COPIES TO: Wingard Engineering, Inc.
lObi ITEMNO·M
g:\miscproj\Central Pkwy-Tass Ck TS\AS Acceptance
----------------------------.----------------------------------
The project has been satisfactorily completed and Staff recommends that the City Council accept the
improvements under Contract No. 03-02, Traffic Signal at Central Parkway and Tassajara Creek, and
authorize the release of retention after 35 days ifthere are no subcontractor claims.
This project installed a traffic signal on Central Parkway at the intersection of the recreational trail along
Tassajara Creek. The traffic signal enhanced the traffic safety for pedestrians crossing Central Parkway at
this location, including trail users, Dougherty Elementary School students, and residents using Emerald
Glen Park.
DESCRIPTION: On October 21,2003, the City Council awarded Contract No. 03-02,
Traffic Signal at Central Parkway and Tassajara Creek, to Wingard Engineering, Inc.
This project is funded through the City's General Fund.
$ 148,166
$ 156,785
$ 9,219
.$...U.[. 94 7
$ 12,930
~855
Design/Staff/Mise:
Improvements:
Estimated Actual
Budget
FY 2003-2004 budget for this capital project:
.~
FINANCIAL STATEMENT:
,"" "",,,,,,,,,,,0,"'. ~1II'nn ..-
1) Accept the improvements under Contract No. 03-02, Traffic
Signal at Central Parkway and Tassajara Creek
2) Authorize the release of retention after 35 days if there are no
subcontractor claims
RECOMMENDATION:
None
ATTACHMENTS:
Acceptance of Work - Contract No. 03-02, Traffic Signal at Central
Parkway and Tassajara Creek
Report Prepared by: Melissa A. Morton, Public Works Director
SUBJECT:
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: August 3, 2004
CITY CLERK
File # œ[Q]Ø]-~