Order No. 1 for the 1995/96 Annual Overlay Project. Page 2 RESOLUTION NO. 48 - 96 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN APPROVING A CHANGE ORDER FOR THE ANNUAL OVERLAY CONTRACT WHEREAS, it was originally intended to include the Dougherty Road overlay with the Dougherty Road Widening ISTEA Project; and WHEREAS, due to the delay in this Dougherty Road project, the Dougherty Road Widening Project will not be under construction before the end of the 1995/96 fiscal year; and WHEREAS, monies set aside to complete the overlay project for Dougherty Road must be used before the end of the 1995/96 fiscal year in order to obtain SB 300 matching funds; and WHEREAS, a change order is required to increase the quantities for the Annual Overlay project to accommodate both Dougherty Road between Amador Valley Blvd. and the Southern Pacific right of way and a section of Dublin Boulevard between Hansen Drive and Donlon Way; and WHEREAS, the amount of this change order exceeds the amount of money that the City Manager is authorized to approve. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby authorize the Mayor of the City of Dublin to execute a change order to include north bound Dougherty Road from the Southern Pacific right of way to south of Amador Valley Boulevard and Dublin Boulevard between Hansen Dr. and Donlon Way with the 1995/96 Annual Overlay Project (Number 96-02). PASSED, APPROVED AND ADOPTED this 14th day of May, 1996. AYES: Councilmembers Barnes, Burton, Howard, Moffatt and Mayor Houston NOES: None ABSENT: None ABSTAIN: None g:loverlayloverlaylresochngl Jt~/5- J 4- 96/resovrly. doc CITY OF DUBLIN CHANGE ORDER EXHIBIT "A" DATE: 05~09~96 F'ROJECT NAME Annual Street Repair and Overlay PROJECT CIP NBR 9658 3ONTRACT NBR 96-02 PERCENT COMPLT % APPVD CONTRACTOR O'GRADY PAVING :APPVD BUDGET AMT $345,119.00 APPVD CONTRACT AMT $ 329,291.96 CHANGE AMOUNT CHANGE QRDER NO. 1 $ 70,000.00 CHANGE ORDER NO. 2 $ CHANGE ORDER NO. 3 $ CHANGE ORDER NO. 4 $ CHANGE ORDER NO. 5 CHANGE ORDER NO. 6 $ CHANGE ORDER NO. 7 $ CHANGE ORDER NO. 8 1 $ CHANGE ORDER NO. 9 $ CHANGE ORDER NO. 1 TOTAL OF ALL CURRENT & PRIOR CHANGE ORDERS $ 70,000.00 I ADJUSTED CONTRACT AMOUNT $ 399,291.96 I PROGRESS PAYMENTS MADE: PAYMENT NO. 1 $ PAYMENT NO. 2 $ PAYMENT NO. 3 $ ~AYMENT NO. 4 $ PAYMENT NO. 5 $ PAYMENT NO. 6 $ PAYMENT NO. 7 $ PAYMENT NO. 8 $ PAYMENT NO. 9 $ PAYMENT NO. 10 $ TOTAL PROGRESS PAYMENTS $ I REMAINING BALANCE ON CONTRACT $ 399,291.96 RECOMMENDATION: APPROVEE~ [\~J APPROVED__ APPROVED__ DENIED ~J DENIED DENIED SUPERVISING CITY MANAGER MAYOR DEPT. HEAD U.S.. DEPT. OF ,JUSTICE CAMP PARKS MILITARY iRES ERVATIO N U.S. NAT. AERONAUTICS ¢SPACE ADM, -- O'GRADY PAVING INC. ~001 05/09/96 TttU 09:57 FAX 415 966_~!9~.~ ........ ~ CITY OF DUBLIN. EXHIBIT CONTRACT CHANGE ORDER NO, ] PROJECT~OAD TFEo:DIgR,~L N/~,($): ~i~n,~__u~l~ Overlay Project-City Wid~ PAGE I O1~ ' -A of Sou~ P~ific ~ght of way to sou~ of ~or V~ley Boul~d bid pri~s ~11 be ~d~ to overly lhe~ ~ street ESTIMATED COST INCREASE: ~ BY REASON OP THIS ORDEp,, THIg TIMId' O,F COMPLtgTIO]~ WILL BE ADJlJSTI~D , --~ - WORKJ[NG DAYS,