TO: Honorable Mayor and City Councilmembers
FROM: Joni Pattillo, City Manager
SUBJE . Presentation by East Bay Regional Park District
Status Update on the Alamo Canal Trail I-580 Undercrossing Project
Prepared By: Ferd Del Rosario, Senior Civil Engineer
EXECUTIVE SUMMARY:
East Bay Regional Park District Trails Development Manager Jim Townsend will update the City
Council on the status of the Alamo Canal Trail I-580 Undercrossing Project. The presentation
will also include discussion of newly acquired National Infrastructure Investments Discretionary
Grant Program (TIGER II) funds for the project.
FINANCIAL IMPACT:
The East Bay Regional Park District is in the process of getting project specific approvals from
the Federal Highway Administration. Once the TIGER II funding is approved, it will be
integrated into the project budget along with other programmed funds.
RECOMMENDATION:
Staff recommends that the City Council receive the presentation.
~
Submitted By
Public Works Director
Reviewed By
Assistant City Manager
r
Page 1 of 2 ITEM NO. '~ • 3 ~
DESCRIPTION:
The City of Dublin is working jointly with the East Bay Regional Park District, the City of
Pleasanton, Caltrans and Zone 7 in constructing a trail underneath I-580 that will connect the
Alamo Canal Trail north of the freeway (adjacent to the City of Dublin Library) with the
Pleasanton trail south of the freeway to transform it to a regional trail.
The trail extension would consist of approximately 713 feet of newly paved trail, with a width of
12 feet to accommodate two-way bicycle traffic and maintenance vehicles. The slope of the
trail is being designed to accommodate people with disabilities, in compliance with the
requirements of the Americans with Disabilities Act.
The City joined together with the East Bay Regional Park District and Pleasanton, applied for
and was approved federal and regional funds to construct the project. East Bay Regional Park
District Trails Development Manager Jim Townsend will update the City Council on the status of
the Alamo Canal Trail I-580 Undercrossing Project. The presentation will also include
discussion of newly acquired TIGER II funds for the project and project schedule.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
Copies of the Staff Report were provided to:
1. Art Dao, ACTC Executive Director
2. Tess Lengyel, ACTC Bike Program Manager
3. Susan Andrade-Wax, Pleasanton Director of Community Service Dept.
ATTACHMENTS: Location Map
G:ICIPWIamo Canal Trail under I-580~,4g St EBRPD Status Update.doc
Page 2 of 2
~l
~,,,, .>
~ ." ~:~
x
'".,r~' . _ 4
Dublin Library
ti~
Pleasanton Trail
Proposed Trail under I-580
ALAMO CANAL TRAIL I-580 UNDERCROSSING PROJECT
PROJECT LOCATION
Alamo Canal Trail
3. 3 Z -~-lr
Attachment 1