HomeMy WebLinkAboutItem 4.06 DubBl UUD99-1 ExtTime CITY CLERK
FILE # 1020-30
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: February 20, 2001
SUBJECT:
Extension of Time, Dublin Blvd. Underground Utility District 99-1
Report Prepared by: Lee S. Thompson, Public Works Director
ATTACHMENTS:
Resolution
RECOMMENDATION: ~/f~dopt resolution extending time limit for 12 months
FINANCIAL STATEMENT:
Financial impact is unknown at this time. Additional Rule 20A
funds would be available; however, the cost of construction would
also be expected to increase.
DESCRIPTION: On October 5, 1999, the City Council adopted a resolution of
intention to form Underground Utility District 99-1, Dublin Boulevard from west of Village Parkway to
Sierra Court. This District encompasses the area that is included in the next phase of Dublin Blvd.
Widening. The ordinance establishing the District was adopted on November 16, 1999.
The resolution of intention established certain completion dates which, at the time, were reasonable for
the anticipated construction time frame for the Dublin Boulevard Widening project. The project has
incurred a number of delays, and it is now necessary to extend the dates for completion of the utility
undergrounding work. It is recommended that the dates be extended for eighteen months. The original
date for property owners to be ready for underground services was January 31,2001, and removal of
overhead utility lines was to take place by March 31, 2001. The proposed resolution changes these dates
to July 31, 2002 and September 30, 2002 respectively. There are only three overhead Cable ~:2services
to individual properties which would be affected by the change of date; the other utilities in thisi~area are
already underground.
Staff recommends that the City Council adopt the resolution revising the completion dates.
ll:\miscproj\uldist\revise dates 2-20-01
COPIES TO:
Utility companies; property owners
ITEM NO.
RESOLUTION NO. - O1
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
EXTENDING COMPLETION DATES FOR DUBLIN BOULEVARD
UNDERGROUND UTILITY DISTRICT 99-1
WHEREAS, on October 5, 1999, the City Council adopted Resolution No. 177-99, a resolution of
intention to form Dublin Boulevard Underground Utility District 99-1; and
WHEREAS, said Resolution included completion dates for undergrounding of services to
individual properties and removal of overhead utility lines; and
WHEREAS, the associated Capital Improvement Project has been delayed so that the utility work
cannot be completed by the specified dates;
NOW, THEREFORE, BE IT RESOLVED that the completion dates specified in Resolution 177-
99 are revised as follows:
Property owners shall be ready to receive underground services by July 31, 2002
Overhead utility distribution facilities shall be removed by September 30, 2002
PASSED, APPROVED AND ADOPTED this 20th day of February, 2001.
AYES:
NOES:
ABSENT:
ABSTAIN:
Mayor
ATTEST:
City Clerk
g:krniscproj\ugdisfireso extend dates 2-20-01