Loading...
HomeMy WebLinkAboutItem 4.09 Street Overlay Program~~~~ OF Dp~~~ i9' d-~~~`-'" '82 STAF C I T `~~~~~ FREPORT Y CLERK ~c~~I~~~ DUBLIN CITY COUNCIL File # ^~00-0~ DATE: May 4, 2010 TO: Honorable Mayor and City Councilmembers FROM: Joni Pattillo, City Manager SUBJECT: Award of Bid - Contract No. 10-04, 2009-2010 Annual Street Overlay Program Prepared By: Steven Yee, Public Works Manager EXECUTIVE SUMMARY: The Annual Street Overlay Program (CIP No. 969101) provides for the resurFacing of various streets with placing 1%2" asphalt concrete overlay on top of existing pavement. FINANCIAL IMPACT: The adopted Fiscal Year 2009-2010 total appropriations for this project were $765,375, including design and inspection. Of this amount, $129,950 has been allocated for design and inspection and $635,425 for improvements to be completed under this Contract. Due to State requirements to expend Traffic Congestion Relief Funds (TCRF) within a finro year period, an adjustment is proposed to the amount funded by TCRF. The total amount of the base bid to be awarded is $486,465.37 and allowing for a 10% contingency would create total contract costs that are below the amount budgeted. RECOMMENDATION: 1. Adopt the Resolution awarding Contract No. 10-04, 2009-2010 Annual Street Overlay Program, to G. Bortolotto Co., Inc. 2. Approve the Budget Change form authorizing an adjustment to the amount funded by Traffic Congestion Relief Funds to reflect the balance available. : S` mitted y Public Works Manager ~ Reviewed By Administrative Services Director ~ Re ~ ed By Assistant City Manager Page 1 of 2 ITEM NO. ~~ '_ DESCRIPTION: The Annual Street Overlay project consists of removing and replacing failed asphalt concrete (AC) pavement to a minimum depth of 4 inches on residential streets and 6 inches on collector/arterial streets, resurfacing the street with a minimum 1-1/2-inch overlay of AC, and re- striping pavement markings. Major cracks will be sealed prior to resurFacing in order to prevent the cracks from reflecting through the new AC overlay. . The 2009-2010 Annual Street Overlay Program will repair and overlay the following streets, as shown on the Location Map (Attachment 1): STREETS TO BE INCLUDED IN THE 2009-2010 ANNUAL STREET OVERLAY PROJECT Mulber Place Lewis Avenue Soleado Court S uirrel Creek Circle Mulber Court Beckett Wa Santo Court Quail Creek Circle Wineber Wa Au usta Court Kolb Place Willow Creek Circle Locust Court Via Za ata Bluebell Wa New ort Court Locust Place Za ata Court Lancaster Road C ress Court Re io Court Juarez Lane The project went to bid on April 6, 2010, and a total of ten (10) bids were received on April 20, 2010 (Attachment 2), with the low bid of $486,465.37 submitted by G. Bortolotto & Co., Inc. Staff has reviewed the bid results, checked references, necessary licenses, and recommends that the City Council adopt the Resolution (Attachment 3) awarding Contract No. 10-04, 2009- 2010 Annual Street Overlay Program to G. Bortolotto & Co., Inc., as the lowest responsive bidder. Staff expects the project to begin the end of May 2010 and anticipate completion of the majority of the improvements by June 30, 2010. A minor adjustment to the appropriations is required as described in the Budget Change Form (Attachment 4). Traffic Congestion Relief Funds have requirements for minimum expenditures within established time periods. Based on the balance of these funds as of June 30, 2009, it is necessary to appropriate an additional $2,562 of project costs from this fund. Based on the low bid the total project remains less than the original adopted budget. NOTICING REQUIREMENTS/PUBLIC OUTREACH: 1) The City mailed notices to affected residents and businesses of the upcoming street overlay improvements. 2) As required by the specification, the Contractor will distribute a notice one week in advance of the overlay improvements to all affected residents and businesses. ATTACHMENTS: 1. Location Map 2. Bid Results 3. Resolution awarding Contract 10-04, 2009-2010 Annual Street Overlay Program to G. Bortolotto & Co., Inc., 4. Budget Change Form G:\CIP\Overlay~2009-2010\Staff Report Award of Bid - Overlay.doc Page 2 of 2 2009-2010 Annual Street Overlav Proaram 0 oz5 os 1 Miles ~ Overlay Streets Streets ~City of Dublin Parks RFTA e ~~ ~ SUMMARY OF BID RESULTS - April 20, 2010 ---- ' ' --- ~ CONTRACT 10-04, 2009-2010 ANNUAL STREET OVERLAY PROGRAM -- - -- - i Page 1. - - --- - - --- I ~ _ - ~ -- , ~ - ---- I --- ENGINEER' S E STIMATE G. BOR TOLOTTO ~ BAY CITI ES PAVING O'GRADY PAVING BID ITEM ITEM DESCRIPTION M UNIT EASURE QTY UNIT PRICE TOTAL PRICE UNIT PRICE ~ TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE -- TOTAL PRICE 1 Striping & Marking Removal _ LS 1 $ 7,000.00 $ 7,000.00 $ 2,300.00 $ 2,300.00 $ 2,415.00 $ 2,415.00 $ 2,300.00 $ 2,300.00 2 Plane AC Pavement 12' Wide LF 1,348 $ 1.70 $ 2,291.60 $ 4.01 $ 5,405.48 $ 3.74 $ 5,041.52 $ 5.00 $ 6,740.00 3 Plane AC Pavement 6' Wide LF 24,493 $ 0.85 $ 20,819.05 $ 1.01 $ 24,737.93 $ 1.08 $ 26,452.44 $ 1.00 $ 24,493.00 _ 4 Base Pavement Failure Repairs 4" SF 48,500 $ 2.770 $ 134,345.00 $ 2.37 $ 114,945.00 $ 2.15 $ 104,275.00 $ 2.450 $ 118,825.00 5 Crack Sealing LS 1 $ 12,000.000 $ 12,000.00 $ 8,500.00 $ 8,500.00 $ 11,550.00 $ 11,550.00 $ 12,000.00 $ 12,000.00 6 -- Install1 1/2"ACoverlay _ SF 439,102 $ 0.660 $ 289,807.32 $ 0.655 $ 287,611.81 $ 0.65 $ 285,416.30 $ 0.72 $ 316,153.44 7 Reconstruction - 4" AC SF 8,215 $ 2.77 $ 22,755.55 $ 2.37 $ 19,469.55 $ 2.71 $ 22,262.65 $ 2.400 $ 19,716.00 8 Install Detector Loops EA 8 $ 500.00 $ 4,000.00 $ 370.00 $ 2,960.00 $ 304.50 $ 2,436.00 $ 320.00 $ 2,560.00 9 Adjust Storm Drain Manhole _ EA 3 $ 476.00 $ 1,428.00 $ 301.00 $ 903.00 $ 483.00 $ 1,449.00 $ 700.00 $ 2,100.00 10 ~ ~'~'~ : , Ad~ust Monuments to Grade ~~~,~~ . ~~~~~ ~ ~ ~. _ LF 57 _ $ 320.00 _ $ 18,240.00 - $ 180.00 $ 10,260.00 $ 357.00 $ 20,349.00 $ 250.00 $ 14,250.00 12 ' Install Detail 22 _ LF _ 967 $ 2.20 $ 2,127.40 $ -- 1.71 $ 1,653.57 $ 1.68 $ 1,624.56 $ 1.60 $ 1,547.20 13 Install Detail 23 LF 323 $ 2.20 $ 710.60 $ 1.71 $ 552.33 $ 1.68 $ 542.64 $ 1.60 $ 516.80 14 Install Detail 38A _ LF 105 $ 1.15 $ 120.75 $ 1.40 $ 147.00 $ 1.47 $ 154.35 $ 1.40 $ 147.00 15 Install Arrow Type III (L) EA 1 $ 150.00 $ 150.00 $ 101.00 $ 101.00 $ 99.75 $ 99.75 $ 100.00 $ 100.00 16 Install Arrow Type III (R) EA 1 $ 150.00 $ 150.00 $ 101.00 $ 101.00 $ 99.75 $ 99.75 $ 100.00 $ 100.00 17 18 Install Arrow Type IV (L) _- Install Arrow Type IV (R) ~ EA - EA , 2 _. 2 $ $ 55.00 55.00 $ $ 110.00 110.00 $ $ 63.00 63.00 $ $ 126.00 126.00 $ $ 63.00 63.00 $ $ 126.00 126.00 $ $ 65.00 65.00 $ $ 130.00 130.00 19 -- -- 20 Install 12" Yellow Crosswalk ~ Install 12" White Xwalk or Stop Bar_ _ LF~ -~ LF _ 230 - 740 $ $ 2.80 2.80 $ $ 644.00 2,072.00 $ $ 3.11 3.11 $ $ 715.30 2,301.40 $ $ 3.15 3.15 $ $ 724.50 2,331.00 $ $ 3.00 3.00 $ $ 690.00 2,220.00 21 Install "PED XING" Legend, Thermo. EA 2 $ 188.00 $ 376.00 $ 121.00 $ 242.00 $ 126.00 $ 252.00 $ 130.00 ' $ 260.00 22 -- Install "STOP" Legend, Thermo. -- EA - 22 $ 91.00 $ 2,002.00 $ 111.00 $ 2,442.00 $ 110.25 $ 2,425.50 $ 110.00 $ 2,420.00 23 Install "25" Legend, Thermoplastic EA 4 $ 70.00 $ 280.00 $ 85.00 $ 340.00 $ 89.25 $ 357.00 $ 90.00 $ 360.00 24 _ Install Reflective Markers (Blue)_ _ ~ _ EA _- 35 ___ $ 15.00 _._ $ 525.00 $ 15.00 $ 525.00 $ 15J5 $ 551.25 $ 20.00 $ 700.00 __ - - ~ - ___ -- TOTAL: $ 522,064.27 $ 486,465.37 $ 491,061.21 $ 528,458.44 ~ ~ ~ ~ ~ ~ ~ E. ..~ r~ ~ SUMMARY OF BID RESULTS - May 5, 200 ~ CONTRACT 09-07, 2008-2009 ANNUAL STREET OVERLAY PROGRAM - -- -- ---- Page 2.__ ~ _ - I T DESILV A GATES GALEDRIGE CONSTR. C.F. ARCHIBALD BID ITEM ITEM DESCRIPTION UNIT~ MEASURE i QTY UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE 1 - Striping & Marking Removal LS ~ _~ 1 _ - $ 5,000.00 $ 5,000.00 $ 10,000.00 $ 10,000.00 $ 2,300.00 $ 2,300.00 2 Plane AC Pavement 12' Wide LF 1,348 $ 3.00 $ 4,044.00 $ 2.95 $ 3,976.60 $ 3.00 $ 4,044.00 3 Plane AC Pavement 6' Wide LF 24,493 $ 1.00 $ 24,493.00 $ 0.80 $ 19,594.40 $ 1.00 $ 24,493.00 4 Base Pavement Failure_Repairs 4" _ SF 48,500 $ 2.400 $ 116,400.00 $ 2.50 $ 121,250.00 $ 2.80 $ 135,800.00 5 CrackSealing LS 1 $15,000.000 $ 15,000.00 $ 10,500.00 $ 10,500.00 $ 11,200.00 $ 11,200.00 6 -- Install11/2"ACoverlay SF 439,102 $ 0.750 $ 329,326.50 $ 0.7685 $ 337,449.89 $ 0.72 $ 316,153.44 7 Reconstruction - 4" AC SF 8,215 $ 2.00 $ 16,430.00 $ 2.45 $ 20,126.75 $ 3.65 $ 29,984.75 8 Install Detector Loops _ EA ___ _ 8 _ $ 300.00 $ 2,400.00 $ 350.00 $ 2,800.00 $ 350.00 $ 2,800.00 9 Adjust Storm Drain Manhole _ EA 3 _ - $ 500.00 $ 1,500.00 $ 500.00 $ 1,500.00 $ 350.00 $ 1,050.00 10 ~;~~~, Ad~ust Monuments to Grade ~ ~~ ~~: ~. . : ~. +~~"~m,,,~ ~.,,, . ~ LF - 57 -- $ 250.00 $ 14,250.00 $ 250.00 $ 14,250.00 $ 250.00 $ 14,250.00 12 13 14 _ 15 16 _ 17 Install Detail 22 Install Detail 23 _ _ Install Detail 38A - --- Install Arrow Type III (L) Install Arrow Type III (R) Tlnstall Arrow Type IV (L) LF LF LF i EA_ EA EA 967 323 105 ~ 1 1 2 $ 1.00 $ 1.00 $ 1.00 $ 100.00 $ 100.00 $ 50.00 $ 967.00 $ 323.00 $ 105.00 $ 100.00 $ 100.00 $ 100.00 $ 2.00 $ 2.00 $ 1.50 $ 150.00 $ 150.00 $ 75.00 $ 1,934.00 $ 646.00 $ 157.50 $ 150.00 $ 150.00 $ 150.00 $ 1.65 $ 1.65 $ 1.45 $ 100.00 $ 100.00 $ 65.00 $ 1,595.55 $ 532.95 $ 152.25 $ 100.00 $ 100.00 $ 130.00 ------ ~--- 18 I Install Arrow Type IV (R) EA 2 $_ 50.00 $ 100.00 $ 75.00 $ 150.00 $ 65.00 $ 130.00 19 i Install 12" Yellow Crosswalk LF 230 _ $ 3.00 $ 690.00 $ 3.50 $ 805.00 $ 3.25 $ 747.50 20 r - Install 12" White Xwalk or Stop Bar - LF 740 - - $ 3.00 - $ 2,220.00 -- $ 3.25 $ 2,405.00 $ 3.25 $ 2,405.00 21 Instail "PED XING" Legend, Thermo. EA 2 $ 100.00 $ 200.00 $ 120.00 $ 240.00 $ 125.00 $ 250.00 22 - Install "STOP" Legend, Thermo. --- -- EA --- 22 $ 100.00 $ 2,200.00 $ 105.00 $ 2,310.00 $ 110.00 $ 2,420.00 23 Install "25" Legend, Thermoplastic EA 4 $ 100.00 $ 400.00 $ 100.00 $ 400.00 $ 90.00 $ 360.00 - 24 ~ Install Reflective Markers (Blue) _ EA 35 $ 15.00 $ 525.00 $ 15.00 $ 525.00 $ 16.00 $ 560.00 -- _ __ _ __- _ TOTAL: ~ - $ 536,873.50 $ 551,470.14 $ 551,558.44 W oh ~~ ~ SUMMARY OF BID RESULTS - May 5, 2009 ~ CONTRACT 09-07, 2008-2009 ANNUAL STREET OVERLAY PROGRAM ' Page 3. - -- _ _- - --- - - - -- - - - _ _ _ _ __ GHILOTTI CONSTR. M S CONSTRUCTION GRANITE CONSTR. -- MCK SERVICES BID ~ UNIT - ITEM' ITEM DESCRIPTION ~ MEASURE QTY UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE 1 Striping & Marking Removal LS 1 $ 4,500.00 $ 4,500.00 $ 2,000.00 $ 2,000.00 $ 2,500.00 $ 2,500.00 $ 10,020.00 $ 10 020.00 2 Plane AC Pavement 12' Wide LF i 1,348 $ 5.00 $ 6,740.00 $ 1.00 $ 1,348.00 $ 3.75 $ 5,055.00 $ 1.60 , $ 2,156.80 3 Plane AC Pavement 6' Wide LF 24,493 $ 1.00 $ 24,493.00 $ 1.00 $ 24,493.00 $ 1.00 $ 24,493.00 $ 1.15 $ 28,166.95 4 Base Pavement Failure Repairs 4" SF 48,500 $ 2.500 $ 121,250.00 $ 2.75 $ 133,375.00 $ 3.07 $ 148,895.00 $ 2.97 $ 144,045.00 5 6 CrackSealing In t ll1 1/2"AC LS ~- 1 $10,900.000 $ 10,900.00 $ 7,500.00 $ 7,500.00 $11,000.00 $ 11,000.00 $ 8,500.00 $ 8,500.00 s a overlay SF 439,102 $ 0.800 $ 351,281.60 $ 0.86 $ 377,627.72 $ 0.85 $ 373,236.70 $ 0.93 $ 408,364.86 7 Reconstruction - 4" AC SF T 8,215 $ 3.00 $ 24,645.00 $ 3.10 $ 25,466.50 $ 2.40 $ 19,716.00 $ 2.83 $ 23,248.45 8 9 Install Detector Loops Adjust Storm Drain Manhole EA EA 8 3 $ 300.00 $ 450.00 $ 2,400.00 $ 1,350.00 $ 350.00 $ 400.00 $ 2,800.00 $ 1,200.00 $ 325.00 $ 573.00 $ 2,600.00 $ 1,719.00 $ 308.00 $ 450.00 $ 2,464.00 $ 1,350.00 10 :.: Ad~ust Monuments to Grade . ,. ` LF _ 57 $ 250.00 $ 14,250.00 $ 375.00 $ 21,375.00 $ 250.00 $ 14,250.00 $ 250.00 $ 14,250.00 ~ ~~ 11t l~ ~ ~ ~` ~ ~ ~ ~~~~~ ~ 12 ... , ._ . .~„ Install Detail 22 LF 967 $ 1.00 $ 967.00 $ 1.60 $ 1,547.20 $ 1.60 $ 1,547.20 $ 1.60 $ 1 547.20 13 Install Detail 23 LF ~ 323 $ 1.00 $ 323.00 $ 1.60 $ 516.80 $ 1.60 $ 516.80 $ 1.60 , $ 516.80 14 Install Detail 38A LF 105 $ 1.00 $ 105.00 $ 1.40 $ 147.00 $ 1.40 $ 147.00 $ 1.40 $ 147.00 15 Install Arrow Type III (L) EA 1 $ 95.00 $ 95.00 $ 95.00 $ 95.00 $ 95.00 $ 95.00 $ 95.00 $ 95.00 16 Install Arrow Type III (R) EA 1 $ 95.00 _ $ 95.00 $ 95.00 $ 95.00 $ 95.00 $ 95.00 $ 95.00 $ 95.00 17 Install Arrow Type IV (L) EA 2 $ 60.00 $ 120.00 $ 60.00 $ 120.00 $ 60.00 $ 120.00 $ 60.00 $ 120.00 18 Install Arrow Type IV (R) ~ EA 2 $_ 60.00 $ 120.00 $ 60.00 $ 120.00 $ 60.00 $ 120.00 $ 60.00 $ 120.00 19 Install 12" Yellow Crosswalk LF 230 $ 3.00 $ 690.00 $ 3.00 $ 690.00 $ 3.00 $ 690.00 $ 3.00 $ 690.00 20 Install 12" White Xwalk or Stop Bar LF 740 $ 3.00 $ 2,220.00 $ 3.00 $ 2,220.00 $ 3.00 $ 2,220.00 $ 3.00 $ 2 220.00 21 Install "PED XING" Legend, Thermo. EA 2 $ 120.00 $ 240.00 $ 120.00 $ 240.00 $ 120.00 $ 240.00 $ 120.00 , $ 240.00 22 Install "STOP" Legend, Thermo. EA 22 $ 105.00 $ 2,310.00 $ 105.00 $ 2,310.00 $ 105.00 $ 2,310.00 $ 105.00 $ 2 310.00 23 Install "25" Legend, Thermoplastic EA _ 4 $ 85.00 $ 340.00 $ 85.00 $ 340.00 $ 85.00 $ 340.00 $ 85.00 , $ 340.00 24 Install Reflective Markers (Blue) EA 35 $ 15.00 $ 525.00 $ 15.00 $ 525.00 $ 15.00 $ 525.00 $ 15.00 $ 525.00 TOTAL:' $ 569,959.60 $ 606,151.22 $ 612,430.70 $ 651,532.06 ~ ~ ~ / C~ , lQ ~ RESOLUTION NO. - 10 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN ~~*~~*~** AWARDING CONTRACT NO. 10-04, 2009-2010 ANNUAL STREET OVERLAY PROGRAM TO G. BORTOLOTTO & CO., INC. WHEREAS, the City of Dublin did on April 20, 2010, publicly open, examine, and declare all sealed bids for doing the work described in the approved Plans, Specifications, and Modifications for Contract No. 10-04, 2009-2010 Annual Street Overlay Program, which Plans, Specifications, and Modifications are hereby expressly referred to for a description of said work and for all particulars relative to the proceedings under the request for bids; and WHEREAS, said bids were submitted to the Public Works Director, who has reviewed the bids to determine the lowest bid which was responsive to the requirements of the bid documents; NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby award Contract No. 10-04, 2009-2010 Annual Street Overlay Program, to the lowest responsible bidder therefore, to wit, G. Bortolotto & Co., Inc., at a bid of Four Hundred Eighty- Six Thousand, Four Hundred Si~y-Five Dollars, and Thirty-Seven Cents ($486,465.37), the particulars of which bid are on file in the office of the Public Works Director. BE IT FURTHER RESOLVED that the City Manager is authorized to execute the Agreement. PASSED, APPROVED AND ADOPTED this 4th day of May, 2010, by the following vote: AYES: NOES: ABSENT: ABSTAIN: Mayor ATTEST: City Clerk G:\CIP\Overlay~2009-2010\Resolution of Award.DOC fl~4~r~~~~c~~`~~~° ~ ~ ~ CITY OF DUBLIN ~ BUDGET CHANGE FORM FY 2009 / 2010 CHANGE FORM # Budget Transfers: _ _ From Budgeted Contingent Reserve (1001.1901.81101) Within Same Department Activity __ Between Departments (City Council Approval Required) (~ther New Appropriations (City Council Approval Required) _X~ From Unappropriated Reserves (Fund) From New Revenues Name: EXPENSE - Traffic Congestion Relief Funds (TCRF) - 2010 Overlay Project - Improvements $ 2,562 Project # 969101.9400.9401.2209 GL Account #: 3600.9601.73103 Fin Mgr/ASD: ~Ct~~ Signature Date: ~ ~~3 ( O ~ REASON FOR BUDGET CHANGE ENTRY: The 2010 Annual Street Overlay Project is funded partially from Traffic Congestion Relief Funds (TCRF). Regulations regarding the use of these funds require that funds be expended within certain time frames. This minor additional appropriation will allow for the full expenditure of the balance of TCRF funds that were held as of 6/30/2009, which complies with the regulations. ~ ~ i City Manage~ ~~ . ~~~~=.~~ Date: ~,' Z~,~' I L~ ~: ~„dge, ~ha»ges~~_zoo9_,o~zo_~_a ,o_T~a~APp,opove,,~,.Da~ ATTAC H M E N T#~