HomeMy WebLinkAboutItem 4.08 CivCntFuelUpgrad01-13 CITY CLERK
File # 600-35
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: January 15, 2002
SUBJECT:
Change Order Request, Civic Center Fuel Tank Upgrade,
Contract 01-13
Report Prepared by: Lee S. Thompson, Public lVorks Director
ATTACHMENTS:
1)
2)
Change Order No. 1
Budget Change Form
RECOMMENDATION:
Approve additional appropriation in the mount of $9,081
Approve Contract Change Order No. I in the amount
of $6,300.
FINANCIAL STATEMENT:
of bid award is as follows:
The revised project budget approved by the City Council at the time
Construction:
Design/Inspection:
Miscellaneous:
$24,412
$ 2,500
$ 250
$27,162
Estimated project costs are:
Construction: $28,493
Design/Inspection: $ 2,500
Miscellaneous: $ 250
$31,243
An appropriation in the amount of $4,081 is needed to process this contract change order. However, it
appears some additional work may be necessary to repair aline that will not hold a pressure test, and Staff
is recommending adding an additional $5,000 to cover potential costs.
DESCRIPTION: The Civic Center Fuel Tank Upgrade project was awarded at the November
20, 2001, meeting. At the time of award, the City Council approved an appropriation for additional work
that was required by the Alameda County Environmental Health Service, which is the regulatory agency
for underground fuel tanks. Work on the project is now in progress, and two situations have arisen to
cause the change order request.
g:~rniscprojXfueltank\agstccol
COPIES TO: Paradiso Mechanical
ITEM NO.
1)
Improvements related to pressure testing and provision of watertight fittings, $4,650. The testing
procedure is a new Environmental Health requirement for 2002. Staff and the contractor
recommended installation of the new watertight fittings to ensure passing the test procedure. Staff
was aware of the new requirement and had planned to budget for additional work in the 2002-03
fiscal year; however, it is less costly in the long run to perform the work for the diesel tank now
while the excavation is open.
2)
Additional cost for concrete slab removal, $1,650. The standard thickness of a concrete slab for
this type of fuel tank installation is 6" to 8". The slab at the diesel tank is 18" thick reinforced
concrete. This condition was not noted on any existing plans or recOrd drawings.
In the process of testing the existing fuel lines between the tank and the generator, the contractor has
discovered that at least one of the lines will not hold a pressure test. It is now necessary to excavate to
repair the leak in order to pass the Environmental Health inspection~ The exact cost of the work is not
known at this time, but Staff is recommending that $5,000 be allotted to cover this work.
Staff recommends that the City Council approve the additional appropriation of $9,081 and the change
order in the amount of $6,300.
Page 2
CITY OF DUBLIN · 400 C~lC PLAZA, DUBLIN, CALIFORNIA 94568 ,~, (925) 833-6630 ,~. (925) 829-9248 FAX
CONTRACT CHANGE ORDER NO. I
DATE:
PROJECT/ROAD:
CONTRACT NO:
TO:
January 10, 2002
Civic Center Fuel Tank Upgrade
01-13
PARADISO MECHANICAL, INC., P. O. BOX 1836, SAN LEANDRO CA 94577
PAGE: 1 of 1
You are hereby directed to make the herein described changes from the plans and specifications or do the following
described work not included in the plans and specifications on this contract. Please. note that this chanRe .order is not
effective until approved by the Public Works Director.
This change order is requested by the Contractor.
1. Additional work at agreed price to satisfy Alameda County Hazardous Materials Requirement,
per Paradiso memorandum dated 1/4/02, attached.
2. Additional work at agreed price: compensation for additional thickness of concrete slab
at diesel tank.
$4,650.00
$1,650.00
ESTIMATED COST INCREASE:
$6,300.00
BY REASON OF THIS CHANGE ORDER, THE TIME OF COMPLETION WILL BE ADJUSTED 3 WORKING DAYS.
/ Date
APPROVED BY:
Janet Lockhart Date
Mayor
We, the undersigned COntractor, have given careful COnsideration to the change proposed and hereby agree, if this
proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above,
and perform all services necessary for the work above specified, and will accept as full payment therefor the prices shown
above.
Accepted: Date Contractor:
Signed By: Tit:
If the Contractor does not sign acceptance of this order, his/her atten
specifications as to oroceedin(] with the ordered work and filin(] a written orot
Rece2ved: 1/ 4/2002 5:47PM; ->C2ty of Dubl±n PW/F&Pe; #850; Page 2 ~ ¢/;~i -~
01/04/2002 16:56 FAX 510 614 8396 PARADIS0 MECHANICAL [~02
PARADISO MECHANICAL, INC.
GENERAL & PETROLEUM CONTRACTORS
' and ENVIRONMENTAL SERVICES
A1 Chavarria
City of Dublin_
100 Civic Plaza
Dublin, CA.
Subject: Fuel Tank Upgrade Contract No. 01 - 13
Dear Al:
In response to your request for a bid to make the necessary repairs to your diesel tank
sump per Alameda County Hazardous Materials r~quircments, please see the following:
Test existing F.R.P. pipe sump @ tank connection, and annular tank.
Pick up necessary materials to make repairs.
· Excavate around pipe sump to expose all penetrations.
· Remove piping from sump, cut back primary & secondary lines.
· Patch unused holes, install new water tight bulkhead fittings.
· Cut, fit, & glue primary & secondary pipe back.
· Reroute electrical, install new water tight bulkhead fittings
Extend 24" F.R.P. top hat reducer to prevent water intrusion.
· Test system for Haz. Mat. Inspector.
Total Cost $ 4,6~0.00
Excludes: Hazardous liquid disposal
Please call with any questions you may have. Thank you.
Sincerely,
Eric V. Montesant~
Vice Pl'esident
Received: 1/ 4/2002 5:47PM; ->City of Dublin PW/FiPe; #858; Page 3
01/04/2002 16:.56 FAX §10 614 8.396 PARADIS0 MECHANICAL ~ 003
PARADISO MECHANICAL, INC
.and ENVIRONMENTAL SERVICES .
A1 Chavarria
City of Dublin.
100 Civic Plaza
Dublin, CA,
Subject: Fuel Tank Upgrade Contract No. 0i - 13
Dear Al,
We have encountered a change in conditions, which has caused us additional cost in
regards to the concrete thickness encountered over the Diesel Tank. Industry standards
are 6" to 8" thick concrete over U.S.T.'s_ Existing concrete is approximately 18" thick,
this condition required additional time, disposal and import gravel.
Total Cost $1,650.00
Please call with any questions you may have. Thank you.
Sincerely,
Eric V.
Vice President
Approved By:
A1 Chavarria Date
EXHIBIT "A" CHANGE ORDER FORM
DATE: 1/10/02
PROJECT NAME: Civic Center Fuel Tank Upgrade
CIP #: 93172
CONTRACT # 01-13
PCT. COMPLETED 60
CONTRACTOR Paradiso Mechanical
APPROVED BUDGET AMi'. $24,412 (construction budget)
CONTRACT AMI'. $ 22,193.00
CHANGE ORDER #1 $ 6,300.00
CHANGE ORDER #2 $ -
CHANGE ORDER #3 $ -
CHANGE ORDER #-4 $ -
CHANGE ORDER #5 $ -
CHANGE ORDER #6 $ -
CHANGE ORDER #7 $ -
CHANGE ORDER #8 $ -
CHANGE ORDER #9 $ -
CHANGE ORDER #10 $ -
TOTAL OF ALL CURRENT AND PRIOR CHANGE ORDERS: $ 6,300.00
I
ADJUSTED CONTRACT AMOUNT: $ 28,493.00
I
PROGRESS PAYMENTS MADE
PAYMENT #1 $ -
PAYMENT #2 $ -
PAYMENT #3 $ -
PAYMENT #4 $ -
PAYMENT #5 $ -
PAYMENT #~ $ -
PAYMENT #7 $ -
PAYMENT #8 $ -
PAYMENT #9 $ -
PAYMENT #10 $ -
PAYMENT #11 $ -
PAYMENT #12 $ -
PAYMENT #13 $ -
PAYMENT #14 $ -
PAYMENT #15 $ -
TOTAL PROGRESS PAYMENTS $ -
REMAINING BALANCE ON CONTRACT: $ 22,193.00
RECOMMENDATION: ~- ~.>-J APPROVED APPROVED
_. DENIED DENIED
SIGNATURE: I Supe~v~.'/s'~ City Mayor
Dept Head Manager
CITY OF DUBLIN
BUDGET CHANGE FORM
CHANGE FORM #
New Appropriations (City Council Approval Required):
Budget TransferS:
__X. From Unappropriated Reserves From Budgeted Contingent Reserve (1080-799.000)
(If Other than General Fund, Fund No. - Within Same Department Activity
From New Revenues Between Departments (City Council Approval Required)
Other
Name: Name: Fuel Tank Upgrade
$9,081
Account #: 001.93172.750.050
Account #:
Name: Name:
Account #: Account #:
Name: Name:
Account #: Account #:
Name: Name:
Account #: Account #:
Name: Name: .
Account #: Account #:
City Manager: Date:
Signature
ASD/Fin Mgr r~'~'~-~ ~ Date:
Signature
REASON FOR BUDGET CHANGE ENTRY: Project scope of work increased by revised Health Dept.
requirements and unforeseen conditions which caused additional work
Mayor: Date:
Signature
Posted By: Date!
Signature
CADocuments and Settings~fredmiLocal SettingsiTemporary lnternet File~iOLK21 ~Budget Change Form2.doc