CITY COUNCIL MEETING DATE: January 21, 2003
SUBJECT: Authorization of Additional Improvements for Contract 02-10,
Traffic Signal Upgrade-Village Parkway/Amador Valley Boulevard
Report Prepared by: Lee Thompson, Public kVorks Director
ATTACHMENTS: 1) Resolution
2) Budget Change Form
3) Intersection Map
RECOMMENDATION: 1) Adopt Resolution authorizing implementation of additional
improvements for Contract 02-10, Traffic Signal Upgrade-
~/~"~ Village Parkway/Amador Valley Boulevard
2) Approve budget change
FINANCIAL STATEMENT: The current CIP project to upgrade the traffic signal at Village
Parkway/Amador Valley Boulevard has a budget of $158,020. Staff
proposes that Council appropriate $55,000 from Gas Tax reserves to
fund additional intersection improvements as part of this project.
DESCRIPTION: The City Council, as part of the 2002-2003 Capital Improvement
Program (CIP) Budget, approved a project to upgrade the traffic signal at Village Parkway/Amador Valley
Boulevard to enhance the operation and safety at this intersection. This project will replace all signal
poles with new standard poles and replace the underground wiring system for the traffic signal. The
estimated cost to complete this project is $158,000, which is being funded, in part, by a Federal grant in
the amount of $127,000 through the Hazard Elimination Safety (HES) program. The City has allocated
approximately $31,000 in General Fund monies to cover the full cost of this project. The project design
has been completed and construction is scheduled for Fall 2003.
City Staff proposes to expand the scope of work of this CIP project to add the elimination of the free right
turn island at the southeast comer of the intersection. The parcel adjacent to this comer (previously BP
gas station) is currently vacant and available for future development, and this improvement would help
create an economic incentive, making the property more developable by extending the comer area toward
the street to allow for such amenities as landscaping, seating areas, etc. Based on a recent analysis
conducted by City Staff at this intersection, the elimination of the free right turn at the southeast comer
would allow the intersection to continue operating at an acceptable level of service during the peak traffic
periods under existing and future traffic conditions.
COPIES TO:
ITEM NO. ~_~
G : IMISCPR OJt VP W-A VB Traffic Signal Upgradelagst_vp-avb budget amend, doc
The improvement can be constructed at a significantly lower cost if implemented as part of the CI~
project, rather than being built as a stand-along project. Staff proposes that Gas Tax reserves in the
amotmt of $55,000 be appropriated to fund the additional improvements. The design plans for the
current CIP project can be revised as necessary to incorporate these improvements without affecting
the overall completion schedule of the project.
Staff recommends that the City Council adopt the Resolution authorizing implementation of additional
improvements for Contract 02-10, Traffic Signal Upgrade - Village Parkway/Amador Valley Boulevard,
and approve the budget change to fund the additional improvements.
RESOLUTION NO. - 03
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
AUTHORIZING ADDITIONAL IMPROVEMENTS FOR CONTRACT 02-10,
TRAFFIC SIGNAL UPGRADE - VILLAGE PARKWAY/AMADOR VALLEY BOULEVARD
WHEREAS, the City Council, as part of the 2002-2003 Capital Improvement Program (CIP),
approved a project to upgrade the traffic signal at Village Parkway/Amador Valley Boulevard to enhance
the operation and safety at this intersection; and
WHEREAS, said CIP project will replace all signal poles with new standard poles and replace the
underground wiring system for the traffic signal at this intersection; and
WHEREAS, project design has been completed and construction is scheduled for Fall 2003; and
WHEREAS, the parcel occupying the southeast comer of the Village Parkway/Amador Valley
Boulevard intersection is currently vacant and available for future development; and
WHEREAS, additional intersection improvements to eliminate the free right turn island at the
southeast comer of the intersection can be constructed as part of the existing CF project to make the
property at this comer more developable; and
WHEREAS, the additional improvements to eliminate the free right turn island can be
constructed at a significantly lo.wer cost if implemented as part of the CIP project; and '
WHEREAS, the additional improvements would not affect the construction schedule of the CIP
project and would allow the intersection to continue operating at an acceptable level of service during the
peak traffic periods under existing and future traffic conditions;
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does
hereby authorize the inclusion of additional improvements to eliminate the free right turn island to
Contract No. 02-10, Traffic Signal Upgrade - Village Parkway/Amador Valley Boulevard.
PASSED, APPROVED AND ADOPTED this 21 st day of January, 2003.
AYE S:
NOES:
ABSENT:
ABSTAIN:
ATTEST: Mayor
City Clerk
CITY OF DUBLIN ,9
BUDGET CHANGE FORM
CHANGE FORM #
New Appropriations (City Council Approval Required): Budget Transfers:
X From Unappropriated Reserves From Budgeted Contingent Reserve (1080-799.000)
Within Same Department Activity
From New Revenues Between Departments (City Council Approval Required)
Other
~' ~ :'Name: Name:~: :~'~'~ Trafficiiii [iii ...... Signal Upgrade~i~ iii. iiii ~..~ ii . -ii_ Village"' "" $5~i000 ..... ..........
Parkway/Amador Valley Boulevard
(Expense)
Account #:
Account #: 206-96564-750-050
Name: Name:
Account #: Account #:
Name: Name:
Account #: Account #:
Name: Name:
Account #: Account #:
Name: .Name:
Account #: Account #:
Fin Mgr/ASD: ,r_~"~~" *[/'x,x_~z,~x~-jP,,~ Date:
Signature
IREASON FOR BUDGET CHANGE ENTRY:
To implement additional improvements at the intersection of Village Parkway/Amador Valley Boulevard as
part of the current CIP project (Contract No. 0210) to upgrade the traffic signal at this intersection.
City Manager: Date:
Signature
Mayor: Date:
Signature
Posted By: ~:
Signature : ~
G: 54 GENM1SCIB UDGCHNG_vp-avb budget amend. DOC
~ I O' ' ~ ~, ,,.,, , 0 30 60 120
~ ,: · ~' ~, .~ ~ ~ , ~ ..... -~ '-~ ~AL~ -- I --~V
AMADOR VALLEY / ~~X BOULEVARD
/
PROPOSED'' '~ X '
IMPROVEMENTS ~ /
~ INTERSECTION MAP