HomeMy WebLinkAbout4.10 Storage Yard Award Bid 85-5AGENDA STATEMENT
CITY COUNCIL MEETING DATE: September 23, 1985
SUBJECT:
City Storage Yard - Contract 85-5A and
Contract 85-5B Bids
EXHIBITS ATTACHED:
Summary of Bid Contract 85-5A; Proposals
for Contract 85-5B
RECOMMENDATION:
FINANCIAL STATEMENT:
1)
2)
3)
Award Bid for Contract 85-5A to MCE
Corporation and authorize Mayor to
execute agreement.
Award Bid for Contract 85-5B to
Page Construction and authorize
Mayor to execute agreement
Authorize budget transfer in the
amount of $29,050 from the
Contingent Reserve to the Capital
Project Fund.
Contract 85-5A Bid $54,900
Contract 85-5B Bid 42,574
Inhouse Costs 22,076
Total Project Cost 119,550
Amount Budgeted 90,500
Budget Transfer Required 29,050
DESCRIPTION: At its meeting of August 26, 1985, the
City Council authorized Staff to solicit separate bids for the
site work and office/storage building for the City Storage Yard
Project at the easterly end of Scarlett Court.
Contract 85-5A provides for the City Storage Yard site work. The
City received a total of three (3) bids for this project, (see
attached Bid Summary).
Although the lowest bid of $40,185.88 was submitted by KW
Contractor; this bid was rejected on the advice of the City
Attorney, because of the absence of a bid bond and other bid
deficiencies. The next lowest bidder was MCE Corporation with a
bid of $54,900.
Contract 85-5B provided for erecting a prefabricated steel
building and constructing an office and bathroom within the
building. The building would be used to provide storage space
for both the Public Works and Police Departments, as well as, an
office for the Public Works Maintenance Supervisor. The City
received a total of three (3) bids (see attached proposals) for
this portion of the project. The lowest bid of $42,574 was
submitted by Page Construction. This bid was a great deal higher
than anticipated when formulating the 1985-86 Budget. The firm
that provided the City with cost estimates during the budget
formulation did not bid.
The City allocated $90,500 in the 1985-86 Budget for the City
Storage Yard Project.
The City Engineer's revised estimate for the total cost of the
project, including the low bids above is broken down below.
ITEM NO. 4. /~ COPIES TO:
$54,900
42,600
2,500
5,450
2,500
6,400
3,200
2,000
$119,550
Site work
Storage/office building
Landscaping
Water Connection Fees
Sewer Connection Fees
Engineering
Inspection
Topographic Survey & Field Staking
TOTAL COST
If the City were to proceed with this project, a budget transfer
from the contingent reserve in the amount of $29,050 would be
necessary.
It is Staff's recommendation that the City Council take the
following action:
Award the Bid for Contract 85-5A to MCE Corporation and
authorize the Mayor to execute the agreement.
Award the Bid for Contract 85-5B to Page Construction
and authorize the Mayor to execute the agreement.
Authorize a budget transfer in the amount of $29,050
from the Contingent Reserve.
BID SU~94ARY
Contract 85-5 For City Storage Yard Site Work
ITeM ITEM
NO. DESCRIPTION
ESTI~£~D
ENGINEERS EST.
KW CONTRACTORS
MCE CORP
Unit Total Unit Total Unit
Price Price Price
REDGWICKCONST.
Total
Unit Total
Price
1. Clearing & Grubbing
2. Finish Grading
3. A.C. Paving (2½"AC;9"AB)
4. 8" V.C.P.
5. 4" V.C.P.
6. Rodding Inlet
7. Sewer Cleanout
8. 8" A.C.P.
9. 1" Copper Type K
10. 2" Rigid Conduit
11. 6' Chainlink Fence
12. 16' Double Swing Gate
13. Sidewalk Removal
14. Curb, Gutter &
Sidewalk Removal
15. Concrete Driveway
16. Reinforced Concrete Slab
17. Reinforced Concrete
Block Wall
18. Remove & Replace
2" Blow-off Assembly
19. Rough Grading
L.S. 2,000 2,000 .... w/item#3 2,060
800 S.Y. 3.50 2,800 .... w/item#3 4.00
6700 S.F. 2.50 16,750 2.47 16,549.00 2.10
360 L.F. 28 10,080 16.58 5,968.80 30.00
70 L.F. 12 840 13.85 950.60 15.00
1 EA. 700 700 1,130.32 1,130.32 500
1 EA. 400 400 249.10 249.10 500
170 L.F. 22 3,740 14.07 2,391.90 40.00
55 L.F. 14 770 13.69 752.95 12.00
40 L.F. 8 320 4.16 166.40 8.50
275 L.F. 13 3,575 8.60 2,365.00 15.00
1 L.S. 1,000 1,000 989.80 989.80 900
300 S.F. 2 600 .31 93.00 3.50
125 S.F. 2 250
1 L.S. 1,000 1,000
407 S.F. 10 4,070
174 S.F. 15 2,610
1 L.S. 500 500
800 S.Y. 3.75 3,000
2,060 4,660 4,660
3,200 5.35 4,280
14,070 2.50 16,750
10,800 28.50 10,260
1,050 22.00 1,540
500 715.00 715
500 550.00 550
6,800 38.50 6,545
660 11.00 605
340 11.00 440
4,125 15.50 4,262.50
900 775.00 775
1,050 2.00 600
.31 38.75 4.00 500 2.00 250
-- 1,500.00 500 500 1,450.00 1,450
4.08 1,660.56 5.00 2,035 12.50 5,087.50
15.00 2,610 20.00 3,480
16.55 2,879.70
..... N/C 600 600 550.00 550
3.13 2,500 3.25 2,600 8.10 6,480
TOTAL PRICE $55,005.00 $40,185.88 $54,900.00 $69,280.00
> .
•
Page Corz€=)trtxctiorl Compariy
P. O. Box 705 • Novato, California 94948 • Telephone (415) 897- 1138
September 16, 1985
City of Dublin
Dublin City Hall
6500 Dublin Boulevard
Dublin, California 94568
ATTENTION: City Manager
SUBJECT: Proposal to Construct
Office/Storage Building
City of Dublin Corporation Yard
Gentlemen:
We propose to construct the Office/Storage Building to be located at the City
of Dublin Corporation Yard, Dublin, California in accordance with the Special
Provisions for Contract #85-5B, Plans dated 8-5-85 (2 pages), Project
Description and Scope of Work Specification, Pages 1,3,4 and 5, and Addendum
No. 1 dated September 5, 1985 for the sum of:
L!eit Tow*Thi -5414 IFw a ligmdi. --!Qr4k 1ND'e
NO/100 DOLLARS.
Our corporate resume is enclosed for your review. It provides the additional
information requested on Page 5 of the Specification. As is shown in the
resume, we have constructed numerous corporation yard projects during the
past twenty years. The proposed project leader will be Donald S. Babcock,
President of Page Construction Company.
We trust the above meets with your approval and look forward to working with
you on this most interesting project.
Yours very truly
PAGE CONSTRUCTION COMPANY
.T-y� ✓jLp`ti�
Donald S. Babcock
President
DSB:cb
Encl.
CONTRACTOR'S STATE LICENSE No. 224795
KW tONTRACTORS,
.k:(D L%✓'_ ., IUD{�i s� ...:� I •JU��.
LIC. #399570
September 17, 1985
City of Dublin
6500 Dublin Blvd.
Dublin, CA
Att: City Manager
Dear Sir:
This will serve as K W Contractors proposal for a metal building
and storage bins, City of Dublin Contract #85-5B. The price includes
all labor, material, etc. for the construction of the project for the •
designated price listed below.
Lump sum price: $ J 7j2
Respectfully submitted, .
- /// - e
Kel Wilson
9 Ridge Circle • Suite A • Benicia , California 04510 • ( 707 )746-7732
Kern bcon Corporation
800 South Claremont Street,San Mateo,.CA 94402 (415)342 9061
418 North Buchanan Circle,No.5,Pacheco,CA 94553 (415)676 2684
•
BID PROPOSAL.
Kembcon Corporation is pleased to , propose ,a 25 ' wide x 40 ' long
x 10 ' eave height building as specified in your spec- f;.cation
outline. The following accessories are included : .
2 each 8 ' x 8 ' overhead doors
1 each 3 ' x '7 ' hollow metal door with lever lockset
80 l.f gutters
2 each. . downspouts
1 each3 ' ',x 3.1 insulated window
1 each6' x 3 ' insulated window
2 each12' gravity ventilators
The building will be a Varco-Pruden building with 26 guage steel
panels for the roof and walls and• the interior . partition. The
panels will be factory painted both sides . It shall comply with
all loads and specifications as outlined .
There are no exceptions .to the: slab work, plumbing, or electrical
specifications . The- interiors work shall be done as specified
and will meet the Title 24 specifications . The' only deviation
from the city' s specification and this proposal are the windows .
The city is asding for a 2 ' x . 3 ' window and a 4' x 3 ' window.
In their place we are offering the windows stated above. The
interior window will be as specified .
The percentage of MBE 'participation on this project would be
approximately 15%.
Exceptions : Kembcon excludes items 1 thru 5 on page 3 under
special conditions those items pertaining to fees,,
permits,landscaping, alarms, and street inprovments .
Price : $49,240.00 Forty Nine Thousand Two Hundren Forty and no/100
dollars. •
Terms : The building must be paid within 20 days of delivery.
This only refers to the metal building material. All
other billings would comply with the City ' s guidlines .
Signed <<%.i1- Xl/ /.l-f-
Bruce H. Whitson-Sales Manager
Date /l// /0612,c
General Contractors Lic.431737
Construction Management
Design—Construct
•
•
•
' • h
Kembcon Corporation
800 South Claremont Street,San Mateo,.CA 94402 (415)342 9061
418 North Buchanan Circle,No.5,Pacheco,CA 94553 (415)676 2684
•
QUALIFICATION STATEMENT
Bank: Wells Fargo Bank
San Mateo Branch on 4th Street
Sal Sanchez
Bonds :. Boring & Vreeburg (Bonding, insurance)
Redwood City
Harry Vreeburg
Kembcon Corporation has been in business for 4 years, primarily
as a General Contractor. Eric Cox our president is a licensed
Civil Engineer: Joseph Kent is our Vice-President and is a
licensed Architect . Both men together are responsible for over
a million square feet of offices, pre-engineered buildings,
and tenant improvments . Kembcon has just completed a 4 million
dollar project for P. G. & E. and " the City, of San Rafael for
a corporate yard for P.G.&E. The Yard consists of 6 pre-engineered
buildings totaling approximately 55 , 000 s.f. of space. The job
was totally bonded .
The project manager for your project would be Bruce Whitson.
Mr. Whitson has 7 years of experience in the pre-engineered
portion of our business. He has put in place over 500, 000
s.f. of these types of buildings. Mr. Whitson is also a part
owner of Kembcon Corporation.
Clients we have built pre-engineered buildings for:
Kamp' s Furniture store-Livermore
Kaiser Aluminum-Cupertino
Sequoyia .Country Club-Oakland
Stony Ridge Winery-Pleasanton
Armando Winery-Livermore
City of San Rafael-San Rafael
Union Carbide-Pittsburgh, Ca.
Kaiser Steel-Napa
Westinghouse-Sunnyvale
If further information is required, we would be happy to comply.
.
General Contractors Lic.431737
Construction Management
Design—Construct