CITY OF DUBLIN
AGENDA STATEMENT
MEETING DATE: March 14 , 1983
SUBJECT Village Parkway Median Drainage Problem
EXHIBITS ATTACHED None
RECOMMENDATION 1 ) Authorize City Engineer to proceed with
designs and preparation of plans &
specifications .
2 ) Authorize a budget transfer from Street
Maintenance Account to Capital Project
Account.
FINANCIAL STATEMENT: Preliminary Cost Estimate - $19 , 000 ; Budget
transfer required.
DESCRIPTION The City Engineer has reviewed the drainage problem
which presently exists along the Village Parkway median between Amador
Valley Boulevard and Kimball Avenue . As you know, there are a number of
locations where ponding occurs and ,presents a potential hazard to motorists
traveling in the lane adjacent to the median. The City Engineer ' s
investigation has revealed that these low points were intentionally designed
to facilitate accumulation of water at locations immediately across from the
present drain openings along the curb lanes, with the idea that the water
would sheet across to those drains . However, as Village Parkway was
resurfaced (multiple times) over the years without raising the median
gutter, the center of the two lanes in each direction has become the crown
of each side of the street, resulting in the accumulation of water at the
medians .
The most economical solution is to- provide an additional catch basin in the
median at each low point and modify the median so that both sides of the
median would drain to the center of the median. The City Engineer has
identified eight locations where modification would be required, and several
minor low points which could be handled through the City ' s overlay program.
The preliminary cost estimate for the work identified above is estimated at
approximately $19 , 000 ; $15 , 000 for construction and $4 , 000 for design,
preparation of plans and specifications to bid, and inspection. The
estimated time frame to complete this project once it is approved would be
approximately four to five months .
------------------------------------7---------------------------------------
COPIES TO:
ITEM NO. 5 ,ZJ
AGENDA STATEMENT : Village Parkway Median Drainage Problem
Page 2
Recommendation
Normally, it would be Staff ' s recommendation to include a project presented
near the end of a fiscal year in the following year ' s Capital Improvement
Program. However, because of the time required to complete the project, it
seems appropriate to proceed with this project as soon as possible so that
completion would be assured hefore any rains which may occur in Fall, 1983 .
With respect to financing, there are no funds set aside for this project in
the capital budget and therefore, a budget transfer would be required.
It is Staff ' s recommendation that the City Council authorize :
1 ) City Engineer to proceed with the design and preparation of plans and
specifications .
' 2 ) A budget transfer from Street Maintenance Account to Capital Projects
Account in the amount of $19 , 000 .