HomeMy WebLinkAboutItem 4.3 Maint Yard Improvements CO
STAFF REPORT CITY CLERK
File #600-35
CITY COUNCIL
DATE:April 1, 2014
TO:
Honorable Mayor and City Councilmembers
FROM:
Christopher L. Foss, Acting City Manager
SUBJECT:
Approval of Change Order for Maintenance Yard Improvements
Prepared by Herma Lichtenstein, Parks and Facilities Development Manager
EXECUTIVE SUMMARY:
On June 18, 2013, the City Council awarded ta contract to Midstate Construction to construct
two Capital Improvement Projects - the Maintenance Yard Facilities Project and the Public
Safety Complex Project. Staff is seeking City Council authorization for the City Manager to
approve Change Order #66 to Contract #13-02. This Change Order will allow for the timely
undergrounding of utilities at the Maintenance Yard Facilities Project by Midstate Construction,
as opposed to PG&E, on Scarlett Court.
FINANCIAL IMPACT:
Contract 13-02 was awarded to Midstate Construction for $10,276,375 to construct both the
Public Safety Complex and the Maintenance Yard Facilities. The project budget includes an
allowance of $370,666 for utility undergrounding work that was going to be done by PG&E. The
contractor will now be performing most of the work and therefore a Change Order is necessary
in the amount of $110,000. There are sufficient funds in the project budget to award the
Change Order. Following is a summary of the cost of improvements to date:
Midstate Contract $10,276,375
10% Contingency $1,027,638
Utility installation allowance in budget $370,666
Total Contingency and Allowance $1,398,304
Total Current Change Orders #1-65 $641,704
Proposed Utility Undergrounding CO #66 $110,000
Total remaining Contingency $646,600
RECOMMENDATION:
Resolution
Staff recommends that the City Council adopt a Authorizing the City Manager to
Execute Change Order #66 for Contract 13-02 for the Maintenance Yard Facilities Project.
ITEM NO. 4.3
Page 1 of 2
Submitted By Reviewed By Reviewed By
Parks and Community Administrative Assistant City Manager
Services Director Services Director
DESCRIPTION:
On June 18, 2013, the City Council awarded the contract to Midstate Construction to construct
two Capital Improvement Projects:the Maintenance Yard Facilities Project and the Public Safety
Complex Project. Staff is seeking City Council authorization for the City Manager to approve
Change Order #66 to Contract #13-02. This Change Order will allow for the undergrounding of
utilities at the Maintenance Yard Facilities Project on Scarlett Court.
The plans for the Maintenance Yard Facilities project always anticipated utility underground
work to maximize the available site. During the design process, Staff worked with PG&E to
estimate the cost of the work to underground the overhead electrical utilities. The final PG&E
engineering documents have been approved, and Midstate Construction can complete the work
in a more timely manner than PG&E so as not to delay the project. The underground work will
also incorporate new communication and data lines for both facilities.
The cost of the proposed Change Order is within the project budget contingency, however the
amount of the change order is in excess of the City Manager’s authority for approval of $50,000
as authorized by the City Council on September 16, 2013. In addition, a portion of the utility
installation allowance was budgeted within another line item and is available to cover the cost of
the work.
Staff recommends that Council adopt the Resolution authorizing the City Manager to approve
Change Order #66 in the amount of $110,000.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
A copy of the Staff Report was sent to Midstate Construction.
ATTACHMENTS:
1. Resolution Authorizing the City Manager to Execute Change Order
#66 for Contract 13-02 for the Maintenance Yard Facilities Project,
with the Change Order as Exhibit A to the Resolution
Page 2 of 2
RESOLUTION NO. XX – 14
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
* * * * * * * * * * *
AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER #66
FOR CONTRACT 13-02 FOR THE MAINTENANCE YARD FACILITIES PROJECT
WHEREAS,
Midstate Construction entered into Contract 13-02 with the City of Dublin to
construct a Public Safety Complex Project and the Maintenance Yard Facilities Project in
accordance with plans and specifications on file with the City Engineer;
WHEREAS,
said improvements for Maintenance Yard Facilities Project included utility
underground work originally anticipated to be performed by the utility company (PG&E); and
WHEREAS,
the utility company will be unable to perform the work in a timely manner; and
WHEREAS
, Midstate is capable of completing the work to maintain control of the project
schedule.
NOW, THEREFORE BE IT RESOLVED,
the City Council of the City of Dublin does
hereby authorize the City Manager to execute Change Order #66 (Exhibit A to this Resolution)
in the amount of $110,000 to perform the underground utility work for the Corporation Yard
Project.
PASSED, APPROVED AND ADOPTED
this 1st day of April 2014, by the following vote:
AYES
:
NOES
:
ABSENT
:
ABSTAIN
:
______________________________
Mayor
ATTEST
:
_________________________________
City Clerk
CITY OF DUBLIN
100 CIVIC PLAZA, DUBLIN, CALIFORNIA 94568 (925) 833-6630 (925) 829-9248 FAX
CONTRACT CHANGE ORDER NO. 66
PAGE 1 OF 1
PROJECT: Maintenance Yard – ALCO (#930010) AGREEMENT DATED 2-20- 2014
TO: MidState Construction Between MidState Construction
and the City of Dublin
You are hereby directed to make the herein described changes from the scope of services or do the following described work not included
description of work to be done, estimate of quantities, and prices to be paid are
in the scope of services of this contract. The
complete, accurate and segregate between additional work at contract price, agreed price and force account. Unless
otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be
made for idle time.
NOTE: This change order is not effective until approved by the City Manager
Change requested by: The City of Dublin
The last percentage shown is the net accumulated increase or decrease from the original fee in the Agreement.
1. Cost to underground overhead utilities.
Extension of time: 0 Work Days COST INCREASE: $110,000
SUBMITTED BY: APPROVAL RECOMMENDED BY APPROVED BY
_____________________________
Herma Lichtenstein Date Gary Huisingh Date Chris Foss
Date
Parks & Facilities Develop. Manager Public Works Director City Manager
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal
is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform
all services necessary for the work above specified, and will accept as full payment therefore the prices shown above.
MidState Construction
Accepted, Date: ___________________________ Contractor:
By: ____________________________________ Principal:
I, the undersigned contractor declare under penalty of perjury under the laws of the State of California, and do personally
certify and attest that: I have thoroughly reviewed the attached request for change order and know its contents, and said
request for change order is made in good faith; that it is supported by truthful and accurate data; that the amount requested
and the additional time requested accurately reflects the allowable expenses that would be incurred, and the time necessary,
to perform the change order; and further, that I am familiar with California Penal Code section 72 and California
Government Code section 12650, et seq., pertaining to false claims, and further know and understand that submission or
certification of a false claim may lead to fines, imprisonment, or other severe legal consequences. If the Contractor does not
sign acceptance of this order, his/her attention is directed to the requirements of the specifications as to proceeding with the
ordered work and filing a written protest within the time therein specified
CITY OF DUBLIN
EXHIBIT "A1" TO CHANGE ORDER FORM
DATE:
2/20/2014
PROJECT NAME:
Public Safety Complex
CIP #:
930016
CONTRACT NO.
12-13 / 12-14
CHANGE ORDER NO.
65
PERCENT COMPLETE:
0%
CONTRACTOR:
Midstate Construction
CONTRACT AMOUNT:
$10,276,375
C.O. AS % OF CONTRACT:
7%
ADJUSTED CONTRACT AMOUNT:$11,023,419
Original Contract Work Days260
Added Contract Work Days0
ADJUSTED CONTRACT WORK DAYS:
260
CONTRACT CHANGE ORDERS:AMOUNT
CHANGE ORDER #01SWPPP monitoring$19,838.00
CHANGE ORDER #02Hazmat Panel Abatement$8,743.00
CHANGE ORDER #03Lead Paint Abatement$5,487.00
CHANGE ORDER #04Sewer Line Replacement$24,827.00
CHANGE ORDER #05Misc. Structural Upgrades$100,000.00
CHANGE ORDER #06Misc. Wall Repair$9,396.00
CHANGE ORDER #07Pipe Trim at Concrete Shear Walls$2,527.00
CHANGE ORDER #08Excavate Wet/Pumping Soil from Tank Slab$2,861.00
CHANGE ORDER #09Asbestos Abatement and Cleanup$5,406.00
CHANGE ORDER #10Additional interior concrete slab work $18,857.00
CHANGE ORDER #11Additional interior concrete slab work $24,530.00
CHANGE ORDER #12Additional Geotech prep for building B$1,294.00
CHANGE ORDER #13DSRSD Bonds$1,303.00CHANGE ORDER #12
CHANGE ORDER #14Misc Grading issues$10,022.00
CHANGE ORDER #15Trencing for New Conduit$12,228.00
CHANGE ORDER #16New ATT Conduit$20,043.00
CHANGE ORDER #17revised Trench Drain at Building A$16,258.00
CHANGE ORDER #18Credit for overhead door revisions($2,792.00)
CHANGE ORDER #19Added Infrastructure for damaged ATT lines$12,257.00
CHANGE ORDER #20Demo and remove wood structure$3,329.00
CHANGE ORDER #21Electrical additions to pathway lighting$37,232.00
CHANGE ORDER #22Revisions to landscape, paving, interior framing & finishes$18,221.00
CHANGE ORDER #23Revisions to wah bay equipment$8,542.00
CHANGE ORDER #24Additional floor preparation$3,039.00
CHANGE ORDER #25Modify existing electrical switch gear$4,208.00
CHANGE ORDER #26Remove abandoned Sprint manhole$3,459.00
CHANGE ORDER #27Grading revisions$24,653.00
CHANGE ORDER #28Trash enclosure revisions$6,160.00
CHANGE ORDER #29Remove requirement to delete slab$0.00
CHANGE ORDER #30Caulking additional slab control joints $1,370.00
CHANGE ORDER #31Additional IT Room electrical$10,084.00
CHANGE ORDER #32Expansion joint cover$3,080.00
CHANGE ORDER #33Additional interior electrical & data$1,330.00
CHANGE ORDER #34Additional exterior sign backing$5,580.00
CHANGE ORDER #35Additional mechanical roof curb$1,675.00
CHANGE ORDER #36Additional Irrigation, Sod, Fine Grading, Bark Mulch $8,752.00
CHANGE ORDER #37Additional Exterior Concrete Work $3,620.00
CHANGE ORDER #38Change out Faucets for Instant Hot Sink Opening$995.00
CHANGE ORDER #39Additonal Cost to Replace RWL Piping$2,841.00
CHANGE ORDER #40$1,238.00
Additional Cost for F9 Light Fixture Ballast
CHANGE ORDER #41$22,827.00
Additional AC Paving Repairs
CHANGE ORDER #42$17,250.00
Delay Settlement Waiver
CHANGE ORDER #43$4,565.00
Additional Cost for Parking Lot Seal Coat
CHANGE ORDER #44$1,480.00
Additional Cost to replace Roof Access Ladder
CHANGE ORDER #45$3,960.00
Additional Cost to repair Exterior Accessible Pathway
CHANGE ORDER #46$15,000.00
Additional Cost for DD Fire Dept Valve
CHANGE ORDER #47Credit for PG&E Electrical Connection($18,000.00)
CHANGE ORDER #48Closeout Project Adjustment$8,702.00
CHANGE ORDER #49Credit to delete test pit & add Pump Commander($30,116.00)
CITY OF DUBLIN
EXHIBIT "A1" TO CHANGE ORDER FORM
DATE:
2/20/2014
PROJECT NAME:
Public Safety Complex
CIP #:
930016
CONTRACT NO.
12-13 / 12-14
CHANGE ORDER NO.
65
PERCENT COMPLETE:
0%
CONTRACTOR:
Midstate Construction
CONTRACT AMOUNT:
$10,276,375
C.O. AS % OF CONTRACT:
7%
CHANGE ORDER #50Cost to modify fire sprinkler riser$1,108.00
CHANGE ORDER #51Cost to add roof supports for fire sprinklers$3,907.00
CHANGE ORDER #52Cost to reroute sewer line$3,920.00
CHANGE ORDER #53Cost to add backflow device at steam wash bay$2,520.00
CHANGE ORDER #54Cost for gas pipe revisions$3,377.00
CHANGE ORDER #55Cost for electrical revisions to MSB and sub-panel$21,722.00
CHANGE ORDER #56Cost for electrical revisions to add EF-6A circuit$1,361.00
CHANGE ORDER #57Cost for electrical revisions to the fluid container tank pump grounding$6,161.00
CHANGE ORDER #58Cost for electrical revisions to add future photovoltaic conduit$2,349.00
CHANGE ORDER #59Cost for electrical revisions to add Plymovent exhaust system$54,960.00
CHANGE ORDER #60Cost for electrical revisions to the steam wash canopy$41,026.00
CHANGE ORDER #61Cost to remove fire hydrant connections and valves$6,945.00
CHANGE ORDER #62Cost to re-route fire sprinkler riser$1,042.00
CHANGE ORDER #63Cost to add concrete pad for wash bay equipment$5,452.00
CHANGE ORDER #64($2,330.00)
CHANGE ORDER #65Cost to relocate storm drain$15,363.00
CHANGE ORDER #66Cost to underground utilities$110,000.00
TOTAL OF ALL CHANGE ORDERS:
$ 747,044
PROGRESS PAYMENTS MADE:
$151,944.00
Pay app #1 (930016)
Pay app #2 (930016) $195,860.00
Pay app #3 (930016) $752,605.00
Pay app #1 (930010)$94,941.00
Pay app #1 (930010) $50,663.00
Pay app #2 (930010) $201,964.50
Pay app #2 (930010) $93,927.50
Pay app #3 (930010) $35,363.00
Pay app #3 (930010) $118,743.00
Pay app #4 (930016) $948,498.00
Pay app #4 (930010) $328,980.00
Pay app #4 (930010) $340,994.00
Pay app #5 (930016) $882,018.00
Pay app #5 (930010) $485,398.00
Pay app #5 (930010) $446,912.00
Pay app #6 (930016) $658,049.00
Pay app #6 (930010) $496,563.00
Pay app #6 (930010) $337,367.00
PAYMENT #$0.00
PAYMENT #$0.00
TOTAL ACTUAL PAYMENTS:6,620,790
ADJUSTED TOTAL CONTRACT:11,023,419
REMAINING BALANCE ON CONTRACT:4,402,629
CITY OF DUBLIN
EXHIBIT "A1" TO CHANGE ORDER FORM
DATE:
2/20/2014
PROJECT NAME:
Public Safety Complex
CIP #:
930016
CONTRACT NO.
12-13 / 12-14
CHANGE ORDER NO.
65
PERCENT COMPLETE:
0%
CONTRACTOR:
Midstate Construction
CONTRACT AMOUNT:
$10,276,375
C.O. AS % OF CONTRACT:
7%
Upon execution by representatives authorized to bind the parties, this Change Order will become a part of the contract. The
consideration specified in this Change Order (whether an adjustment of the contract price, an adjustment of time, and/or other
consideration) is the full and sole compensation owed to the contractor as a result of the changes and issues described in this
Change Order. Such consideration includes, but is not limited to, any and all direct and indirect costs incurred by the contractor
as a result of the changes and issues described in this Change Order for any labor, equipment, materials, overhead (additional,
extended, field and home office), profit, or time adjustments. By signing this Change Order the contractor waives and releases
the owner from any and all claims for additional compensation concerning any of the changes and issues specified in this
Change Order.
Theundersigned,beingthe________________________________(Title)oftheContractor,bysigningthisChangeOrder
declaresunderpenaltyofperjuryunderthelawsoftheStateofCalifornia,anddoespersonallycertifyandattestthat:the
undersignedhasthoroughlyreviewedtheattachedrequestforchangeorderandknowsitscontents,andsaidrequestfor
changeorderismadeingoodfaith;thatitissupportedbytruthfulandaccuratedata;thattheamountrequestedandthe
additionaltimerequestedaccuratelyreflecttheallowableexpensesthatwouldbeincurred,andthetimenecessary,toperform
thechangeorder;andfurther,thattheundersignedisfamiliarwithCaliforniaPenalCodeSection72andCaliforniaGovernment
CodeSection12650etseq.,pertainingtofalseclaims,andfurtherknowsandunderstandsthatthesubmissionorcertification
of a false claim may lead to fines, imprisonment, or other severe legal consequences.
SIGNATURE:
Supervising Dept. HeadCity ManagerMayor
____________________________________________________________
RECOMMENDATION:
APPROVED ____________APPROVED ___________APPROVED ____________
DENIED ____________DENIED ____________DENIED ____________