STAFF REPORT
CITY COUNCIL
June 18, 2013
Honorable Mayor and City Councilmembers
CITY CLERK
File #420 -20
FROM:
Joni Pattillo City Manager""' "
SUBJECT: General Plan Amendment Policy and Status Report
Prepared by Jeff Baker, Assistant Community Development Director
EXECUTIVE SUMMARY:
The City Council will consider amending the existing General Plan Amendment Study Policy
which provides direction on the processing of General Plan Amendment Studies. The City
Council will also receive a report on the status of all current General Plan Amendments Studies
in progress.
FINANCIAL IMPACT:
None. The cost to process a General Plan Amendment Study is borne by the project applicant.
RECOMMENDATION:
Staff recommends that the City Council receive the General Plan Amendment Studies Status
Report and adopt a Resolution approving a revised General Plan Amendment Study Policy.
Submitted By
Director of Community Development
DESCRIPTION:
Reviewed By
Assistant City Manager
The City Council adopted a General Plan Amendment Study Policy on October 7, 1997
(Attachment 1). This policy identifies milestones that applicants are required to accomplish
within the first 6 months following City Council initiation of a General Plan Amendment Study.
The intent was to ensure that project applicants demonstrate, by their actions, that they are
actively pursuing the requested entitlements.
Staff recently became aware of this policy which predates the existing development services
Staff. The Policy does not appear to be consistent with the current practices for General Plan
Amendment Studies. Therefore, Staff is recommending that the City Council adopt a revised
General Plan Amendment Study Policy (Attachment 2).
Page 1 of 3 ITEM NO. 8.2
ANALYSIS:
Proposed Policy
Applicants periodically request that the City Council initiate General Plan Amendment Studies.
However, these studies are not always diligently pursued by the Applicant once initiated. This
can lead to uncertainty about the status of an existing Study and difficulty in appropriately
allocating staffing resources.
Staff proposes to revise the General Plan Amendment Study Policy to more closely align with
current practices, the needs of the development community, and the City (Attachment 2). The
proposed Policy outlines actions that are required by the applicant and Staff following the
initiation of a General Plan Amendment Study by the City Council. The proposed Policy also
provides for the expiration of Studies where progress has not been achieved by the applicant.
The proposed Policy has also been revised to address recent concerns raised about the
impacts to the Dublin Unified School District (DUSD) resulting from residential land use
amendments. The proposed policy requires Staff to notify the DUSD of each residential GPA
Study initiated by the City Council and report back to the City Council if the District raises
concerns about the proposed GPA. The DUSD will be provided 60 days in which to respond
once it is notified. Staff will also continue the current practice of notifying the District when the
City Council first holds a meeting to consider initiating a GPA Study.
The following identifies the proposed key milestones and actions by the applicant and Staff:
Applicant
• Commence Planning and Environmental Studies within 6 months of initiation.
• Submit completed GPA application and Environmental Checklist within 12 months of
initiation.
Staff
• Notify the Dublin Unified School District regarding each General Plan Amendment Study
to change a residential land use designation and provide a report back to the City Council
if the DUSD is not able to support the proposed Amendment.
• Provide the City Council with a report on the progress of all GPA Studies with the annual
General Plan Progress Report in March of each year.
The Policy provides realistic and measurable actions to confirm that applicants are making
progress. This will enable the City to allocate resources as appropriate to process these
requests in a timely manner while continuing to meet the operating needs of the City. This will
also provide a mechanism to update the City Council on the studies.
GPA Study Status Report
Please refer to Attachment 3 for the status of all current General Plan Amendment Studies that
have been initiated by the City Council.
Page 2 of 3
CONSISTENCY WITH THE GENERAL PLAN, SPECIFIC PLAN AND ZONING ORDINANCE:
The adoption of a revised General Plan Amendment Study Policy is consistent with the General
Plan, applicable Specific Plans and the Zoning Ordinance in that the Policy is intended to
establish General Plan Amendment Study procedures. The proposed Policy does not change
any land use designations or zoning designations.
ENVIRONMENTAL REVIEW:
This project is exempt from the California Environmental Quality Act (CEQA) per CEQA
Guidelines Section 15061(b)(3). Section 15061(b)(3) states that CEQA applies only to those
projects that have the potential to cause a significant effect on the environment. The adoption of
a General Plan Amendment Study Policy is an activity that is exempt from CEQA because it
does not allow the construction of any building or structure, but sets forth procedures that shall
be followed if an applicant requests to initiate a General Plan Amendment Study. This policy,
therefore, has no potential for resulting in significant physical change in the environment, directly
or ultimately.
NOTICING REQUIREMENTS /PUBLIC OUTREACH:
Public noticing is not required for the City Council to adopt a policy for processing General Plan
Amendment Studies. Although not required, the City mailed notices to the development
community, and to all property owners /applicants that are currently processing General Plan
Amendments. A notice was also published in the Valley Times and posted in the designated
posting places throughout the City. A copy of this Staff Report was made available on the City's
website.
ATTACHMENTS: 1. City Council Resolution 119 -97 adopting a General Plan Amendment
Study Policy, with the Policy attached as Exhibit A
2. Proposed General Plan Amendment Study Policy Dated June 18,
2013
3. General Plan Amendment Study Status Report
Page 3 of 3
RESOLUTION NO. 119 - 97
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN
ADOPTING A GENERAL PLAN AMENDMENT POLICY
WHEREAS, the City Council has determined that it is important to establish criteria to judge the
progress of a General Plan Amendment once the City Council has initiated such a study; and
WHEREAS, it is in the interest of the City of Dublin to have applicants demonstrate by their
actions that the proposed amendment is proceeding towards completing formal applications; and
WHEREAS, a reasonable time should be afforded applicants to start necessary planning and
environmental studies leading up to the filing of a formal application.
NOW, THEREFORE, BE IT RESOLVED that the City Council does hereby adopt the attached
General Plan Amendment Policy (Exhibit A), and Staff is authorized to utilize said policy in dealing with
all requests for General Plan Amendment in the future.
BE IT FURTHER RESOLVED that the General Plan Amendment applicants shall pay for all
processing costs involved with the General Plan Amendment policy.
PASSED, APPROVED, AND ADOPTED this 7th day of October, 1997.
AYES: Councilmembers Barnes, Howard, Lockhart and Mayor Houston
NOES: Councilmember Burton
ABSENT: None
ABSTAIN: None A'J 4-vk
MAYOR
ATTEST:
CIT C i RK
K2 1G /10- 7- 97 1reso gpa.doc
G`�Y of D�QfI� CITY OF DUBLIN
'';i� Ixl'
is;— '�" —t'ezl GENERAL PLAN AMENDMENT
(GPA)
CgLIFOR
POLICY
PURPOSE- From time to time, various applicants file requests for consideration of a General
Plan Amendment for properties in the City and adopted sphere of influence. This
policy identifies what is required of the applicant after a GPA study has been
authorized and related timetables.
REQUIRED ACTIONS BY GPA APPLICANT WITHIN 6 MONTHS OF
AUTHORIZATION
1. Start Planniniz and Environmental Studies
a) Determine what kind of project should be considered
b) Begin environmental reconnaissance analysis of site
C) Start land use feasibility of proposed uses and the
benefits of the project to the City
d) Contact staff about the applicant's planning team
e) Begin discussing alternatives with staff
f) Give staff a written monthly report on progress related to activity
2. File a completed General Plan Amendment application and Environmental Checklist
a) Prepare and submit application for a General Plan Change
b) Complete environmental checklist regarding the proposed change
C) Pay appropriate fees for staff review
At the end of six months, staff will return to the City Council to report on progress. Staff will
identify whether monthly written reports and/or GP applications have been filed in the past six
months in accordance with 1 and 2 above.
CITY COUNCIL ACTION AT 6 MONTHS REVIEW
The City Council, by minute order, will direct staff to continue to process the affected GPA or
will rescind its previous action authorizing the GPA based on compliance with the steps
identified above.
dated: October 7, 1997 v
g:corresp /ep /projspec /gpapoiic EXHIBIT A
ribim
General Plan Amendment Study Policy
June 18, 2013
Purpose: Applicants periodically request the initiation of a General Plan Amendment (GPA) Study to
consider amending the City's adopted General Plan. This policy identifies the steps necessary to initiate
a GPA Study and identifies what is required of the project proponent and Staff, and the related time
table after the City Council has authorized the initiation of a GPA Study.
Actions to Initiate a General Plan Amendment Study
1. The project proponent submits a letter and applicable exhibits requesting that the City Council
initiate a General Plan Amendment Study.
2. Staff prepares a brief Staff Report to the City Council requesting consideration to authorize the
initiation of a General Plan Amendment Study.
3. The City Council, by majority vote, determines whether or not to authorize the initiation of a General
Plan Amendment Study.
Actions by the project proponent within 12 months of initiation
1. Commence Planning and Environmental Studies within 6 months of initiation.
a. Refine the project type and scope;
b. Begin environmental reconnaissance analysis of the site;
c. Start land use feasibility of the proposed use and the benefits of the project to the City; and
d. Begin discussing project alternatives with Staff.
2. Submit a GPA application and Environmental Checklist within 12 months of initiation.
Actions by Staff following initiation
1. Notify the Dublin Unified School District (DUSD) regarding each General Plan Amendment Study to
change a residential land use designation and provide a report back to the City Council if the DUSD is
not able to support the proposed Amendment. Within 6o days of the notification to DUSD, the
DUSD shall provide a preliminary response.
2. Authorization of a GPA Study will expire if the activities by the applicant, as described above, have
not occurred within 12 months of initiation. Staff will notify the City Council when such expirations
have occurred.
3. Applications where no substantive activity has occurred in the prior 12 months may be deemed by
Staff to be inactive and withdrawn. Staff will notify the City Council when such actions have been
taken.
4. Staff will provide the City Council with a report on the progress of all current GPA Studies with the
annual General Plan Progress Report in March of each year.
Active General Plan Amendment Study - Status Report
Updated through May 30, 2013
Council
Estimated
Project Dame
Project 'De cri tion
Status
Initiation
Council
Date
Hearing Date
Bikeways Master Plan
GPA to ensure consistency between the
Draft Bikeways Master Plan under review for necessary
N/A
Summer 2013
General Plan and the Bikeways Master
changes to the General Plan.
Plan update.
Camp Parks /Dublin
GPA, Specific Plan, Tentative Maps,
Draft Specific Plan and Draft EIR nearing completion.
4/15/03
Nov -13
Crossings
Development Agreement, EIR, and
Anticipate releasing the Draft EIR for public comment on
related entitlements for development of
6/21. Working on street alignment and need phasing
a 187 acre project site with up to 1,996
plan from applicant. Applicant finalzing deal points
residential units, 225,000 SF of
proposal for CC consideration.
commercial, and related parks, school
site, and infrastructure.
Dublin Preserve (Doolan
Request to amend the City of Dublin
Currently working with Livermore and EPS on a
12/7/10
TBD
Canyon)
Sphere of Influence and General Plan to
development feasibility study.
include the Doolan Canyon Area.
Energy Conservation
Create an Energy Conservation
City Council prioritized this project for FY 2014.
6/21/11
Spring 2014
Element
Element.
Preparing to initiation project.
Frederich /Vargas
GPA, SPA, PD Rezone, Site
Applicant finalizing the project description to enable Staff
8/21/12
Fall 2013/
Development Review, and Vesting
to begin the CEQA analysis (likely an Addendum). Staff
Winter 2014
Tentative Map to change the land use
is working with the applicant on the right -of -way
on the Fredrich property from
acquisition for the Moller Creek overcrossing. Applicant
neighborhood Commercial and Medium-
still needs to provide development proposal for review.
High Density residential to Medium
Density Residential and develop the two
properties as one project.
Green @ Park Place
GPA, SPA, PD Rezone, Site
Applicant finalizing the project description (i.e. unit count
2/5/13
Spring 2014
Development Review, Map, and
& commercial s.f.) in order to start the CEQA analysis
Development Agreement.
and prepare the Supplemental EIR. KMA ready to
proceed with fiscal analysis once project description is
completed.
Heritage Park
GPA, SPA, Rezone, Site Development
Applicant preparing the project description in order to
11/20/12
Winter 2014
Review, and Tentative Map for 55 -60
start the CEQA Analysis and EIR. Staff is working with
single - family residential units and a
the applicant on geological issues related to the
157000 SF office bldg.
earthquake fault line running through the property. Staff
has received initial elevations for review. Applicant will
submit revised subdivision map once geological issue
resolved.
Site 16A - Regency Centers
GPA, SPA, PD Rezone, Site
Finalizing the Supplemental EIR and anticipate releasing
11/20/12
Winter 2014
Development Review, Tentative Map,
draft for public review in late July. Applicant to submit
and Supplemental EIR for a retail
project plans for review.
commercial center with up to 167,200
square feet of gross floor area on 14.3
acres.
Schaefer Ranch Unit 3
GPA, PD Rezone, and Vesting
Applicant has completed the project description.
2/7/12
Fall 2013
Tentative Map to change land use from
Preparation of CEQA Addendum underway. Proposed
Open Space and Estate Residential to
subdivision map under review. Applicant preparing
Single Family Residential.
proposed development standards of PD and architecture
for SDR.
UP ROW
GPA to assign a Parks /Public
Currently under review and working with P &CS.
3/19/13
Sep -13
Recreation land use designation for use
Preparing a Mitigated Negative Declaration for the
as a City park.
project.
Water Conservation
Create a Water Conservation Element
Draft Element is complete. Planning Commission
6/21/11
6/18/2013
Element
recommended approval on 5/28/13. Scheduled for City
Council consideration on June 18.
RESOLUTION NO. XX - 13
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
* * * * * * * * * * * * * * * * * * * * *
APROVING A REVISED GENERAL PLAN AMENDMENT STUDY POLICY
WHEREAS, the City Council has determined that it is important to establish
criteria by which to judge the progress of a General Plan Amendment Study once
initiated by the City Council; and
WHEREAS, it is in the interest of the City of Dublin to have applicants
demonstrate by their actions that they are proceeding towards completing formal
applications; and
WHEREAS, a reasonable time should be afforded applicants to start necessary
planning and environmental studies leading up to the filing of a formal application; and
WHEREAS, the Dublin Unified School District should be notified of proposed
General Plan Amendments and have adequate time to provide feedback regarding
potential negative impacts to the District; and
NOW, THEREFORE, BE IT RESOLVED that the Dublin City Council does
hereby adopted the General Plan Amendment Study Policy attached as Exhibit A and
Staff is authorized to utilize said policy to process all future General Plan Amendment
requests.
BE IT FURTHER RESOLVED that the applicant for a General Plan Amendment
shall pay for all costs associated with preparing the General Plan Amendment Study
and processing the General Plan Amendment application.
PASSED, APPROVED AND ADOPTED this 18th day of June 2013 by the
following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
1 of 2
Mayor
ATTEST:
City Clerk
G:lAgendas120131GPA PolicylAtt 2 CC Reso GPA Policy 6.18.13.doc