HomeMy WebLinkAboutItem 4.09 DubBlWidDoughScarletCTTY CLERK #600-35
AGENDA STATEMENT
CZTY COUNCTL MEETZNG DATE: February 5, 2002
SUBJECT:
Approval of Change Order Nos. 9 and 10 for Contract No. 00-16,
Dublin Boulevard Widening - Dougherty Road to Scarlett Drive
Report Prepared by: Lee S. Thompson, Public Works Director
ATTACHMENTS:
1)
2)
3)
Contract Change Order No. 9
Contract Change Order No. 10
Change Order Summary
RECOMMENDATION: d~/~Approve Change Order Nos. 9 and 10 for Contract No. 00-16
FINANCIAL STATEMENT:
TOTAL BUDGET:
CITY
$1,216,154.00
Project improvements budget:
DSRSD TOTAL
$ 455,666.00 $1,671,820.00
contract Amount:
Change Orders No. 1-8:
Change Order No. 9
Change Order No. 10
TOTAL CONTRACT AMOUNT:
$1,105,635.50 $ 387,703.00
$ 29,038.25 $ 64,856.10
$ 0.00 $ 2,650.00
$ 36,485.92 $ 0.00
$1,171,159.67
$ 455,209.10
$1,493,338.50
$ 93,894.35
$ 2,650.00
$ 36,485.92
$1,626,368.77
This project is funded through Traffic Impact Fees (300) for City improvements and
General Fund (001) for Dublin San Ramon Services District (DSRSD) improvements.
Improvement costs (plus 7.5% administrative fee) for DSRSD's portion of the project are
being reimbursed by DSRSD back to the City's General Fund. No budget change is
required for Contract Change Order Nos. 9 and 10 as the total contract amount to date is
under the total budget.
Even though the project will still be under budget, the City's policy relating to contract
change orders for capital improvement projects (Resolution No. 18-88) caps the amount of
change orders that the City Manager can approve at 5% of the contract amount.
COPIES TO: McGuire & Hester
g:\miscproj\DBW-dougherty scarlett\AS change orders 9 & 10
ITEM NO.
DESCRIPTION: On February 6, 2001, the City Council awarded Contract No. 00-16,
Dublin Boulevard Widening - Dougherty Road to Scarlett Drive. This project widens Dublin Boulevard
to six lanes from Dougherty Road to Scarlett Drive, including installation of a new traffic signal at the
Dublin Boulevard/Scarlett Drive intersection, and installation of a DSRSD recycled water pipeline. The
project is currently 90% complete.
Contract Change Order No. 9 (Attachment 1) is requested by the City to relOcate a DsRsD air release
valve located in the new street pavement. The City's contractor, McGuire and Hester, will relocate the
existing valve under the existing sidewalk on the northeast comer of the Dublin Boulevard/Scarlett Drive
intersection per the direction of DSRSD. The estimated cost increase for furnishing all materials,
equipment and labor to perform the necessary relocations is $2,650.00.
Contract Change Order No. 10 (Attachment 2) is requested by the City to perform additional work not
described in the Plans and Specifications for removing and relocating an existing maintenance hole, and
repairing the existing pavement east of the Dublin Boulevard/Scarlett Drive intersection. This is
neceSsary in order to accommodate the placement of traffic signal detector loops. This change order also
includes extra work to complete the electrical connection for the new traffic signal system at the Dublin
Boulevard/Scarlett Drive intersection. The estimated cost increase for furnishing all materials, equipment
and labor to perform the work described in Contract Change Order No. 10 is $36,485.92.
Staff has reviewed the Contract Change Orders and recommends that the City Council approve Contract
Change Order Nos. 9 and 10 in the amounts of $2,650.00 and $36,485.92, respectively.
Page 2
CITY OF DUBLIN
100 CIVIC PLAZA, DUBLIN, CALIFORNIA 94568 4. (925) 833-6630 · (925) 829-9248 FAX
CONTRACT CHANGE ORDER NO. 9
DATE:
PROJECT/ROAD:
CONTRACT NO:
TO:
January 7, 2002
Dublin Boulevard Widening - Dougherty Road to Scarlett Drive
00-16
MCGUIRE & HESTER, 9009 Railroad Avenue, Oakland, CA 94603
PAGE: 1 of 1
You are hereby directed to make the herein described changes from the plans and specifications or do the following
described work not included in the plans and specifications on this contract. Please note that this change order is not
effective until approved by the Public Works Director.
This change order is requested by the City.
Furnish all materials, equipment and labor to complete a relocation of one 2" air release valve
from the existing hne at STA 26 00/53 Left, to the sidewalk at STA 26+10/80' Left. This extra
work is to be paid for at the agreed lump sum price of $2,650.00.
$2,650.00
ESTIMATED COST INCREASE:
$2,650.00
BY REASON OF THIS CHANGE ORDER, THE TIME OF COMPLETION WILL BE ADJUSTED
S~.~BY:~ ~T-r'~n ! -'"t - C:~_.
St~e~'t~e-n Yee' '~ -- Date
Ass$ciate Civir Engineer
5 WORKING. DAYS.
~~/. zVAL~MMENDED BY:
Rhodora Bi,Ir'on/.,/ D/ate ¢
Associate Engineer
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this
proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise ~)e noted above,
and perform all services necessary for the work above specified, and_will accept as full payment therefor the prices shown
,,ov,,
AccePted: Date Contractor:
Signed By: ~~~, _. Title:
If the Contractor does not sign a~eptanoe~ this order, his/her a~ent:
specifications as to proceeding with the ordered work and filing a wri~en prot~
CITY OF DUBLIN
100 CiViC PLAZA,.DUBLIN, CALIFORNIA 94568 ,/, (925) 833-6630 & (925) 829-9248 FAX
CONTRACT CHANGE ORDER NO. 10
DATE:
PROJECT/ROAD:
CONTRACT NO:
TO:
January 8, 2002
Dublin Boulevard. Widening - Dougherty Road. to Scarlett Drive
00-16
MCGUIRE & HESTER, 9009 Railroad. Avenue, Oakland, CA 94603
PAGE: 1 of 1
You. are hereby directed to make the herein described changes from the plans and specifications or do the following
described work not included, in the plans and specifications on this contract. Please note that this change order is not
effective until approved by the Public Works Director.
This change order is requested by the City.
Furnish all materials, equipment and labor to remove, an existing 36" maintenance hole frame
and. cover near STA 17+50 and install a 24" maintenance hole frame and cover within the
new median island, as directed by the Engineer. This work shall be paid for at the agreed
lump sum. price of $3,250.00.
Furnish all materials, equipment and labor to remove approximately 1,500 SF of existing AC
pavement to a depth of 1" more than existing AC thickness, as. directed by the Engineer, re-
compact aggregate base to 95%,. and place. Type A, W' max., medium. AC, per-Section 39 of
the Standard Specifications. This work shall be paid. for on a force account (attached).
Furnish all materials, equipment and labor to perform 5,700 SF of 0.15 feet overlay with Type
A, W' max., medium AC, per Section 39 of the Standard Specifications including AC planing
at conforms, as directed by the Engineer. This work shall be paid for on a force account
(attached).
Furnish all materials, equipment and labor to complete connection of PG&E established point
of service to the traffic signal cabinet as directed by the Engineer. This work shall be paid for
at the agreed lump. sum price of $9,430.00.
$3,250.00
$10,091.98
$13,713.94
$9,430.00
ESTIMATED MAXIMUM COST INCREASE:
$36,485.92
BY REASON OF THIS CHANGE ORDER, THE TIME OF COMPLETION WILL BE ADJUSTED
Associate Civil Engineer
Date
25
APPROVAL ~MENDED BY:
~erd Del Rosario~/ Date
Senior Civil Engineer .
WORKING DAYS.
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this
proposal is. approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above,
and perform all services necessary for the work above Specified, and will accept as full. payment therefor the prices shown
above. ' . ~ ' .
AccePted: Date //'~ .~z~----~--'~'~ ~ Contractor:
. Signed By: Title:
If the Contractor does not sign acceptance of this order, hiS/her attentir
specifications as to proceeding with the ordered work and. filing a written prote
DATE: January 28, 2002
CHANGE ORDER SUMMARY
PROJECT NAME:
CIP #:
Dublin Boulevard Widening - Dougherty Road to Scarlett Drive
96890
CONTRACT NO: 00-16
CONTRACTOR: McGuire & Hester
PERCENT COMPLETED: 90%
CONTRACT AMOUNT: $1,493,338.50
APPROVED BUDGET AMT:
$1,671,820.00 (Revised. Budget increased by DSRSD for CCO #4)
CHANGER ORDERS:
CHANGE ORDER #1
CHANGE ORDER #2
CHANGE ORDER #3
CHANGE ORDER #4
CHANGE ORDER #5
CHANGE ORDER #6
CHANGE ORDER #7
CHANGE ORDER #8
CHANGE ORDER #9
CHANGE ORDER #10
$3,000.00
$2,O63.5O
$5,750.00
$29,193.00
$14 781.00
$3 900.00
$20 882.10
$14 324.75
2 650.00
36 485.92
TOTAL OF CHANGE ORDERS: $133,030.27
CURRENT CHANGE ORDER DESCRIPTION:
IModifications to the DSRSD recycled water pipeline and traffic signal system. Install additional conduits across
Dublin Boulevard for future extension of median island.
ADJUSTED CONTRACT AMOUNT:
PROGRESS PAYMENTS MADE:
PAYMENT #1
PAYMENT #2
PAYMENT #3
PAYMENT #4
PAYMENT #5
PAYMENT #6
PAYMENT #7
PAYMENT #8
PAYMENT #9
PAYMENT #10
PROGRESS PAYMENTS:
TOTAL
REMAINING BALANCE ON CONTRACT:
$1,626,368.77
$60,853.00
$74371.00
$121 070.53
$332 893.00
$157 178.00
$340 175.97
$120 894.00
$122 688.95
$84 958.40
$1,415,082.85
$211,285.92
RECOMMENDATION: ~APPROVED
DENIED
SIGNATURES: Public W~ctor
APPROVED
DENIED
City Man~
APPROVED
DENIED
.3.