HomeMy WebLinkAbout8.2 2020-2025 Five-Year Capital Improvement Program UpdateSTAFF REPORT CITY COUNCIL Page 1 of 16 Agenda Item 8.2 DATE:April 20, 2021 TO:Honorable Mayor and City Councilmembers FROM:Linda Smith, City Manager SUBJECT:2020-2025 Five-Year Capital Improvement Program Update Prepared by: Laurie Sucgang, City Engineer and Michael Boitnott, Capital Improvement Program Manager EXECUTIVE SUMMARY: The City Council will receive an update of the 2020-2025 Five-Year Capital Improvement Program adopted in Fiscal Year 2020-21. STAFF RECOMMENDATION: Receive the report and provide direction to Staff for the Capital Improvement Program Update to be presented to the City Council on June 1, 2021. FINANCIAL IMPACT: Any financial impact resulting from City Council direction will be included in the Fiscal Year 2021- 22 budget proposal scheduled for the June 1, 2021 City Council meeting. DESCRIPTION: Every two years, the City Council adopts a new Five-Year Capital Improvement Program (CIP), following a review of certain projects by the Planning Commission, the Parks and Community Services Commission, and/or the Heritage and Cultural Arts Commission. In the years in between the CIP adoption, Staff provides the City Council with an update to the CIP, which may include new projects and revisions to existing projects. The current CIP for years 2020-2025, was adopted by the City Council on June 9, 2020, therefore the CIP included in this report serves as an update. A new CIP cycle will start in Fiscal Year 2022- 23. 2020-2025 CIP Projects The 2020-2025 CIP Update summary is provided as Attachment 1, which includes total projects costs and funding sources. 556 Page 2 of 16 Projects in the CIP are identified in four major categories. Below is a summary of the 2020-2025 CIP expenditures by category, followed by a description and status of the projects in each category. New projects and projects with proposed budget adjustments are indicated in bold italics. 2020-2025 CIP Expenditures Category 2020-21 2021-22 2022-23 2023-24 2024-25 Total General $14,981,037 $6,991,969 $2,315,200 $690,360 $205,000 $25,183,566 Public Art $608,397 $544,700 $375,000 $0 $0 $1,528,097 Parks $41,997,952 $7,533,216 $1,577,034 $3,938,435 $8,603,705 $63,650,342 Streets $41,361,423 $9,230,242 $13,310,390 $3,458,695 $3,862,775 $71,223,525 Total $98,948,809 $24,300,127 $17,577,624 $8,087,490 $12,671,480 $161,585,530 General Improvements Audio Visual System Upgrade (GI0421): This project provides for audio visual system upgrades in the Ambrose Hall and adjoining conference room at the Shannon Community Center and the Program Room at the Dublin Library. The upgrades will include replacement of equipment to improve the service quality for rentals, meetings, and corporate events. The upgrade will also bring the audio-visual systems to current industry standards. The total project cost is $109,040 funded by the General Fund. A request for proposals was released in spring 2021 with the proposals and award of an agreement anticipated to be presented to the City Council in June 2021. Citywide Energy Improvements (GI0121): This project provides for the planning (Investment Grade Audit), design, and construction of various energy upgrades, efficiency improvements, lighting upgrades, energy generation, solar photovoltaic systems, and energy storage projects at facilities, parks, and other City-owned property. The project includes construction of lighting upgrades in Fiscal Year 2022-2023 at Mape Memorial Park, Alamo Creek Park, and Ted Fairfield Park. Future construction phases and funding sources will be determined during project planning and may include a variety of site and building energy efficiency improvements and lighting upgrades at Emerald Glen Park and at the Phase 1 area of Fallon Sports Park. The total project cost is $517,420 funded by the General Fund with possible future funding sources such as power purchase agreements and on-bill financing through PG&E. On November 17, 2020, the City Council approved a contract with Willdan Energy Solutions to proceed with an Investment Grade Audit to develop energy efficiency and infrastructure improvement projects. Civic Center HVAC and Roof Replacement (GI0119): This project provides for the design and replacement of the heating, ventilation, and air conditioning (HVAC) system and controls, roof replacement, associated building modifications, and code compliance upgrades for City Hall portion of the Civic Center complex. With the roof replacement, the project will also upgrade communications infrastructure for new data connections to 557 Page 3 of 16 offices, workstations, and conference rooms. The project will be completed in several phases to minimize disruption to the public and to Staff working within the buildings. The HVAC and roof improvements for the future Cultural Arts Center portion of the Civic Center complex will be completed with the renovation of the Cultural Arts Center Project, CIP No. GI0120. The total project cost is $4,895,155 funded by the General Fund, Internal Service Fund, and IT Fund. The project is currently under construction and is anticipated to be completed by summer. Civic Center Rehabilitation (GI0001): This project provides for the planning, design, and construction of various rehabilitation and renovation projects at the Civic Center. Projects may include renovation of all restrooms, showers, kitchenettes, and the employee break room; modifications to conference rooms; lighting and ceiling replacement; site improvements to the parking lot area and surrounding walkways of the Civic Center; building security evaluation and upgrades; repainting; and Americans with Disabilities Act and Code upgrades. Interior repainting in select areas were completed during the construction of the Civic Center HVAC and Roof Replacement project, and minor parking lot and walkway improvements are anticipated to be designed and constructed in conjunction with the Cultural Arts Center project. Planning for other projects is anticipated to begin in Fiscal Year 2021-22. The total project cost is $2,241,370 funded by the General Fund. Cultural Arts Center (GI0120): This project provides for the design and improvement of an approximately 13,000-square-foot Cultural Arts Center on the first floor of the Civic Center, which was formerly occupied by Dublin Police Services. The Parks & Recreation Master Plan identifies a Cultural Arts Center that would serve as a multi-use facility that affords cultural, educational, and social opportunities for the community. The Cultural Arts Center could include an Art gallery; Black Box theater space; multi-purpose art and music classrooms; a dance studio; and restrooms. The project also provides for the replacement of the heating, ventilation, and air conditioning (HVAC) systems, HVAC controls, roof replacement, major upgrades to the main telecommunications room, and the relocation of the Parks and Community Services Department offices to the second floor of the Cultural Arts Center. The total project cost is $11,972,035 funded by the Public Facilities Fee Program, General Fund, and Internal Service Fund. In October 2019, the City Council approved an agreement with Group 4 Architecture Research and Planning, Inc. to design the Cultural Arts Center. Electric Vehicle (EV) Charging Stations (GI0219): This project provides for the design and construction of at least two electric vehicle (EV) charging spaces at The Wave at Emerald Glen Park and the underground infrastructure for future expansion. In future years, the project could provide for design and construction of EV charging spaces at other City facilities. Staff will apply for grant funding that will pay for charging units themselves; agencies typically fund conduits, wiring, and electrical panel upgrades as local match contribution to grant funding. The total project cost is $142,041 funded with the General Fund Reserve designated for Innovation/New Opportunities. Installation of EV charging units at The Wave is planned for spring/summer 2021. 558 Page 4 of 16 Library Tenant Improvement (GI0521): This project provides for the design and construction of tenant improvements to the Dublin Library, including completion of 5,150 square feet of currently unoccupied space within the library building. The 37,000 square- foot library building was completed in Fiscal Year 2002-2003, however, only 30,000 square feet was occupied. In Fiscal Year 2016-2017, a tenant improvement project was completed which opened an additional 1,850 square feet of space adjacent to the children's area. This project will open the remaining 5,150 square feet of building area for library and community use. Improvements may include removal of interior walls and the installation and modification of shelving and fixtures; carpet replacement; and repainting. The project is consistent with the 2016 Alameda County Library Space Plan. The total project cost is $1,839,970 funded by the Public Facilities Fee Program and Internal Service Fund. Design is anticipated to begin in Fiscal Year 2022-23. Resiliency and Disaster Preparedness (GI0221): This project provides for the planning, design, and construction of various disaster and emergency preparedness improvements to facilities and major signalized intersections to prepare for future PG&E Public Safety Power Shutoff events and other emergency events. Improvements may include energy storage, back-up power generators, transfer switches for temporary generators, battery backup units for traffic signals, temporary traffic control devices, portable changeable message electronic boards, power outage alarms and notification systems. The total project cost is $703,095 funded by the General Fund. On November 17, 2020, the City Council approved a contract with Willdan Energy Solutions to proceed with an Investment Grade Audit to develop energy efficiency and infrastructure improvement projects, including projects that support resiliency and disaster preparedness efforts. Solar Photovoltaic System (PV) Canopies at The Wave (GI0321): This project provides for the planning, design, and construction of a solar photovoltaic system, such as solar arrays on canopy structures in the parking lot of The Wave, for energy generation, potential energy storage, and energy efficiency improvements at The Wave facility at Emerald Glen Park. The total project cost is $168,150 funded by the General Fund with possible additional funding through a power purchase agreement with an energy service provider. On November 17, 2020, the City Council approved a contract with Willdan Energy Solutions to proceed with an Investment Grade Audit to develop energy efficiency and infrastructure improvement projects, including a PV project at The Wave. Public Art Camp Parks Sign (PK0121): This project includes the restoration and relocation of the historic Camp Parks entrance sign from its current location at approximately 201 Dougherty Road to the new entrance at Camp Parks Boulevard and Dougherty Road. The original sign was constructed by artist/architect Bruce Goff in the 1940s and is eligible for the National Register. Rehabilitation will be in accordance with standards and guidelines per the U.S. Department of the Interior National Park Service. The addition of functional public art will be incorporated into the sign relocation site. The total project cost is $500,450 funded by the Public Art Fund. Design and engineering are anticipated to begin in summer/fall 2021. 559 Page 5 of 16 Heritage Park Public Art (PANEW01):This project could include a monument piece at the northern edge of the park along Dublin Boulevard, as well as sculpture benches, culture walks, diversity streams, and artifact cubes as originally outlined in the Heritage Park Master Plan. These artistic elements will represent Dublin's rich heritage, culture, and diversity. The total project cost is $519,700 funded by an Art in-lieu contribution from the Schaefer Ranch Development and the Public Art Fund. Parks Alamo Creek Park - Fence Replacement (PKNEW01): This project provides for the design and construction of replacement fencing in and around Alamo Creek Park, split between general City property and City property that falls within Landscape and Lighting District No. 1986-1, which has its own funding source. o Non-Assessment District Portion: The project will include replacement of fencing on both sides of Alamo Creek, which runs through the middle of the park, and the fencing along the park street frontages of Dougherty Road, Wildwood Road, and Willow Creek Drive. In addition to the steel fencing, the existing decorative concrete masonry walls, which include integrated tubular steel fence elements, will be evaluated, repaired as needed, and repainted. This portion of the project cost is estimated at $450,000 funded by the General Fund. o Assessment District Portion: The Alamo Creek Park tubular steel fencing matches other fencing on Amador Valley Boulevard west of Wildwood Road, on the west sides of Fall Creek Road and Wildwood Road, and on the north side of Willow Creek Drive. This other fencing, and the associated landscaping, is within Landscape and Lighting District No. 1986-1. Assessments are levied on properties within the District to cover maintenance of these fences and landscaping, as well as other landscaping and amenities within the District. As is the case with Alamo Creek Park, the District fencing needs replacement and repair, the cost of which exceeds the projected end of Fiscal Year 2020-2021 District fund balance of approximately $404,000. Staff and the City’s assessment district consultant are currently evaluating project funding options as part of the District’s annual assessment and levy report. Project funding options, including levying the maximum allowable assessment and/or phasing the fence replacement, are being developed and will be presented for City Council consideration with the Capital Improvement Program on June 1, 2021. Don Biddle Community Park (PK0115): This project provides for the design and construction of a 30-acre community park in the Boulevard Development within the Dublin Crossing Specific Plan. The park will be located between Dublin Boulevard, Scarlett Drive, Horizon Parkway, and Columbus Street and will be built by the Boulevard Developer. The conceptual plan was approved by the City Council on January 9, 2018. The plan includes tennis courts, basketball courts, a picnic and barbeque area, a great lawn (multi-use lawn area), playgrounds, parent paddock, community garden, and other amenities. On October 2, 2018, City Council provided direction to use $600,000 of Community Benefit Funds for 560 Page 6 of 16 the inclusion of a specimen tree and upgraded playground equipment in the park design. The total project cost is $24,824,002. In accordance with the Dublin Crossing Development Agreement, the Developer is responsible for project costs up to $12,857,142. The City is responsible for reimbursing the Developer for project costs that exceed that amount. City funding will come from Public Facilities Fee Program and the General Fund. Park construction has started and is anticipated to be completed in spring 2022. Downtown Dublin Town Square Park (PK0221): This project provides for the planning of a new Town Square, in accordance with the main principles of the Downtown Dublin Preferred Vision, which was approved by the City Council on November 5, 2019. The Town Square is a one-acre park and plaza that will serve as Downtown Dublin's gathering place, which may include a market promenade, outdoor dining, and event space, and will be located one block north of Dublin Boulevard in the Dublin Place shopping center along the proposed extension of Golden Gate Drive. The total project cost is $4,611,040 and the planning phase, which is anticipated to begin in Fiscal Year 2021-22, is funded by the General Fund. Possible funding sources for future phases of the project are the Public Facilities Fee Program, development impact fees, community facilities district financing, or other assessment district fees. Fallon Sports Park - Phase 3 (PK0119): Fallon Sports Park is a 60-acre community park bordered by Fallon Road, Central Parkway, Lockhart Street and Gleason Drive. Phases 1 and 2 of the park have been completed and Phase 3 represents the final phase of park development. The Phase 3 project provides for the design and construction of the remaining 14 acres of Fallon Sports Park, referred to as the Upper Terrace. On December 17, 2019, the City Council approved the concept design that includes a cricket field, sand volleyball courts, and multi-sport batting cages. The total project cost is $10,598,000 funded by the Public Facilities Fee Program. The City Council approved the construction contract on February 16, 2021, and construction is anticipated to be complete in summer 2022. Iron Horse Nature Park and Open Space (PK0001): This project provides for the planning, design, and construction of 12.13 acres of a nature park and open space adjacent to the Iron Horse Trail, from the Dublin/San Ramon city limit to the confluence of Amador and South San Ramon Creeks, that will be developed in partnership with Zone 7 Water Agency. The park size could increase to over 20 acres of usable parkland when combined with adjacent Zone 7 Water Agency property. The park will be designed in accordance with the Iron Horse Nature Park and Open Space Master Plan, which was approved by the City Council on October 1, 2013. The City has already acquired the 12.13 acres and the balance of the parkland would be accessible through an easement and operational agreement with Zone 7 Water Agency. The total project cost is $11,563,000 funded by the Public Facilities Fee Program with possible additional funding sources such as state grants. It is anticipated that planning will begin in Fiscal Year 2022-23. Jordan Ranch Neighborhood Square (PK0002): This project provides for the design and construction of a 2.0-acre neighborhood square in the Jordan Ranch Development. The 561 Page 7 of 16 neighborhood square will be designed in accordance with the Neighborhood Square Standards contained in the Parks and Recreation Master Plan. The total project cost is $1,514,000 funded by the Public Facilities Fee Program. It is anticipated that the planning will begin in Fiscal Year 2021-22. Playground Replacement (PK0003): This project provides for the planning, design, and construction of the replacement of playground equipment at various parks. Based on the results of annual inspections and regular maintenance records, all City parks will be evaluated for the need to replace play equipment at the end of their useful lives. The total project cost is $1,431,780 funded by the General Fund. The first phase, anticipated to begin in Fiscal Year 2023-24, will include Emerald Glen Park (Near Splash Pad Ages 5-12), Ted Fairfield Park (Ages 2-5 and 5-12), and Kolb Park (Ages 2-5 and 5-12). Restrooms Replacement (PK0321): This project provides for the planning, design, and construction to replace the existing restrooms at Alamo Creek Park, Mape Memorial Park, and Kolb Park. In order to bring the restrooms up to current accessibility standards and codes, the existing restroom buildings will be demolished and replaced with pre- engineered restroom buildings. The total project cost is $1,000,000 funded by the General Fund. Planning and design are anticipated to begin in Fiscal Year 2021-22. Wallis Ranch Community Park (PK 0421): The Wallis Ranch Community Park consists of three separate parcels totaling 8.85 acres in the Wallis Ranch Development. The project will provide for the design and construction of a community park with a dog park and potential amenities such as a play area, picnic facilities, turf area, natural area, restrooms, pathways, lighting, and irrigation and landscaping. The total project cost is $6,699,000 funded by the Public Facilities Fee Program. Community engagement on the preliminary design has started and will continue through spring. Concept park designs are anticipated to be presented to the City Council this summer. Streets Annual Street Resurfacing (ST0117): This project provides for the design and construction of a variety of pavement resurfacing treatments, from slurry seal to major rehabilitation and reconstruction of streets and resurfacing of bridge decks. The project also includes installation of new or upgrade of existing ADA curb ramps on roads that are reconstructed or receive an asphalt concrete overlay. Streets are selected for improvements based on the City's Pavement Management System to optimize the pavement condition in relation to available budget. The City owns and maintains approximately 150 centerline miles of streets. The Metropolitan Transportation Commission groups Pavement Condition Index (PCI) ratings into the following categories: 80-100 Very Good-Excellent; 70-79 Good, 60-69 Fair, 50-59 At Risk, 25-49 Poor, and 0-24 Failed. The City is rated Very Good with a rolling three-year average PCI of 84. This program protects the substantial investment the City has in the public street system. The total project cost is $17,742,660 funded by Alameda County Transportation Commission Measure B/BB funds, Gas Tax, Local Recycling Programs, Mitigation Contributions, and the General Fund. This year’s slurry seal project is anticipated to be in construction in summer/fall 2021. 562 Page 8 of 16 Citywide Bicycle and Pedestrian Improvements (ST0517): This project includes planning, design, and construction of improvements to various pedestrian and bicycle facilities throughout the City, including pedestrian/bicycle bridges. This project replaces former projects that provided funding for Americans with Disabilities Act (ADA) Transition Plan improvements and Citywide Sidewalk Repair Improvements. In addition to the scope of those previous projects, this project includes design and construction of improvements recommended in the City of Dublin Bicycle and Pedestrian Master Plan, the ADA Transition Plan, and the Class 1 Facilities Maintenance Plan. The project includes an update to the ADA Transition Plan with a review of City buildings, parks, and rights-of-way. The ADA Transition Plan update is funded by General Fund and is anticipated to be completed in 2021. An update of the Bicycle and Pedestrian Master Plan began in Fiscal Year 2019-20 and in anticipated to be completed in early 2022. The total project cost is $4,016,600 funded by Transportation Development Act, Measure B/BB Local Streets and Bike & Pedestrian Funds. Citywide Signal Communications Upgrade (ST0713): This project provides for the continued upgrades of the traffic signal communications system and includes the replacement of signal controllers, conflict monitors, and battery backup units, as well as managing ongoing signal operations of coordinated corridors; expanding the traffic communication network by connecting traffic signals on Fallon Road and Tassajara Road and replacing existing copper communication cables with fiber optic cables on Dublin Boulevard; expanding the adaptive traffic signal system along key corridors; connecting existing and new public safety infrastructure, such as situational awareness cameras and automated license plate recognition cameras to the high speed fiber optic communications system; updating the existing City of Dublin Travel Demand Forecasting Model to provide traffic flow projections on the arterial and collector roadways and analyze future land use development proposals and transportation network changes in the City. The total cost is $4,457,606 and is partially funded with General Fund Reserves designed for One Time Initiative – Capital, Gas Tax, Measure B Local Streets, Transportation for Clean Air, Vehicle Registration Fee, Road Maintenance & Rehabilitation Account, Eastern Dublin Traffic Impact Fee Program, Western Dublin Traffic Impact Fee Program, and Internal Service Fund for Equipment. Potential other funding for this project may include Federal and State grants. The fiber optic cables upgrade on Dublin Boulevard is anticipated to begin in summer 2022, and the Travel Demand Forecasting Model update is anticipated to be completed in spring 2021. Downtown Dublin Street Grid Network (ST0221): This project provides for the planning of a new Street Grid Network, in accordance with the main principles of the Downtown Dublin Preferred Vision, which was approved by the City Council on November 5, 2019. The Street Grid Network will introduce new streets that will break down the large block format into smaller, walkable-sized blocks between 350 to 450 feet per side. The proposed extension of Golden Gate Drive north from Dublin Boulevard up to Amador Valley Boulevard will become a new main street with the classic Downtown street grid network within street rights-of-way varying between 60 and 90 feet wide. Street infrastructure may include 563 Page 9 of 16 storm drainage, sewer, water, recycled water, communications, gas, and electric utilities, as well as landscaping and irrigation. Street rights-of-way are anticipated to be dedicated by developers. The total project cost is $21,431,680. The planning phase, which began in 2020 in conjunction with the update of the existing City Travel Demand Forecasting Model to provide traffic flow projections on the new roadways and analyze future land use development proposals and transportation network changes in the Downtown, is funded by the General Fund. Possible funding sources for future phases of the project are development impact fees, community facilities district financing, or other assessment district fees. Dublin Boulevard Extension – Fallon Road to North Canyons Parkway (ST0216): This project provides for the environmental review, preliminary engineering, design and construction of the 1.5-mile extension of Dublin Boulevard from Fallon Road to North Canyons Parkway in Livermore. The extension is planned to have four to six travel lanes, bike lanes, a Class 1 bike/multi-use path, sidewalk, curb and gutter, traffic signals, street lighting, landscaped medians, bus stops, and all city street utilities. The preliminary engineering, environmental impact report, and cost allocation between the City of Dublin and City of Livermore is governed by a Memorandum of Understanding approved by the City Council on April 19, 2016. On November 1, 2016, the City Council approved a contract for Preliminary Engineering and an Environmental Impact Report. On April 27, 2017, Alameda County Transportation Commission (ACTC) approved $8.233 million of Measure BB Grant funds for the design and environmental phases of the project. The project EIR and precise roadway alignment were completed in 2020, after which ACTC took the lead in final design. The NEPA Environmental Assessment was completed in early 2021 with a Finding of No Significant Impact. The preliminary engineering level cost estimate for this project is approximately $166.1 million, which includes all project mitigation costs and indirect impacts mitigation, and is anticipated to be divided among the City of Dublin ($111.1 million) and the City of Livermore ($55 million) on the basis of street length in each jurisdiction. Unincorporated Alameda County's costs will be shared between Dublin and Livermore with the final cost allocation to each jurisdiction to be defined by a Cooperative Agreement. Funding sources are the General Fund, Measure BB, Gas Tax, and Eastern Dublin Traffic Impact Fee Program. Possible other funding sources are State and Federal grants. In spring 2021, ACTC and their consultant team started the final design process, which is anticipated to take 24 months to complete. Dublin Ranch Street Light Improvements (ST0417): This project provides for the design and repainting of decorative streetlight poles and conversion of existing streetlights into energy-efficient LED streetlights in the Dublin Ranch Street Light Assessment District (1999-1). The conversion to LED lights is expected to reduce the District’s annual energy costs. Repainting of the streetlight poles protects the integrity of the poles and also improves aesthetics in the surrounding neighborhood. The total cost is $966,565 funded by revenue collected through District assessments. Design for the LED conversion project is anticipated to commence in 2021 with construction to follow in 2022. 564 Page 10 of 16 Golden Gate Drive Intersection Improvements at Dublin Boulevard and St Patrick Way (ST0002): This project provides for the design and construction of intersection improvements at the intersections of Dublin Boulevard at Golden Gate Drive and St. Patrick Way at Golden Gate Drive. This is a Western Dublin Traffic Impact Fee Program project to relieve congestion, reduce GHG, and is an Active Transportation Solution. The project is identified in the Downtown Dublin Specific Plan and the Bicycle and Pedestrian Master Plan. The improvements may include a new traffic signal at the intersection of St. Patrick Way and Golden Gate Drive; traffic signal modifications at the intersection of Dublin Boulevard at Golden Gate Drive; conversion of copper connection to fiber optic; signing, striping and markings; necessary utility, pavement, curb, gutter, and sidewalk modifications or adjustments. The total project cost is $948,250 funded by the Western Dublin Traffic Impact Fee Program. Design is anticipated to begin in 2022. Green Stormwater Infrastructure (ST0121): This project provides for the planning, design, and construction of various citywide projects that will improve water quality and provide other environmental benefits in accordance with the Green Stormwater Infrastructure (GSI) Plan, which was approved by City Council on June 18, 2019. The GSI Plan and implementing projects are mandated by the Municipal Regional Stormwater Permit (MRP). Projects may include: stormwater trash capture; bioretention areas and rain gardens; tree well filters; Bay Friendly landscape retrofits; and/or storm drain hydrology assessments (e.g. determining inverts, pipe diameter, asset photos, etc.). The total project cost is $2,156,895 funded by the General Fund. The planning phase is anticipated to begin in Fiscal Year 2021-22. Iron Horse Trail Bridge at Dublin Boulevard (ST0118): This project provides for the planning, design, and construction of the Iron Horse Trail bridge for bicycles and pedestrians over Dublin Boulevard. The project will construct a truss arch bridge consistent with the Iron Horse Trail Feasibility Study and preliminary bridge design, approved by the City Council on November 7, 2017. The bridge will provide safer and easier trail access, including access to and from the Dublin-Pleasanton BART station. The total cost is $11,604,439 funded by Gas Tax, Measure B/BB Local Streets and Bike & Pedestrian Funds and Grants, Transportation for Clean Air, Road Maintenance & Rehabilitation Account, developer contributions from Dublin Crossing, and Measure RR Safe Routes to BART. The City Council approved the design contract on February 20, 2018 and approved a construction management contract on March 2, 2021. It is anticipated that solicitation of bids for construction will occur in mid-2021. Local Roadway Safety Plan (STNEW01): This project will provide for developing a Local Roadway Safety Plan (LRSP), which will prioritize safety for all users, provide a framework to identify, analyze, and prioritize roadway safety improvements on local roads. Aligning with federal regulations, the State’s Strategic Highway Safety Plan and the vision for California, the LRSP will guide the City to data-driven solutions for safer streets; identify the stakeholders; use safety data to identify safety issues; choose proven solutions; identify the implementation process; and support future safety investments. The LRSP along with the current update of the Bicycle and Pedestrian Master Plan will create a transportation 565 Page 11 of 16 system that promotes multi-modal transportation options and community safety with a key goal to provide safe, comfortable, and convenient travel along the City’s roadways through a comprehensive, integrated transportation network for all users. The total cost is $117,980 funded by State Transportation Improvement funding and Measure BB Local Streets Fund. The City Council approved a grant funding agreement on March 16, 2021, which provides for State funding of $72,000 for the project. St. Patrick Way Extension (ST0003): This project provides for the design and construction of the final segment of Saint Patrick Way from west of Golden Gate Drive to Regional Street. This is a Western Dublin Traffic Impact Fee Program project to relieve congestion, reduce GHG, and is an Active Transportation Solution. The project is identified in the General Plan, Downtown Dublin Specific Plan, and the Bicycle and Pedestrian Master Plan. Prior segments of Saint Patrick Way were constructed by Caltrans in 1998 and Connelly Station in 2014. The developer of the St. Patrick Way Bayview Development Group project entered into an agreement with the City on June 18, 2018, which required dedication of right-of- way and construction of improvements to complete the Saint Patrick Way Extension. The total project cost is $3,742,556 and the developer is responsible for all project costs to acquire right-of-way, design, and construction in exchange for credit toward Western Dublin Traffic Impact Fees. Construction is anticipated to begin in 2021. Tassajara Road Realignment and Widening – Fallon Road to North City Limit (ST0116): This project provides for the design and construction of a realigned Tassajara Road from Fallon Road to the northern City limit, which will be coordinated with Contra Costa County. Planning and preliminary engineering cost will be split in accordance with the Memorandum of Understanding, which was approved on September 16, 2014. Costs for the design and construction will be agreed upon and split proportionally with the work within each jurisdiction. The project will widen Tassajara Road to a four-lane arterial standard with bike lanes, sidewalks, landscaped median, stormwater treatment areas, and other associated street improvements. Portions of the existing roadway have been improved by adjacent development projects and this project will complete the street improvements and realign a portion of existing roadway to improve safety and achieve better circulation while adhering to the Complete Streets Policy. The roadway segment is a project within both the Tri-Valley Transportation Council Strategic Expenditure Plan (Project B-8) and the Eastern Dublin Traffic Impact Fee Program (Category 1). The total project cost is $12,777,416 and is funded by Gas Tax, Road Maintenance & Rehabilitation Account, Eastern Dublin Traffic Impact Fee Program, Dougherty Valley Traffic Impact Fees, and the Tri-Valley Transportation Development Fees. Contra Costa County Public Works has started the preliminary design. Tassajara Road Improvements – North Dublin Ranch Drive to Quarry Lane School (ST0119): This project provides for design and construction to complete the street improvements on Tassajara Road, from North Dublin Ranch Drive to Quarry Lane School and will improve Tassajara Road to a four-lane arterial standard, with bike lanes, sidewalks, landscaped median, stormwater treatment areas, and other associated street improvements. Portions of the existing roadway have been improved by adjacent 566 Page 12 of 16 development projects and this project will complete the street improvements implementing the General Plan and the Complete Streets Policy. This roadway segment is a project within the Eastern Dublin Traffic Impact Fee program (Category 1). The total cost is estimated to be $9,000,000, which is a $1,500,000 increase from the current project budget of $7,500,000. The estimated cost increase is due to refined estimates from the designer, including cost increases for utility relocation, right-of-way acquisition, and permitting. Staff proposes the $1,500,000 budget increase to fund Fiscal Year 2022-23 costs and has not identified a specific funding source at this time. Current project funding is by Gas Tax, Eastern Dublin Traffic Impact Fee Program, and Tri-Valley Transportation Development Fees. Potential additional funding sources are regional and state grants. Design began in early 2020 and construction is anticipated to begin in Fiscal Year 2022-23. Traffic Signal Re-lamping (ST0001): This project provides for the replacement of the traffic signal and pedestrian signal LED lamps at approximately 78 traffic signals. The City currently has 98 traffic signals, many of which were installed in 2008, and the LED lamps are reaching the end of their useful life, which is typically eight to ten years. The City has replaced 20 traffic signal lamps through on-going maintenance efforts. New LED lamps will ensure proper visibility of vehicle and pedestrian signal heads, which is critical for maintaining a safe traffic flow. The total project cost is $598,040 funded by Gas Tax, Measure B Bike & Pedestrian Fund, and Vehicle Registration Fees. Design is anticipated to begin in Fiscal Year 2022-23. Funding Sources The funding for the 2020-2025 CIP comes from a variety of sources, summarized as follows: Category 2020-21 2021-22 2022-23 2023-24 2024-25 Total General Fund $17,815,543 $3,838,550 $2,485,780 $2,244,855 $327,715 $26,712,443 Special Rev. - Public Works $16,459,789 $3,037,439 $3,187,209 $3,187,209 $2,888,189 $28,759,835 Special Rev - Assmt. Dist.$799,595 $40,106 $41,016 $41,016 $41,016 $962,749 Public Art Fund $608,397 $544,700 $375,000 --$1,528,097 Traffic Impact Fees $18,081,642 $1,911,076 $20,630 $112,260 $815,360 $20,940,968 Public Facilities Fees $21,564,742 $11,165,701 $3,208,989 $2,502,150 $4,117,200 $42,558,782 Internal Service Funds $5,045,925 $20,000 $90,000 --$5,155,925 Dublin Crossing Fund $1,000,000 ----$1,000,000 Other $1,881,676 ----$1,881,676 Developer Built $15,691,500 $3,742,556 ---$19,434,056 Unidentified --$8,169,000 -$4,482,000 $12,651,000 Total $98,948,809 $24,300,128 $17,577,624 $8,087,490 $12,671,480 $161,585,531 567 Page 13 of 16 Approximately 39% or $63.5 million of the CIP costs are funded by Traffic Impact Fees and Public Facilities Fees. It is important to note that the completion of projects funded by impact fees is contingent upon development proceeding as estimated and fees being collected as projected. The timing of projects funded by this source may need to be re-evaluated if there is a slowdown of projected development activities. Public Facilities Fees Projects The following are the projects and total costs funded by the Public Facilities Fee Program over the 2020-2025 CIP timeframe, excluding projects that are expected to be completed in Fiscal Year 2020-21. Project 2020-21 2021-22 2022-23 2023-24 2024-25 Total Cultural Arts Center $690,990 $4,949,904 ---$5,889,200 Don Biddle Community Park $9,490,765 ----$9,866,860 Fallon Sports Park - Phase 3 $10,207,421 ----$10,598,000 Iron Horse Nature Park & Open Space --$461,650 $2,502,150 $4,117,200 $7,081,000 Jordan Ranch Neighborhood Square*-$403,121 $1,110,879 --$1,514,000 Library Tenant Improvements*$35,305 $78,205 $1,636,460 --$1,749,970 Wallis Ranch Community Park*$964,530 $5,734,470 ---$6,699,000 Total**$21,389,011 $11,165,701 $3,208,989 $2,502,150 $4,117,200 $42,383,051 *Projects using an advance from the General Fund General Fund Projects The General Fund contributes to approximately 17% or $26.7 million of the CIP costs. The following project are funded or partially funded by the General Fund. Project 2020-21 2021-22 2022-23 2023-24 2024-25 Total Alamo Creek Park - Fence Replacement (New)-$450,000 ---$450,000 Annual Street Resurfacing $468,000 ----468,000 568 Page 14 of 16 Audio Visual System Upgrade $65,020 $44,020 ---109,040 City Entrance Monument Signs $285,000 ----285,000 Citywide Bicycle and Pedestrian Improvements $325,766 $108,000 $108,000 $108,000 $108,000 757,766 Citywide Energy Improvements $35,860 $115,780 $365,780 --517,420 Citywide Signal Communications Upgrade $1,420,148 ----1,420,148 Civic Center HVAC and Roof Replacement $2,212,634 ----2,212,634 Civic Center Rehabilitation -$1,123,050 $222,960 $690,360 $205,000 2,241,370 Cultural Arts Center $4,539,197 ----4,539,197 Don Biddle Community Park $2,100,000 ----2,100,000 Dougherty Road Improvements - Sierra Lane to North City Limit $93,483 ----93,483 Downtown Dublin Street Grid Network $140,840 $60,210 $10,210 $10,210 $10,210 231,680 Downtown Dublin Town Square Park $68,020 $29,505 $4,505 $4,505 $4,505 111,040 Dublin Boulevard Extension - Fallon Road to North Canyon Parkway $123,000 ----123,000 Dublin Heritage Park Cemetery Improvements $1,447,764 ----1,447,764 Electric Vehicle (EV) Charging Stations $142,041 ----142,041 Financial System Replacement $1,845,000 ----1,845,000 Green Stormwater Infrastructure $71,715 $310,855 $1,774,325 --2,156,895 Imagine Playground at Dublin Sports Grounds $1,502,671 ----1,502,671 569 Page 15 of 16 Maintenance Yard Facility Improvements $58,350 ----58,350 Parks Playground Replacement ---$1,431,780 -1,431,780 Public Safety Complex - Police Services Building $258,923 ----258,923 Resiliency and Disaster Preparedness Improvements $22,085 $681,010 ---703,095 Restrooms Replacement $83,880 $916,120 ---1,000,000 San Ramon Road Landscape Renovation $238,660 ----238,660 San Ramon Road Trail Lighting $99,335 ----99,335 Solar PV Canopies at The Wave $168,150 ----168,150 Total $17,815,543 $3,838,550 $2,485,780 $2,244,855 $327,715 $26,712,443 570 Page 16 of 16 Approximately 19% or $31.25 million of CIP costs are funded by Special Revenues, where the primary funding sources are State Gas Tax, Measure B/BB Sales Tax, and the Public Art Fund. The Other Funding Sources category includes improvements to be constructed by other agencies and developers, and accounts for 13% or $21.3 million in CIP costs. There is approximately 8% or $12.65 million in project costs that do not have an identified funding source within the CIP timeframe. Future Projects The Future Projects category identifies projects that are beyond the current CIP timeframe, for which a funding source may or may not yet be identified. The following are the projects with future funding needs beyond the CIP timeframe: City Entrance Signs - $180,000 Eastern Dublin Traffic Impact Fee Projects - $57,000,000 Western Dublin Traffic Impact Fee Projects - $8,500,000 Village Parkway Pavement Reconstruction - $10,000,000 Dublin Sports Grounds – Phase 5 Renovation - $2,180,000 Croak Neighborhood Park West - $3,785,000 Croak Neighborhood Park East - $4,163,000 Emerald Glen Recreation and Aquatic Complex – Phase 2 - $16,120,000 STRATEGIC PLAN INITIATIVE: None. NOTICING REQUIREMENTS/PUBLIC OUTREACH: The City Council Agenda was posted. ATTACHMENTS: 1) CIP Update Summary 571 Attachment 1 2020-2025 Capital Improvement Program – General Improvements PROJECT 2020-21 2021-22 2022-23 2023-24 2024-25 Five-Year Audio Visual System Upgrade $65,020 $44,020 $109,040 Citywide Energy Improvements $35,860 $115,780 $365,780 $517,420 Civic Center HVAC and Roof Replacement $4,895,155 $4,895,155 Civic Center Rehabilitation $1,123,050 $222,960 $690,360 $205,000 $2,241,370 Cultural Arts Center $6,773,825 $4,949,904 $11,723,729 Electric Vehicle (EV) Charging Stations $142,041 $142,041 Library Tenant Improvements $35,305 $78,205 $1,726,460 $1,839,970 Resiliency and Disaster Preparedness Imp.$22,085 $681,010 $703,095 Solar PV Canopies at The Wave $168,150 $168,150 TOTAL $12,137,441 $6,991,969 $2,315,200 $690,360 $205,000 $22,339,970 572 2020-2025 Capital Improvement Program – Public Art CATEGORY 2020-21 2021-22 2022-23 2023-24 2024-25 Five-Year Camp Parks Sign $100,450 $400,000 $500,450 Heritage Park $144,700 $375,000 $519,700 TOTAL $100,450 $544,700 $375,000 $0 $0 $1,020,150 573 2020-2025 Capital Improvement Program – Parks CATEGORY 2020-21 2021-22 2022-23 2023-24 2024-25 Five-Year Alamo Creek Park - Fence Replacement $450,000 $450,000 Don Biddle Community Park $24,447,907 $24,447,907 Downtown Dublin Town Square Park $68,020 $29,505 $4,505 $4,505 $4,505 $111,040 Fallon Sports Park - Phase 3 $10,207,421 $10,207,421 Iron Horse Nature Park and Open Space $461,650 $2,502,150 $8,599,200 $11,563,000 Jordan Ranch Neighborhood Square $403,121 $1,110,879 $1,514,000 Parks Playground Replacement $1,431,780 $1,431,780 Restrooms Replacement $83,880 $916,120 $1,000,000 Wallis Ranch Community Park $964,530 $5,734,470 $6,699,000 TOTAL $35,771,758 $7,533,216 $1,577,034 $3,938,435 $8,603,705 $57,424,148 574 2020-2025 Capital Improvement Program – Streets CATEGORY 2020-21 2021-22 2022-23 2023-24 2024-25 Five-Year Annual Street Resurfacing $2,407,543 $2,303,961 $2,303,961 $2,303,961 $2,303,961 $11,623,387 Citywide Bicycle and Pedestrian Imp.$872,698 $389,158 $456,228 $456,228 $456,228 $2,630,540 Citywide Signal Communications Upgrade $2,307,841 $400,320 $236,000 $236,000 $236,000 $3,416,161 Downtown Dublin Street Grid Network $140,840 $60,210 $10,210 $10,210 $10,210 $231,680 Dublin Boulevard Extension - Fallon Road to North Canyon Parkway $1,254,386 $6,669,000 $7,923,386 Dublin Ranch Street Light Improvements $799,595 $40,106 $41,016 $41,016 $41,016 $962,749 Golden Gate Drive Intersection Imp. at Dublin Boulevard and St. Patrick Way $20,630 $112,260 $815,360 $948,250 Green Stormwater Infrastructure $71,715 $310,855 $1,774,325 $2,156,895 Iron Horse Trail Bridge at Dublin Boulevard $10,768,311 $10,768,311 Local Road Safety Plan $117,980 $117,980 St. Patrick Way Extension $3,742,556 $3,742,556 Tassajara Road Realignment and Widening - Fallon Road to North City Limit $10,658,132 $1,865,096 $12,523,228 Tassajara Road Improvements - N Dublin Ranch to Quarry Lane School $7,457,721 $1,500,000 $8,957,721 Traffic Signal Re-Lamping $299,020 $299,020 $598,040 TOTAL $36,738,782 $9,230,242 $13,310,390 $3,458,695 $3,862,775 $66,600,884 575 2020-2025 Capital Improvement Program – Funding Sources Category 2020-21 2021-22 2022-23 2023-24 2024-25 Total General Fund $ 17,815,543 $ 3,838,550 $ 2,485,780 $ 2,244,855 $ 327,715 $ 26,712,443 Special Rev. - Public Works $ 16,459,789 $ 3,037,439 $ 3,187,209 $ 3,187,209 $ 2,888,189 $ 28,759,835 Special Rev - Assmt. Dist.$ 799,595 $ 40,106 $ 41,016 $ 41,016 $ 41,016 $ 962,749 Public Art Fund $ 608,397 $ 544,700 $ 375,000 $ - $ - $ 1,528,097 Traffic Impact Fees $ 18,081,642 $ 1,911,076 $ 20,630 $ 112,260 $ 815,360 $ 20,940,968 Public Facilities Fees $ 21,564,742 $ 11,165,701 $ 3,208,989 $ 2,502,150 $ 4,117,200 $ 42,558,782 Internal Service Funds $ 5,045,925 $ 20,000 $ 90,000 $ 5,155,925 Dublin Crossing Fund $ 1,000,000 $ - $ 1,000,000 Other $ 1,881,676 $ - $ 1,881,676 Developer Built $ 15,691,500 $ 3,742,556 $ 19,434,056 Unidentified $ 8,169,000 $ 4,482,000 $ 12,651,000 Total $98,948,809 $24,300,128 $17,577,624 $8,087,490 $12,671,480 $161,585,531 576 Item 8.2 2020-2025 Five-Year CIP Update City Council April 20, 2021 Capital Improvement Program (CIP) •A CIP is a five-year planning document used by the City to identify and establish budgets for capital improvement projects •Adopted every 2 years.This year is the update. •CIP project budgets are funded from various funding sources, including General Fund, Impact Fees, Assessment Districts, and Grants •CIP funding is annually appropriated, coinciding with the City Budget process 2020-2025 CIP Project Costs CATEGORY 2020-21 2021-22 2022-23 2023-24 2024-25 Five-Year General Improvements $14,981,037 $6,991,969 $2,315,200 $690,360 $205,000 $25,183,566 Public Art $608,397 $544,700 $375,000 $0 $0 $1,528,097 Parks $41,997,952 $7,533,216 $1,577,034 $3,938,435 $8,603,705 $63,650,342 Streets $41,361,423 $9,230,242 $13,310,390 $3,458,695 $3,862,775 $71,223,525 TOTAL $98,948,809 $24,300,127 $17,577,624 $8,087,490 $12,671,480 $161,585,530 2020-2025 CIP General Improvements PROJECT 2020-21 2021-22 2022-23 2023-24 2024-25 Five-Year Audio Visual System Upgrade $65,020 $44,020 $109,040 Citywide Energy Improvements $35,860 $115,780 $365,780 $517,420 Civic Center HVAC and Roof Replacement $4,895,155 $4,895,155 Civic Center Rehabilitation $1,123,050 $222,960 $690,360 $205,000 $2,241,370 Cultural Arts Center $6,773,825 $4,949,904 $11,723,729 Electric Vehicle (EV) Charging Stations $142,041 $142,041 Library Tenant Improvements $35,305 $78,205 $1,726,460 $1,839,970 Resiliency and Disaster Preparedness Imp.$22,085 $681,010 $703,095 Solar PV Canopies at The Wave $168,150 $168,150 2020-2025 CIP Public Art *New Project * CATEGORY 2020-21 2021-22 2022-23 2023-24 2024-25 Five-Year Camp Parks Sign $100,450 $400,000 $500,450 Heritage Park $144,700 $375,000 $519,700 2020-2025 CIP Parks *New Projects * CATEGORY 2020-21 2021-22 2022-23 2023-24 2024-25 Five-Year Alamo Creek Park - Fence Replacement $450,000 $450,000 Don Biddle Community Park $24,447,907 $24,447,907 Downtown Dublin Town Square Park $68,020 $29,505 $4,505 $4,505 $4,505 $111,040 Fallon Sports Park - Phase 3 $10,207,421 $10,207,421 Iron Horse Nature Park and Open Space $461,650 $2,502,150 $8,599,200 $11,563,000 Jordan Ranch Neighborhood Square $403,121 $1,110,879 $1,514,000 Parks Playground Replacement $1,431,780 $1,431,780 Restrooms Replacement $83,880 $916,120 $1,000,000 Wallis Ranch Community Park $964,530 $5,734,470 $6,699,000 2020-2025 CIP Streets *New Projects * CATEGORY 2020-21 2021-22 2022-23 2023-24 2024-25 Five-Year Annual Street Resurfacing $2,407,543 $2,303,961 $2,303,961 $2,303,961 $2,303,961 $11,623,387 Citywide Bicycle and Pedestrian Imp.$872,698 $389,158 $456,228 $456,228 $456,228 $2,630,540 Citywide Signal Communications Upgrade $2,307,841 $400,320 $236,000 $236,000 $236,000 $3,416,161 Downtown Dublin Street Grid Network $140,840 $60,210 $10,210 $10,210 $10,210 $231,680 Dublin Boulevard Extension - Fallon Road to North Canyon Parkway $1,254,386 $6,669,000 $7,923,386 Dublin Ranch Street Light Improvements $799,595 $40,106 $41,016 $41,016 $41,016 $962,749 Golden Gate Drive Intersection Imp. at Dublin Boulevard and St. Patrick Way $20,630 $112,260 $815,360 $948,250 Green Stormwater Infrastructure $71,715 $310,855 $1,774,325 $2,156,895 Iron Horse Trail Bridge at Dublin Boulevard $10,768,311 $10,768,311 Local Road Safety Plan $117,980 $117,980 St. Patrick Way Extension $3,742,556 $3,742,556 2020-2025 CIP Streets (cont.) CATEGORY 2020-21 2021-22 2022-23 2023-24 2024-25 Five-Year Tassajara Road Realignment and Widening -Fallon Road to North City Limit $10,658,132 $1,865,096 $12,523,228 Tassajara Road Improvements - N Dublin Ranch to Quarry Lane School $7,457,721 $1,500,000 $8,957,721 Traffic Signal Re-Lamping $299,020 $299,020 $598,040 2020-2025 CIP Funding Sources Future Projects & Costs Beyond 5-Year CIP Projects & Costs beyond the CIP timeframe ($306.4M) •Electric Vehicle (EV) Charging Stations (Future Phase) •Croak Neighborhood Park East & West* •Downtown Dublin Town Square Park •Dublin Sports Grounds –Phase 5 Renovation* •Emerald Glen Rec & Aquatic Complex -Phase 2* •City Entrance Signs* •Downtown Dublin Street Grid Network •Dublin Boulevard Extension (Future phases) •Eastern Dublin Traffic Impact Fee Projects* •Village Pkwy Pavement Reconstruction* •Western Dublin Traffic Impact Fee Projects* *Future Projects beyond 5-year timeframe. Staff Recommendation •Receive the Report •Provide Direction to Staff on the Update to the Five-Year Capital Improvement Program 2020-2025 Thank You