HomeMy WebLinkAboutItem 4.13 Zumwalt Engr SvcsCITY CLERK # 0600-30
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: June 20, 2000
SUBJECT:
Amendment to Agreement with Zumwalt Engineering Group for
Engineering Services
Report Prepared by: Lee S. Thompson, Public Works Director
ATTACHMENTS:
1)
2)
Resolution and Proposed Amendment (adjustment of rates)
Letter from James Zumwalt dated February 11, 2000,
including comparison of current and proposed rates
RECOMMENDATION: /~Adopt resolution.
FINANCIAL STATEMENT:
Zumwalt Engineering has proposed an adjustment of rates for 2000-
2001 which ranges from 2% to 2.9%. The actual effect of the
adjustment, based on 1999-2000 hours by rate classification, is
2.5%. It is recommended that the existing $550,000 not-to-exceed
limit remain in effect for the 2000-2001 fiscal year. The cost of
Zumwalt's services is primarily paid by private development
reimbursement.
DESCRIPTION: The City has contracted with Zumwalt Engineering Group since
1997 for general engineering services. The scope of work has primarily been in the area of private
development review, and, to a lesser degree, Capital Project design. The current agreement expires June
30, 2001 and provides that an adjustment of rates can be requested effective July 1, 2000.
Zumwalt Engineering's proposed rate schedule reflects increases in amounts ranging from 2% to 2.9%
depending on personnel classification. The increased rates have been applied to an analysis of hours
spent by classification for Fiscal Year 1999-2000 in order to determine the actual effect of the increase.
On the basis of 1999-2000 hours, the overall effect of the increase is approximately 2.5%. The bulk of the
work performed by Zumwalt Engineering is in the area of private development review; therefore, the cost
of their work is paid by developers.
The work performed by Zumwalt Engineering to date has been satisfactory, professional, and competitive,
and Staff recommends that the City Council adopt the resolution approving the amendment to the
agreement.
G:\engr-contracfizumwalfiagstamend99-00. doc
COPIES TO:
James Zumwalt, Zumwalt Engineering Group
ITEM NO. __~
RESOLUTION NO. - 00
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
APPROVING AMENDMENT TO AGREEMENT
WITH ZUMWALT ENGINEERING GROUP
WHEREAS, the City of Dublin, State of California, entered into an agreement with Zumwalt
Engineering Group on July 7, 1998 and subsequently extended said agreement to June 30, 2001; and
WHEREAS, Consultant has requested an adjustment of rates for Fiscal Year 2000-2001 which is
reasonable and commensurate with the Consumer Price Index rate of increase;
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby
approve the amendment to the agreement with Zumwalt Engineering Group, which is attached hereto as
"Exhibit A."
PASSED, APPROVED AND ADOPTED this 20th day of June, 2000.
AYES:
NOES:
ABSENT:
ABSTAIN:
ATTEST:
City Clerk
Mayor
G'lengrL-umwaliresoamendOO-OJ
EXHII~IT "A" OF RESOLUTION -00
AMENDMENT TO AGREEMENT
BETWEEN CITY OF DUBLIN AND ZUMWALT ENGINEERING GROUP
FOR ENGINEERING SERVICES
WFI-EREAS, the City of Dublin (hereinafter referred to as "CITY") and Zumwalt
Engineering Group (hereinafter referred to as "CONSULTANT"), entered into an agreement on July 7,
1998, to provide engineering services to CITY: and
WKEREAS, the City and the Consultant have ex-tended the term of agreement for an
addkionaI two years, terminating June 30, 2001; and
WltF. REAS, Consultant has requested an adjustment of rates for Fiscal Year 2000-2001;
NOW, TI:rF. REFORE, the parties hereto agree as follows:
Adjustment of Rates
The rate schedule attached hereto as Exhibit 1 shall be in effect for Fiscal Year 2000-2001.
The agreement shall have a not-to-exceed limit of $550,000 for Fiscal Year 2000-2001.
CITY OF DUBLIN
ATTEST:
Mayor
City Clerk
ZUMWALT ENGINEE~G GROUP
James W. Zumwalt, Principal
Date:
ZUMWALT ENGINEERING GROUP
2000-2001 CHARGE RATE FEE SCHEDULE
.The compensation of Zumwalt Engineering Group for work done will be on the basis of an hourly charge rate,
plus incurred expenses and will be the sum of all the items set forth below:
A. PERSONNEL SERVICES
PRINCIPAL
SUPERVISING ENGINEER
SENIOR ENGINEER
ASSOCIATE ENGINEER
ASSISTANT ENGINEER
FIELD REPRESENTATIVE
TECHNICIAN/CAD OPERATOR
CLERICAL / OFFICE SUPPORT
TWO-MAN SURVEY CREW
$126 HR
121 HR
111 HR
99 HR
84 HR
79 HR
74 HR
47 HR
168 HR
Rates for individuals may vary depending on the service performed.
EFFECTIVE THROUGH JUNE 30, 2001 AND SUBJECT TO REVISION ANNUALLY
Bo
TRANSPORTATION EXPENSES
1. Thirty-five cents (0.35) per mile for use of vehicles. A minimum of six dollars ($6.00) per hour will
be charged for use of vehicles used for field inspection and supervision.
Co
OUTSIDE SERVICES
1. Invoice cost of services and expenses charged to Zumwalt Engineering Group by outside consultants,
professional, or technical firms engaged in connection with the order, plus 15% handling charge.
MISCELLANEOUS EXPENSES
l. The invoice cost of materials, supplies, reproduction work, and other services procured by Zumwalt
Engineering Group from outside sources, plus a handling charge of 15%. Ail out-of-pocket expenses
not included in Items A, B and C will be included in this category..
ZUMWALT ENGINEERING GROUP
MUNICIPAL STAFF AUGMENTATION
2000-2001 CHARGE RATE FEE SCHEDULE
The compensation of Zumwalt Engineering Group for work done will be on the basis of an hourly charge rate,
plus.incurred expenses and will be the sum of all the items set forth below:
A. MUNICIPAL STAFF AUGMENTATION SERVICES
PRINCIPAL
SENIOR ENGINEER
PROJECT ENGINEER/SURVEYOR
ASSOCIATE ENGINEER
SENIOR DESIGNER
STAFF ENGINEER
FIELD REPRESENTATIVE
CAD DESIGNER
TECHNICIAN/CAD OPERATOR
CLERICAL / OFFICE SUPPORT
97 HR
92 HR
87 HR
81 HR
81 HR
70 HR
70 HR
70 HR
52 HR
42 HR
EFFECTIVE THROUGH JUNE 30, 2001 AND SUBJECT TO REVISION ANNUALLY
TRANSPORTATION EXPENSES
1. Thirty-five cents (0.35) per mile for use of vehicles. A minimum of six dollars ($6.00) per hour will
be charged for use of vehicles used for field inspection and supervision.
OUTSIDE SERVICES
1. Invoice cost of services and expenses charged to Zumwalt Engineering Group by outside consultants,
professional, or technical firms engaged in connection with the order, plus 15% handling charge.
D. MISCELLANEOUS EXPENSES
The invoice cost of materials, supplies, reproduction work, and other services procured by Zumwatt
Engineering Group from outside sources, plus a handling charge of 15%. All out-of-pocket expenses
not included in Items A, B and C will be included in this category.
ZUMWALT ENGINEERING GROUP
Civil Engineering/Project Management
February 11, 2000
Mr. Lee S, Thompson
Public Works Director
CITY OF DUBLIN
P.O. Box 2340
Dublin, CA 94568
2680 Bishop Drive, Suite 150 San Ramon, California 94583
Tel. (925) 830-5016
Fax (925) 830-5023
F--o
Subject:
Proposed contract rates for FY 2000/2001
Dear Mr. Thompson:
This letter is in response to your January 20, 2000 letter requesting our proposed contract rates for
Fiscal Year 2000/2001, as well as any proposed contract, personnel or service level changes.
Attached herewith is our proposed 2000-2001 Charge Rate Fee Schedule. This fee schedule applies to
design projects that are performed on a not-to-exceed basis. Also attached is our proposed 2000-2001
Municipal Staff Augmentation Charge Rate Fee Schedule. This schedule provides for special reduced
rates that apply to assignments in which we serve as an extension of City staff (staff augmentation)' at
City offices or at our offices in San Ramon. For your information, all of our work to date during the
current fiscal year has been performed at the municipal staff augmentation rates.
Please note that both of these fee schedules include a rate increase ranging from 2.0 to 2.9 percent to
offset the increase in the cost of providing services including the retainage and training of qualified
personnel.
Furthermore, we propose to provide the CiD~ with the same personnel and services level as we are
currently prox,iding. However, to accommodate staff's recent refinements to the City plan checking
process, Mark Lander will be the point of contact in lieu of A.D. Dopson. A.D. will continue to
perform plan chec'king services at our office in San Ramon as requested by your staff under the
supervision of' Mr. Lander, P.E. Thank you for the opportunity to provide you this information for the
planning of the-forthcoming year. I look forward to discussing this information with you at your
meeting on Februao~ 17, 2000.
Very truly yours,
ZUMWALT ENGINEERING GROUP
A California Corporation
James W. Zuirfwalt, P.E.
Principal
Attachments
ZUMWALT ENGINEERING GROUP
Fiscal Year 2000-2001 Update
STANDARD RATES
1999-2000 2000-2001
CLASSIFICATION HOURS 1999-2000 TOTAL PROPOSED TOTAL TOTAL COST
TO DATE RATE COST RATE COST % CHANGE
Principal 0 $ 123.00 $ $ 126.00 $ 0%
Supervisin~l Eneineer 0 $ 118.00 $ $ 121.00 $ - 0%
SeniorEneineer 0 $ 108.00 $ $ 111.00 $ - 0%
Associate Engineer 0 $ 97.00 $ $ 99.00 $ - 0%
Assistant En~lineer 0 $ 82.00 $ $ 84.00 $ - 0%
Field Representative 0 $ 77.00 $ - $ 79.00 $ - 0%
Technician/CAD Operator 0 $ 72.00 $ - $ 74.00 $ 0%
!Cencal/Office Support 0 $ 46.00 $ - $ 47.00 $ 0%
Two-Man Survey Crew 0 $ 164.00 $ - $ 168.00 $ 0%
CUMULATIVE EFFECT 0 $ - $ 0%
MUNICIPAL STAFF AUGMENTATION RATES
1999-2000 2000-2001
CLASSIFICATION HOURS 1999-2000 TOTAL PROPOSED TOTAL TOTAL COST'
TO DATE RATE COST RATE COST % CHANGE
Principal 0 $ 95.00 $ $ 97.00 $ 0.0%
Senior Engineer 377 $ 90.00 $ 33,930.00 $ 92.00 $ 34,684.00 2.2%
Proiect Engineer/Surveyor 0 $ 85.00 $ - $ 87.00 $ 0.0%
~Associate Engineer 227 $ 79.00 $ 17,933.00 $ 81.00 $ 18,387.00 2.5%
~Senior Designer 1068 $ 79.00 $ 84,372.00 $ 81.00 $ 86,508.00 2.5%
Staff Engineer 11.5 $ 68.00 $ 782.00 $ 70.00 $ 805.00 2.9%
Field Representative 0 $ 68.00 $ - $ 70.00 $ 0.0%
CAD Designer 105 $ 68.00 $ 7,140.00 $ 70.00 $ 7,350.00 2.9%
Technician/CAD Operator 28 $ 51.00 $ 1,428.00 $ 52.00 $ 1,456.00 2.0%
Clerical 309.5 $ 41.00 $ 12,689.50 $ 42.00 $ 12,999.00 2.4%
CUMULATIVE EFFECT 2126 $ 158,274.50 $ 162,189.00 2.5%
Admin/ZEG General/Budgets/Hours - Rate Increase Worksheet Dublin version .. 2215/00
ZUMWALT ENGINEERING GROUP
MUNICIPAL STAFF AUGMENTATION
2000-2001 CHARGE RATE FEE SCHEDULE
The compensation of Zumwalt Engineering Group for work done will be on the basis of an hourly charge rate,
plus incurred expenses and will be the sum of all the items set forth below:
A. MUNICIPAL STAFF AUGMENTATION SERVICES
PRINCIPAL
SENIOR ENGINEER
PROJECT ENGINEER/SURVEYOR
ASSOCIATE ENGINEER
SENIOR DESIGNER
STAFF ENGINEER
FIELD REPRESENTATIVE
CAD DESIGNER
TECHNICIAN/CAD OPERATOR
CLERICAL / OFFICE SUPPORT
97 HR
92 HR
87 HR
81 HR
81 HR
70 HR
70 HR
70 HR
52 HR
42 HR
EFFECTIVE THROUGH JUNE 30, 2001 AND SUBJECT TO REVISION ANNUALLY
TRANSPORTATION EXPENSES
1. Thirty-five cents (0.35) per mite for use of vehicles. A minimum of six dollars ($6.00) per hour will
be charged for use of vehicles used for field inspection and supervision.
OUTSIDE SERVICES
1. Invoice cost of services and expenses charged to Zumwalt Engineering Group by outside consultants,
professional, or technical firms engaged in connection with the order, plus 15% handling charge.
MISCELLANEOUS EXPENSES
l. The invoice cost of materials, supplies, reproduction work, and other services procured by 7.umwalt
Engineering Group from outside sources, plus a handling charge of 15%. All out-of-pocket expenses
not included in Items A, B and C will be included in this category.
SUPPLEMENT TO
ZUMWALT ENGINEERING GROUP
MUNICI~PAL STAFF AUGMENTATION
2000-2001 CHARGE RATE FEE SCHEDULE
Classification of Employees anticipated to provide services to the City of Dublin during the
2000-2001 Fiscal Year:
Employee 1999-00 Classification 2000-2001 Classification
J. Zumwalt Principal Principal
M. Lander Senior Engineer Senior Engineer
J. Enke Senior Engineer Senior Engineer
C. VanKatwyk Project Engineer Project Engineer
G. Antkowiak Associate Engineer Associate Engineer
M. Coulson Associate Engineer Associate Engineer
M. Uzegbu Associate Engineer Associate Eng~eer
A.D. Dopson Senior Designer Senior Designer
M. Kaseman N/A StaffEngineer
L. Hernandez CAD Designer CAD Designer
Employees other than those listed above are available to the City upon request. Clerical staff support
is available to assist the technical staff'with the preparation of development review documents.