HomeMy WebLinkAboutItem 4.02 Maintenance Yard Facilities Accpt Project or 19 82 STAFF REPORT CITY CLERK ` CITY COUNCIL File #600-35 DATE: February 17, 2015 TO: Honorable Mayor and City Councilmembers FROM: Christopher L. Foss, City Manager " SUBJECT: Project Acceptance - Contract No. 12-13/12-14 Maintenance Yard Facilities Prepared by Meghan Tiernan, Parks & Facilities Coordinator EXECUTIVE SUMMARY: The City Council is being asked to consider approval of a final Change Order and acceptance of the improvements under the Contract for construction of the Maintenance Yard Facilities at 5777 Scarlett Court. The project has been completed and the City has had beneficial occupancy of the buildings since July 15, 2014, for Alameda County Fire's Maintenance building and August 28, 2014, for the City of Dublin Corporation Yard building. FINANCIAL IMPACT: Contract 12-13 / 12-14 was awarded to Midstate Construction for $10,276,375 to construct both the Public Safety Complex and the Maintenance Yard Facilities. With the approval of the final Change Order the construction costs will be over-budget by $34,142 as follows. Total Construction Budget $11,353,164 Midstate Contract $10,276,375 Total Change Orders $1,109,931 Total Construction Cost $11,387,306 Difference ($34,142) There is sufficient savings in the total project budget to cover the construction shortfall without allocating any additional funds to the project. RECOMMENDATION: Staff recommends the City Council authorize the City Manager to approve final Change Order Number 111; adopt the Resolution Accepting the Improvements Under Contract No. 12-13/12- 14 Maintenance Yard Facility Improvements; and authorize Staff to accept a maintenance bond in the amount of$1,027,638. Submitted y \ Reviewed By Parks and Community S rvices Director Assistant City Manager Page 1 of 2 ITEM NO. 4.2 DESCRIPTION: On June 18, 2013 the City Council awarded Contract No. 12-13/12-14 to Midstate Construction for the construction of two Capital Improvement Projects, including the Maintenance Yard Facilities at 5777 Scarlett Court and the Public Safety Complex at 6363 Clark Avenue. The City Council formally accepted the improvements for the Public Safety Complex on February 18, 2014. The City received beneficial occupancy of the Alameda County Fire Maintenance building on July 15, 2014, and the City's Maintenance Yard building on August 28, 2014. Midstate has reached completion of the Maintenance Yard Facility Project and Staff has conducted its final inspection. On September 17, 2013, the City Council authorized the City Manager to approve Change Orders for the entire construction contingency of $1,027,637, with the exception of Change Orders that exceeded $50,000. In order to close out the contract the City Council will need to approve a final Change Order in the amount of $67,910. This Change Order includes site work due to additional hardware not in base contract, unforeseen site conditions and resulting delays. The City presently holds a performance bond in the amount of $10,276,375 to provide the necessary security for the performance of the work involved on both projects. Following City Council acceptance of the improvements, the performance security requirement can be reduced, in accordance with authority contained in Section 66499.7 of the Government Code, to an amount necessary to guarantee warranty of the work for a one-year period following acceptance of the work. The Contractor will provide a new maintenance bond in the amount of $1,027,637 which is 10% of the contract amount, and is sufficient to cover the one-year warranty period. Upon City Council acceptance of the project, Staff will file a notice of completion with the Alameda County Clerk. The City will release the 10% retention thirty-five (35) days subsequent to recording the notice of completion with Alameda County so long as all claims on the project have been released. NOTICING REQUIREMENTS/PUBLIC OUTREACH: A Notice of Completion will be filed with Alameda County following City Council acceptance of the improvements. A copy of the staff report was sent to Midstate Construction. ATTACHMENTS: 1. Resolution Accepting the Improvements Under Contract Nos. 12-13 / 12-14 2. Change Order No. 111 Page 2 of 2 RESOLUTION NO. XX - 15 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN * * * * * * * * * * * ACCEPTING IMPROVEMENTS UNDER CONTRACT 12-13/12-14 PUBLIC SAFETY COMPLEX WHEREAS, Midstate Construction entered into a contract with the City of Dublin to construct the Public Safety Complex Project (Contract #12-13/12-14) incorporating the Maintenance Yard Facilities Project (CIP G10509) and the Public Safety Complex Project (CIP G10712) in accordance with the plans and specifications on file with the City Engineer; and WHEREAS, on February 18, 2013 the City Council formally accepted the improvements for the Public Safety Complex portion of the contract work; and WHEREAS, said improvements for the Maintenance Yard Facilities Project portion of the work have been completed in accordance with the plans and specifications, and any approved modifications thereof, to the satisfaction of the City Engineer of the City of Dublin; and WHEREAS, in July 2014 Alameda County Fire had beneficial occupancy of the Fire Maintenance Facility, and in August 2014 the City had beneficial occupancy of the Corporation Yard; and WHEREAS, as a condition of said contract, Midstate Construction is required to warranty the improvements for a period of one year following acceptance of the work by the City of Dublin; and WHEREAS, the original performance bond security requirement can be reduced, in accordance with the authority contained in Section 66499.7 of the Government Code of the State of California, to an amount found necessary to guarantee maintenance of the completed work for aforesaid one-year period. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does herby: 1. Accept the improvements, subject to the aforesaid one-year warranty, and authorize Staff to file a Notice of Completion with Alameda County; and 2. Authorize Staff, if after 35-days of filing the Notice of Completion there are no subcontractor claims, to release the retention and reduce the aforesaid performance bond security requirement upon acceptance by Staff of the replacement maintenance bond in the amount of$648,984 as security for the aforesaid one-year maintenance period; and 3. Authorize Staff to release the original performance bond posted in connection with the portion of the work involved in the construction of said Facility upon acceptance of the warranty. ATTACHMENT 1 PASSED, APPROVED AND ADOPTED this 17th day of February, 2015, by the following vote: AYES: NOES: ABSENT: ABSTAIN: Mayor ATTEST: City Clerk ATTACHMENT 1 19f _ 8 CITY OF DUBLIN 4 100 CIVIC PLAZA,DUBLIN,CALIFORNIA 94568 4 (925)833-6630 4 (925)829-9248 FAX CONTRACT CHANGE ORDER NO. 111 PAGE 1 OF 1 PROJECT: Maintenance Yard—ALCO (#930010) AGREEMENT DATED 1-20-2015 TO: MidState Construction Between MidState Construction and the City of Dublin You are hereby directed to make the herein described changes from the scope of services or do the following described work not included in the scope of services of this contract.The description of work to be done,estimate of quantities, and prices to be paid are complete, accurate and segregate between additional work at contract price, agreed price and force account. Unless otherwise stated,rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. NOTE: This change order is not effective until approved by the City Manager Change requested by: The City of Dublin The last percentage shown is the net accumulated increase or decrease from the original fee in the Agreement. 1. Miscellaneous site work due to unforeseen conditions, additional hardware not in base contract, and delay settlement. Extension of time: 0 Work Days COST INCREASE: $67,910 SUBMITTED BY: APPROVAL RECOMMENDED BY APPROVED BY Meghan Tiernan Date Paul McCreary Date Chris Foss Date Parks &Facilities Dev.Coordinator Parks &Community Services Director City Manager We,the undersigned contractor,have given careful consideration to the change proposed and hereby agree,if this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefore the prices shown above. Accepted,Date: Contractor: MidState Construction By: Principal: I,the undersigned contractor declare under penalty of perjury under the laws of the State of California,and do personally certify and attest that:I have thoroughly reviewed the attached request for change order and know its contents, and said request for change order is made in good faith;that it is supported by truthful and accurate data;that the amount requested and the additional time requested accurately reflects the allowable expenses that would be incurred, and the time necessary,to perform the change order; and further,that I am familiar with California Penal Code section 72 and California Government Code section 12650,et seq.,pertaining to false claims, and further know and understand that submission or certification of a false claim may lead to fines,imprisonment,or other severe legal consequences. If the Contractor does not sign acceptance of this order,his/her attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified CITY OF DUBLIN EXHIBIT"A"CHANGE ORDER FORM DATE: 2/3/2015 PROJECT NAME: Public Safety Complex CIP#: 930016 CONTRACT NO. 12-13/12-14 CHANGE ORDER NO. 111 PERCENT COMPLETE: 100% CONTRACTOR: Midstate Construction CONTRACT AMOUNT: $10,276,375 C.O.AS%OF CONTRACT: 1% ADJUSTED CONTRACT AMOUNT: $11,385,988 Original Contract Work Days 260 Added Contract Work Days 0 ADJUSTED CONTRACT WORK DAYS: 260 CONTRACT CHANGE ORDERS: AMOUNT CHANGE ORDER#98 Cost to add slurry seal to existing parking lot $9,319.00 CHANGE ORDER#99 Cost to expedite shipping for exhaust fans $664.00 CHANGE ORDER#100 Cost to add truncated domes per OPR 014 $11,557.00 CHANGE ORDER#101 Cost to add trash receptacles per ASI 002 $1,605.00 CHANGE ORDER#102 Cost to revise site electrical work at Zone 7 water line $4,567.00 CHANGE ORDER#103 Cost to revise exterior building lighting $1,314.00 CHANGE ORDER#104 Cost for additional Zone 7 revisions to parking lot layout $1,226.00 CHANGE ORDER#106 Cost for additional galvanized railings $2,197.00 CHANGE ORDER#107 Cost for extended general conditions $20,000.00 CHANGE ORDER#108 Cost to remove concrete from old highway $7,461.00 CHANGE ORDER#109 Cost to revise the bioswale area $8,000.00 TOTAL OF ALL CHANGE ORDERS: $ 67,910 PROGRESS PAYMENTS MADE: Pay app#1 $0.00 Pay app#2 $0.00 Pay app#3 $0.00 Pay app#4 $0.00 Pay app#5 $0.00 Pay app#6 $0.00 Pay app#7 $0.00 Pay app#8 $0.00 Pay app#9 $0.00 Pay app#10 $0.00 Pay app#11 $0.00 Pay app#12 $0.00 Pay app#13 $0.00 Pay app#14 $0.00 Pay app#15 $0.00 Pay app#16 $0.00 TOTAL ACTUAL PAYMENTS: 0 ADJUSTED TOTAL CONTRACT: 10,275,375 REMAINING BALANCE ON CONTRACT: 0 CITY OF DUBLIN EXHIBIT"A"CHANGE ORDER FORM DATE: 2/3/2015 PROJECT NAME: Public Safety Complex CIP#: 930016 CONTRACT NO. 12-13/12-14 CHANGE ORDER NO. 111 PERCENT COMPLETE: 100% CONTRACTOR: Midstate Construction CONTRACT AMOUNT: $10,276,375 C.O.AS%OF CONTRACT: 1% Upon execution by representatives authorized to bind the parties,this Change Order will become a part of the contract. The consideration specified in this Change Order(whether an adjustment of the contract price,an adjustment of time,and/or other consideration)is the full and sole compensation owed to the contractor as a result of the changes and issues described in this Change Order. Such consideration includes,but is not limited to,any and all direct and indirect costs incurred by the contractor as a result of the changes and issues described in this Change Order for any labor,equipment,materials,overhead(additional, extended,field and home office),profit,or time adjustments. By signing this Change Order the contractor waives and releases the owner from any and all claims for additional compensation concerning any of the changes and issues specified in this Change Order. The undersigned, being the (Title) of the Contractor, by signing this Change Order declares under penalty of perjury under the laws of the State of California, and does personally certify and attest that: the undersigned has thoroughly reviewed the attached request for change order and knows its contents,and said request for change order is made in good faith;that it is supported by truthful and accurate data;that the amount requested and the additional time requested accurately reflect the allowable expenses that would be incurred,and the time necessary,to perform the change order; and further, that the undersigned is familiar with California Penal Code Section 72 and California Government Code Section 12650 et seq., pertaining to false claims, and further knows and understands that the submission or certification of a false claim may lead to fines,imprisonment,or other severe legal consequences. SIGNATURE: Supervising Dept. Head City Manager Mayor RECOMMENDATION: APPROVED APPROVED APPROVED DENIED DENIED DENIED