HomeMy WebLinkAboutItem 4.04 ShannonParkPlanArea
CITY CLERK
File # D~[Q][Q]-~
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: February 1,2005
SUBJECT:
Shannon Park Play Area Renovation
Report Prepared by Rosemary Alex, Parks and Facilities
Development Coordinator
ATTACHMENTS:
I)
2)
Resolution of Award
Budget Change FOI1J1
RECOMMENDATIO¥ :;
Adopt resolution awarding Contract 04-13 to G & G Builders
Inc.
Approve Budget Change
FINANCIAL STATEMENT:
Authorized Budget to Purchase and Install Equipment:
Play Equipment
A vailable Funds to Complete Installation
$136,713
$73. 967
$62,746
Lowest Bid Including Two Alternates
$113,602
In order to award base bid with both alternates (Staff
recommendation) plus a 10% contingency, an additional
appropriation from Unappropriated General Fund Reserve for
$62,216 is required. This budget can be reduced once the deductive
change order is executed.
DESCRIPTION: Aller receiving proposals from several play equipment
representatives, on March 2, 2004 the City Council authori7:ed Starr to issue a purchase order for play
equipment from Ross Recreation Equipment In consideration of Shannon Park's extensive use in the
summer months, the installation of play equipment was delayed until the oft~season_
After a nearly three-week competitive bidding period ending on December 22nd, 2004 the City received a
single equipment installation bid as follows:
1) G & G Builders
Base Bid $84,622
Additive Bid Item #1 Replace Handrail Along Water Feature $6,600
Additive Bid Item #2 Install Bridge Across Water Feature $22.380
Total $113,602
_____________________________~______________________________________________________m_n~_~___________________
COPIES TO: (; and (; Builder, and Ross ;~::n NO. ~
\\Filcscrvcrl\pcs\COUNCIL\Agcnda Statcm~nt1)\2005\2-1 Shonllon Patk Play Equipme:nt.doc
\ Db d..
c
Since there was only one bidder, and the price proposed was beyond the City's current budget, Staff
contacted the bidder to deteI1J1ine whether a lower price could be negotiated for this Project. G & G
Builders submitted a revised proposal as follows:
Base Bid $62,666
Additive Bid ltem #1 Replace Handrail Along Water Feature $5,300
Additive Bid Item #2 Install Bridge Across Water Feature $15.000
Total $82,966
Staff consulted with the City Attorney's office, which advised that the City Council had three options: (1)
the City Council could accept the bid as originally submitted, and award the project to G&G Builders; (2)
the City Council cou.ld reject this bid and direet Staff to re-bid the project; or (3) the City Council eould
accept the bid as submitted, award the project, and direct Staff to issue a deductive change order prior to
issuing the Notice to Proceed to reduce the project cost to the anlOunt proposed by G&G Builders, as
discussed above.
If the City Couneil elects to award the project as originally bid, the Council will also need to approve an
additional appropriation from the Unappropriated General Fund Reserve in the amount of$62,216.
Tflhe City Council elects to rejcet all bids and re-bid the project, it will delay the project construction until
late spring. Further, there will be added costs of advertising, printing and Staff time associated with the
re·bidding process.
Staff recommends that the City Council award contract to G & G Builders and direct Starf to issue a
deductive change order prior to issuing the Notice to Proceed to reduce the project eost to $82,966. Staff
further recommends that both additive bid items be included in the Project The handrail adjacent to the
water feature is rusted out and is in need of replacement. Further, the current play structure includes a
small bridge across the water feature, which, when it is removed, will leave a void over the water feature.
If City Council elects this option, Staff anticipates that total cost for the project will not exceed $91,262.
This option will utilize $28,516 from Unappropriated General Fund Reserves as opposed to $62,216.
In awarding the contract as Staff recommends, the award is 1egally required to be in the full amount
proposed in G&G Builder's submitted bid price. After award of contract Staff would then prepare a
deductive change order in the revised amounts proposed above for signature Jìom G & G Builders. In
conjunetion with the deductive change order, Staff will complete a budget change that will reflect the
reduction in the project cost. These steps will oCCur berore the Notice to Proceed is issued on the project.
If, despite Staff's previous negotiations with G&G Builders, the parties cannot come to a final agreement
on the deductive change order, the City may cancel the contract at little or no additional cost. Starr does
not anticipate that this step will become necessary.
RECOMMENDATION: It is the recommendation of Staff that the City Council adopt the
resolution in Attachment 1 awarding the contract including Additive Bid Items #1 and #2 to G & G
Builders Incorporated with Council's further direction that Staff issue a deductive ehange order prior to
issuing the Notice to Proceed to reduce the Project's cost to $82,966. It is also recommended that the City
Council approve the Budget Change, Attachment 2.
~oo:;1.
\~'2.-
RESOLUTION NO.-
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
**********
AWARDING CONTRACT NO. 04-13
SHANNON PARK PLAY AREA RENOVATION
TO
G AND G BUILDERS INCORPORATED
WHEREAS, the City of Dublin did, on December 22, 2004, publicly open, examine and declare
all sealed bids for doing the work described in the approved Plans and Specifications for Contract No. 04-
13, which Plans and Specifications are hereby expressly referred to for a description of said work and for
all particulars relative to the proceedings under the request for bids; and
WHEREAS, said bids were submitted to the City Engineer, who has reviewed the bids to
determine the lowest bid which was responsive to the requirements of the bid documents.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does
hcceby award Contract No. 04-13 to the lowest responsible bidder therefor, to wit, G and G Builders,
Incorporated, at a base bid of eighty-four thousand sjx hundred and twenty-two ($84,622) and alternate
# 1 at six thousand six hundred dollars ($6,600) and alternate #2 at twenty two thousand three hundred and
eighty dollars ($22,380) the particulars of which bid are on file in the office of the City Engineer.
PASSED, APPROVED AND ADOPTED, this 1st day of February, 2005.
AYES:
NOES:
ABSENT:
ABSTAIN:
Mayor
ATTEST:
City Clerk
ATTACHMENT #1
4,~ ::1--1-0$
CITY OF DUBLIN
BUDGET CHANGE FORM
~oò'.;)..
CHANGE FORM #
New Appropriations (City Councjl Approval Required):
Budget Transfers:
_x_From Unappropriated Reserves
(If Other than General Fund, Fund No -
From New Revenues
From Budgeted Contingent Reserve (I 080Q-799.(00)
__"._ Within Same Department Activity
Between Departments (City Council Approv.1 Required)
Other
Namc;
; ("iim,
Namc; Park Play Area Renovations
$62,216
Acenunt #. OOL95635.750.050
Account #:
Name:
Name:
Account #:
Name~
Account #~
Name:
Account #:
Name~
Account #:
Name~
Account #;
Name.
Account #;
Name;
Account #:
Account #:
ASD/Fin Mgr
(~~~
Date: \ 1'"2- ç ¡oJ
Signature
REASON FOR BUDGET CHANGE ENTRY: Award Contraet 04-13 for Shannon Park Play Equipment
City Manager:
Date:
Signature
As approved at the City Council Meeting on: Date:
Mayor:
Date:
Signature
Posted By:
Date:
Signature
ATTACHMENT #2
H:IC(;-FORMSIFORM-brll1i:tl (.Jlilrtg.;'.'¡'f.