HomeMy WebLinkAbout7.2 San Ramon Rd Traffic Study CITY OF DUBLIN
AGENDA STATEMENT
MEETING DATE : January 24 , 1983
SUBJECT San Ramon Road - Comprehensive Traffic & Improvement
Study
EXHIBITS ATTACHED Memorandum to City engineer from City Traffic Engineer
dated January 17 , 1983
RECOMMENDATION 1) Authorize study under the City' s existing services
contract with Santina & Thompson.
2 ) Authorize budget transfer from contingent reserve
of $14 , 200
FINANCIAL STATE.Q. 1 ) Cost of San Ramon Road Traffic & Improvement Study
not to exceed $11, 000 (approximately $1, 100 might
-� be recoverable from CALMET project.
2 ) Cost of Dublin Boulevard survey & aerial
photography $3 , 200 .
Budget transfer from contingent reserve would be
required to finance both items .
DESCRIPTION In accordance with City Council direction at its
meeting of January 10 , 1983 the City Engineer and Traffic Engineer have
identified the scope of services required to determine the ultimate
configuration of San Ramon Road. As shown in the attached memorandum from
the Traffic Engineer, the tasks proposed provide sufficient detail to enable
the City ' s engineering staff to begin the actual design work on San Ramon
Road once the City Council has approved the conceptual design. The City
Traffic Engineer has also included the development of short-term improvement
priorities which would be in accordance with the overall plan and could be
constructed as funds became available. The estimated time of completion of
the study is 8 weeks .
The total cost of the study is not to exceed $11, 000 and is broken down as
shown on the attached memorandum. With respect to the costs for an aerial
photo base map, $2 , 800 covers not only the aerial photography, but also the
ground survey crew time required to set-up for the aerial photography. If
ground survey crews were used in lieu of aerial photography, the cost for
developing the appropriate survey information and base map would exceed
$2 , 800 . It should also be pointed out that $1 , 100 of the cost of the study
could be recovered from the CALMET project if CALMET proceeds with its
project.
---------------------------------------------------------------------------
r� COPIES TO :
ITEM NO.
AGENDA STATEMENT - San Ramon Road
Page 2
It is also important to note that if the City Council was desirous of
developing a base map for Dublin Boulevard at the same time Dublin/Silver-
gate and San Ramon Road were photographed, an additional $3 , 200 '
appropriation would be necessary. This would save the City approximately
$300 in making an additional flight.
RECOMMENDATION
It is Staff ' s recommendation that 1 ) the City Council authorize the traffic
and improvement study under the City ' s existing contract with Santina &
Thompson, and 2 ) a budget transfer from the contingent reserve be authorized
in the amount of $14 , 200 for the San Ramon Road study and the development of
a base map for Dublin Boulevard.
MEMORANDUM '
TO: Lee Thompson, City Engineer
FROM: Chris Kinzel OL-
DATE: January 17, 1983
SUBJECT: Scope of Services
San Ramon Road Precise Plan Line
As requested by the City Council , I have detailed an outline of a
proposed traffic study of San Ramon Road. The primary objective of the
study would be to determine future travel demand along San Ramon Road
between I-580 and the Contra Costa County line and prepare a precise
plan line for the ultimate configuration of the street including details
on lanes, medians, intersections , signalization, private driveway
access, bicycle and pedestrian facilities and landscaping potential .
Following the tasks listed below are the estimated maximum cost for each
broken down by Santina and Thompson (S&T) , TJKM or others as noted .
Both S&T and TJKM costs would be at the 80 percent billing rates
proposed in our basic services agreement.
1. Obtain new aerial photos at 1" = 40 ' . Establish ground control for
aerials, plot right of way and property lines. Costs: S&T - $300 ,
aerial photos - $2,800 ( $700 for aerial photos plus $2 ,100 for
ground control ) . ( Includes savings of $300 if flown with Dublin and
Silvergate intersection. )
2. Obtain existing 24 hour counts and intersection peak hour counts and
update as necessary. Costs: TJKM - $500. (Note: Costs of counts
currently being made by others for private traffic study not
included. )
3. Evaluate existing traffic and accident conditions, including signing
and striping. Review and evaluate existing County-prepared frontage
road designs. Costs: TJKM - $200.
4. Evaluate street and land use development plans in Contra Costa
County affecting San Ramon Road in Dublin . Consists primarily of
gathering and reviewing development proposals and their traffic
studies. Costs: TJKM - $250.
5. Planning staff prepares build-out development scenario for western
Dublin . Traffic engineer develops traffic generation and assigns to
Dublin street network. Costs: TJKM - $400.
Lee Thompson -2- January 17, 1983
6. Develop future corridor traffic volumes and future intersection T
volumes on San Ramon Road. Consider present traffic , traffic from
future Dublin development and through traffic from Contra Costa
County and Pleasanton. Costs: TJKM - $1,500.
7. Determine need for traffic signals at Dublin/Donlon . Evaluate
impacts of proposed Cal -Met development. Costs: TJKM - $1,100.
8. Develop ultimate cross-section requirements for San Ramon Road.
Include lanes , medians , median openings, pedestrian, bicycle and
parking requirements. Determine access ( driveway) constraints and
ultimate intersection lane and signalization needs at 6 Dublin
intersections: Dublin Boulevard, Amador Valley Boulevard, Silvergate
Drive , Shannon Avenue, Vomac Road, Bellina Street. Costs: TJKM -
$1,200.
9. Prepare precise plan lines for adoption by City of Dublin .
Engineered drawings would show curb lines, slope requirements ,
pedestrian and bike lanes , medians and future striping. Costs:
TJKM - $250, S&T - $2,000.
10. Develop priorities for short-term improvement projects such as
signalization, intersection widening, improved signing, median or
driveway changes , etc . Identify possible funding sources such as
developer contribution, FAU, gas tax, etc. Costs: TJKM -$500
The total costs identified above include : aerial photo base maps -
$2,800, TJKM costs -$5,900, Santina and Thompson office costs - $2 ,300.
These are maximum costs billed at hourly rate and do not include
attendance at meetings or hearings . The work will be completed in an
approximate eight-week period.
Following the completion of hearings on the study recommendations and
adoption by the City Council , the City will have an ultimate improvement
plan for San Ramon Road to guide its development by both public and
private sources on a priority basis.
Note: If aerial photos of Dublin Boulevard were flown at the same time
as the San Ramon Road and the Dublin-Silvergate photos , their
cost would be an additional $3,200, a savings of $300 from a
separate flight.