HomeMy WebLinkAboutItem 4.06 CivCntrElectricalImprCITY CLERK FILE # 200-30 AGENDA STATEMENT CITY COUNCIL MEETING DATE: November 20, 2001 SUBJECT: New Capital Improvement Project: Civic Center Electrical Improvements Report Prepared by: Lee S. Thompson, Public Works Director ATTACHMENTS: Budget change form RECOMMENDATION:/7, j)/ Approve additional appropriation for new capital improvement project to upgrade electrical facilities in the Civic Center and authorize Staff to advertise for bids FINANCIAL STATEMENT: The estimated cost of the project is as follows: Improvements related to Smart Corridor Project: Capacity improvements Total construction estimate: $ 9,000 $ 5,000 $14,000 (includescontingency) Design/project administration/inspection Legal notice and miscellaneous $ 5,000 $ ],ooo Total estimated project cost: $20,000 DESCRIPTION: This proposed project would provide improvements to the Civic Center related to the upcoming 1-580 Smart Corridor project and would also provide a new transformer and subpanel for future use. The 1-580 Smart Corridor project is being managed and processed through the City of Pleasanton, and the City of Dublin does not have a Capital Improvement Project related to this work. The City Council received a presentation a few months ago regarding the Smart Corridor project and the new Traffic Operations Center that will be located in the Police Wing of the Civic Center. The scope of the project, as bid through the City of Pleasanton, does not include improvements related to electrical capacity and facilities in the Civic Center that are required to support the computer equipment and monitors for the Traffic Operations Center and the two office workstations. Staffhas reviewed the scope of work and obtained preliminary estimates from electrical contractors for the work, and the estimated construction g:~raiscproj\elec upgrade COPIES TO: ITEM NO. cost, including contingencies, is $9,000. This includes provision of a transformer, electrical subpanel, wiring, and various electrical outlets and computer cable jacks. At the same time, Staff,has also noted that the existing electrical subpanels are now full. As the building occupancy has increased over the past twelve years, the number ofworkspaces has increased and more circuits have been added to accommodate them, and circuits have been added for additional copiers, computer equipment, and so forth. There are currently three slots left on the last available subpanel in the Administrative Wing, and these slots Mll be needed for a portion of the Smart Corridor equipment. While Building Maintenance Staffhas not been made aware of any other new office equipment being added in the next few months, it would be prudent to provide the additional capacity now, rather than wait until the need arises. Also, unused circuits typically provide the power supply for special events that are held in the courtyard, such as the Tree Lighting and possibly the upcoming 20th Anniversary celebration. Staff` proposes to add a transformer and 200-amp subpanel which Would be located in the main electrical room, at an estimated cost of $5,000 (including contingency). This proposed panel should be sufficient for any foreseeable needs until the next building expansion, which is still several years away. The cost of Staff time, which is essentially contract thrOugh MCE, plus miscellaneous costs, is estimated at $6,000, for a total estimated project cost of $20,000. Staff recommends that the City Council approve an additional appropriation and authorize solicitation of bids for this project. Page 2 CITY OF DUBLIN BUDGET CHANGE FORM New Appropriations (City Council Approval Required): Budget Transfers: CHANGE FORM # __ X__ From Unappropriated Reserves From Budgeted Contingent Reserve (1080-799.000) (If Other than General Fund, Fund No - Within Same D~partment Activity From New Revenues Between Depathxients (City Council Approval Required) Other Name: Name: Civic Center Electrical Improvements (Consmaction) Account #: 001.93936.750.050 ' $14,000 Account #: Name: Name: Civic Center Electrical Improvements (Design, Project Admin., Inspection) $5,000 Account #: Account #: 001.93936.740.000 Name: Name: Civic Center Electrical Improvements Legal Ad $400 Account #: Account #: 001.93936.728.000 Name: --' Name: Civic Center Electrical Improvements Printing Cost $600 Account #: Account #: 001.93936.716.000 Name: Name: Account #: Account #: City Manager: ASD/Fin Mgr Date: Signature Signature REASON FOR BUDGET CHANGE ENTRY: New capital improvement project related to Smart Corridor improvements and electrical capacity in Civic Center. Mayor: Date: Signature Posted By: Date: G:LFREDWORD~Budget Change Form civic center electrical, doc Signature