HomeMy WebLinkAbout4.10 Accept Work 89-7 CITY OF DUBLIN
AGENDA STATEFiENT
City Council Meeting Date: June 24,
1991
SUBJECT:
Acceptance of Work - Contract No. 89-7
Shannon Park Renovation
Report by Lee S. Thompson, Public Works Director
EXHIBITS ATTACHED:
1) Change Order No. 9
2) Change Order No. 10
3) Copy of Subcontractor Stop Notice
RECOMMENDATION:
1) Authorize approval of Change Order No. 9 for
$26,381.08, and Change Order No. 10 in the amount of
$17,785.29 as the total amount of Change Orders is
over the amount which the the City Manager is
authorized to approve.
2) Accept improvements under Contract 89-7
3) Authorize final progress and retention payment in
the amount of $50,414.83 to A.V.& C. Construction.
4) Authorize Staff to release $15,383.44 which is being
withheld due to a Subcontractor Stop Notice once the
Stop Notice has been legally cleared.
5) Authorize Staff to release $20,000 which is being
withheld as security for warranty items once those
items have been fixed.
6) Authorize the transfer of $388,096.43 to this
project from unallocated reserves.
FINANCIAL STATEMENT:
88-89 & Prior 89-90 90-91 TOTAL
Design $38,656.93 $ 22,257.83 $ 1,546.32 $ 62,461.08
Topography 4,178.64 2,727.97 0.00 6,906.61
Inspection 0.00 12,072.90 18,588.03 30,660.93
Printing 9.36 4,095.48 122.47 4,227.31
Improvements 0.00 408,917.79 ** 568,590.61 977,508.40
Soils Test 0.00 2,830.00 0.00 2,830.00
Legal 0.00 457.50 0.00 457.50
Other Improvements 0.00 * 12,105.17 0.00 12,105.17
TOTALS
$42,844.93 $465,464.64 $588,847.43 $1,097,157.00
* Work not under A.V.& C. contract (includes emergency lighting
work and parking lot pavement patching).
** $612,121.15 less $37,250.00 liquidated damages
Since most of this project was planned to be completed last fiscal year, only
$200,751 was budgeted for FY 90-91. It is necessary to authorize a transfer of
$388,096~43 from unallocated reserves in order to complete this project.
BUDGET ACTUAL
Design $ 59,451 $ 62,461.08
Topography 6,744 6,906.61
Inspection 29,000 30,660.93
Printing 3,900 4,227.31
Improvements 975,626 977,508.40*
Soils Test 2,830 2,830.00
Legal 428 457.50
Improvements by Others 0 12,105.17
TOTALS $1,077,979
$11097,157.00
*(including liquidated damages)
ITEM NO. COPIES TO: A.V.& C. Construction
DESCRIPTION: In October 1989, the City Council awarded Contract 89-7,
Shannon Park Renovation, to A.V.& C. Construction. The project improvements
included a complete renovation of the existing park with play areas for younger
and older children, a shallow pond and spray pool, a plaza area and two
fountains, landscaping and drainage improvements, an additional pedestrian
bridge over the creek, and parking and lighting improvements. Council also
approved Alternates for a railroad-tie path under the existing bridge, a
demonstration garden on the slope behind Shannon Community Center, and the
replacement of a concrete culvert headwall facing with a river rock culvert.
A.V.& C. Construction did not complete the improvements until 149 days after
the contract date of completion. The contractor was charged $37,250 ($250.00
per day) liquidated damages to defray the costs of the additional time for
inspection and contract administration, and loss of public use of the park.
During the course of construction, Change Orders were generated to correct the
existing condition of underground spring water in the parking lot, change the
water meter size, install a new park sign (the existing sign could not be
recycled as intended), adjust field dimensions from design dimensions for crib
retaining walls, and alter the wiring and lighting plan since the existing
lighting electrical service proved to be unserviceable. Change Orders No. 9
for additional grading on the slope behind Shannon Center and items of work
which were not included in the bid items (work under the bridge related to the
path and to drainage, additional electrical work, and handrail), and Change
Order No. 10 to balance the actual field quantities of work from the original
estimated bid quantities are attached to this Agenda Statement for City Council
approval. Approval by the City Council is required as the cumulative amount of
the Change Orders exceeds the limit which can be approved by the City Manager.
The total project is 5.2% over budget, partly due to Staff time for the project
completion delays by the contractor, but mostly due to unforeseen items such
as the lighting system having to be removed and replaced because of inadequate
as-built plans, the parking lot requiring extensive subdrain work and patch
paving, and due to items designed into the plans and not included in the
contract pay items.
The sum of $15,383.44 is being withheld from the final payment until the Stop
Notice (Exhibit 3), which was filed by one of A.V. & C.'s subcontractors, has
been released, and $20,000 is being withheld as a completion bond for warranty
items. The project must be finaled out this fiscal year in order to maintain
and collect outside park grant funds.
The City Engineer has reviewed the work on the project and determined that
it is complete and in accordance with the approved plans and specifications.
Staff recommends that the City Council accept the improvements and authorize
final progress and retention payment in the amount of $50,414.83 to A.V.& C.
Construction.
- 2 -
CITY OF DUBLIN - EXHIBIT "B"
CONTRACT CHANGE ORDER NO. 9
PROJECT/ROAD: SHANNON PARK RENOVATION PAGE 1 OF 1 PAGE
~'moERAL NO.(S) N/A CONTRACT NO. 89-7
A.V & C. onstruction, 240 Allen Drive, San Bruno CA 94066
1. REGRADE SLOPES NORTH AND WEST OF 'BUILDING
(Compensation as per Section 9, Standard Specifications)
Labor: 2 operators @ $24.44/hr each
24.44 x 2 x 80 hfs = $3,910.40
29% labor surcharge 1,134.02
5,044.42
33% mark-up 1,664.66
Labor Total 6-~-9.08
Equipment:
1 backhoe, 1 tractor @ $15.50/hr each
15.50 x 2 x 80 hrs = $2,480.00
15% mark-up 372.00
Equipment Total 2,~2.00
Item Total
$ 9,561.08
2. CONSTRUCT RETAINING WALLS AT ENTRANCE TO BRIDGE
3. INSTALL WOODEN STAIRS, RETAINING WALL AND
HANDRAIL IN PATIO AREA UNDER BRIDGE
4. INSTALL DRAIN UNDER BRIDGE
5. EXTRA ~qT.FCTRICAL WORK ON pARKING LOT LIGHTS,
FOUNTAIN PUMPS, AND IRRIGATION cONTROIJ~R
6. INSTALL 108 if OF HANDRAIL AT STAIRS
ACCORDING TO BUILDING CODE
Lump Sum 2,700.00
Lump Sum 7,720.00
Lump Sum 500.00
Lump Sum 1,700.00
Lump Sum 4,200.00
ESTIMATED COST: Increase $26_~_381.08
BY REASON OF THIS ORDER, THE TIME OF COMPLETION WILL BE ADJUSTED AS FOLLOWS:
i No additional days
I DATE: May 22, 1991
]SUB~4_I'I'f~LO BY: Don Santina, P.W. Inspector
Thompsor~, Director DATE: May 23, 1991
%PPROVAL RECOY~ENDED: Lee S. ~ ~.
APPROVED, CHIEF ENGINEER, BY: LST ~ J DATE: May 23, 1991
CITY OF DUBLIN - EXHIBIT "B"
CONTRACT CHANGE ORDER NO. 10
PROJECT/ROAD: SHANNON PARK RENOVATION PAGE 1 OF 1 PAGE
FEDERAL NO.(S) N/A CONTRACT NO. 89-7
TO: A.V. & C. Construction, 240 Allen Drive, San Bruno CA 94066
~OT£: This change order ~s not e~;ve u.til a~pr~ved by Th~ Ch~f Engineer.
INCREASE AbD DECREASE ON BID ITEM QUANTITIES
Item ~ Description Bid Actual
Amount
14. Concrete 975 if 1,259 if $ 2,272.00
15. Concrete Curb/Gutter 487 if 902 if 4,150.00
16. Concrete Swale 30 if 23 if (350.00)
17. Concrete Steps 295 if 474.5 if 7,180.00
18. Interlocking Pavers 6,890 sf 5,645 sf (5,722.40)
19. Colored Concrete 10,875 sf 12,488 sf 5,242.25
20. Concrete Paving 5,250 sf 3,264 sf (5,362.20)
21. Concrete Walkways 16,110 sf 18,503 sf 8,375.50
25. Crib Walls 16,000 ls 18,503 ls (1,824.15)
28. 6" Concrete Mow Band 120 if 237 if 1,872.00
31. A.C. Paving - Price change on C.O. 1 Item #1 (1,252,56)
42. New Drinking Fountain 1 ea 2 ea 3,500.00
43. Re-use Fountain 1 ea 0 ea (500.00)
45. Trash Receptacles 7 ea 8 ea 600.00
54. Annual Color Item deleted (395.00)
ESTIMATED COST: Increase Paid in Previous Progress Payments $17,785.44
BY REASON OF THIS ORDER, THE TIME OF COMPLETION WILL BE ADJUSTED AS FOLLOWS:
Ne Additional Days
SUBMITTED BY: Don Santina, PW Inspector
APPROVAL RECOMMENDED: Lee S. Thompso~,~ ~W
APPROVED, CHIEF ENGINEER, BY: LST~/~3
DATE: June 21, 1991
Director DATE: June 21, 1991
DATE: June 21, 1991
EXHIBIT "A"
CHANGE ORDER FORM
DATE: 6/21/91
PROJECT NAME:
PROJECT CIP #: 9593
PROJECT FINANCE CONTROL #:
ENGINEERING CONTRACT #:
PERCENT COMPLETED: 100
COUNCIL-APPROVED CONTRACTOR:
APPROVED BUDGET AMOUNT:
Shannon Park Renovation
9593
89-7
%
A. V. & C. Construction
$971,400 (adiusted amount)
COUNCIL-APPROVED CONTRACT AMOUNT:
CMANGE AMOUNT (+/-)
CHANGE ORDER
CHANGE ORDER
CHANGE ORDER
CHANGE ORDER
CHANGE ORDER
CHANGE ORDER
CHANGE ORDER
CHANGE ORDER
CHANGE ORDER
CHANGE ORDER
TOTAL OF ALL
NO. 1
NO. 2
NO. 3
NO. 4
NO. 5
NO. 6
NO. 7
NO. 8
NO. 9
NO. 10 $
CURRENT AND PRIOR CHANGE ORDERS:
$ 20,208.70
$ 5,082.00
$ (6,068.97)
$ o.oo
$ 6,800.00
$ 51980.90
$ 10,900.00
$ 2,551.00
$ 26,381.08
17~785.44
LESS LIQUIDATED DAMAGES
ADJUSTED CONTRACT AMOUNT:
PROGRESS PAYMENTS MADE:
PAYMENT NO. 1
PAYMENT NO. 2
PAYMENT NO. 3
PAYMENT NO. 4
PAYMENT NO. 5
PAYMENT NO. 6
PAYMENT NO. 7
PAYMENT NO. 8
PAYMENT NO. 9
PAYMENT NO. 10
PAYMENT NO. 11
PAYMENT NO. 12
PAYMENT NO. 13
PAYMENT NO. 14
PAYMENT NO. 15
$ 69,046.72
$ 1501526.75
$ 691499.40
$ 61,878.66
$ 57,966.26
$ 11,044.59
$ 17,730.00
$ 531464.56
$ 28,877.60
$ 106,478.36
$ 441020.39
$ 29,710.40
$ 131~850.00
$ 49,151.51
$ 10,464.93
TOTAL PROGRESS PAYMENTS:
REMAINING BALANCE ON CONTRACT:
RECOMMENDATION:
~ APPROVED
DENIED
S'~ip e rv~i~ng
Dept. Head
APPROVED
DENIED
City Manager
$ 925,138.25
$ 89,620.15
$ 1,0141758.40
$ (37,250.00)
$ 977,508.40
$ 891,710.13
$ 851798.27
APPROVED
DENIED
Mayor