HomeMy WebLinkAbout4.05 DubBlWid #7&#8 #00-16CTTY CLERK FILE # 600-35 AGENDA STATEMENT CTTY COUNCTL MEETZNG DATE: October 2, 2001 SUBJECT: Approval of Change Orders No. 7 and 8 for Contract No. 00-16, Dublin Boulevard Widening - Dougherty Road to Scarlett Drive Report Prepared by: Lee S. Thompson, Public Works Director ATTACHMENTS: 1) 2) 3)' Contract Change Order No. 7 Contract Change Order No. 8 Change Order Summary RECOMMENDATION: ~d~Approve Change Order Nos. 7 and 8 for Contract No. 00-16 FINANCIAL STATEMENT: Prqject improvements budget: Contract Amount: Contingency: Total Budget: City DSRSD Total $1,105,635.50 $ 387,703.00 $1,493,338.50 $ 110,518.50 $ 67,963.00 $ 178,481.50 $1,216,154.00 $ 455,666000 $1,671,820.00 Change Order Nos. 1-6: $ Change Order No: 7 $ Change Order No. 8 $ Total Change Orders: $ 14,713.50 $ 43,974.00 $ 58,687.50 0.00 $ 20,882.10 $ 20,882.10 14,324.75 $ 0o00 $ 14,324.75 29,038.25 $ 64,856.10 $ 93,894.35 The project is funded through Traffic Impact Fees (300) for City improvements and General Fund (001) for Dublin San Ramon Services District (DSRSD) improvements. Improvements costs (plus 7.5% administrative fee) for DSRSD's portion of the project are being reimbursed by DSRSD back to the General Fund. No budget change is required for Contract Change Order Nos. 7 and 8 as total of the change orders to date is within the contingency amount. Even though the project will still be under budget, the City's policy relating to contract change orders for capital improvement projects (Resolution No. 18-88) caps the amount of change orders that the City Manager can approve at 5% of the contract amount. g:\miscproj\DBW-dougherty scarlettkAS change order COPIES TO: DSRSD ITEM NO. DESCRIPTION: On February 6, 2001, the City COuncil awarded Contract No. 00-16, Dublin Boulevard Widening - Dougherty Road to Scarlett Drive. This project widens Dublin BoUlevard to six lanes from Dougherty Road to Scarlett Drive, including installation of a new traffic signal at the Dublin BOulevard/Scarlett Drive intersection, and installation of a DSRSD recycled water pipeline. The project is currently 80% complete. 'Contract Change Order No. 7 (Attachment 1) is requested by DSRSD to perform extra work as part of the recycled water pipeline installation. The City's contractor, McGuire and Hester, encountered several utilities shown incorrectly on the plans and is required to make pipeline adjustments to accommodate existing conditions. The estimated cost increase for furnishing all materials, equipment and labor to. perform the necessary adjustments is $20,882.10~ Contract Change Order No. 8 (Attachment 2) is requested by the City to perform additional work not described in the Plans and Specifications for the traffic signal system and street lighting. Conduits will be added to complete the traffic signal interconnect on Dublin Boulevard to the traffic signal at DeMarcus Boulevard. This change order also includes placing conduits across Dublin Boulevard (east of Scarlett Drive) for the future median island construction between Scarlett Drive and DeMarcus Boulevard. Installing the median irrigation and subdrain conduits prior to resurfacing Dublin Boulevard will eliminate the need to trench across the new pavement. Staff has reviewed the change orders and recommends that the City Council approve Contract Change Order Nos. 7 and 8 in the amounts of $20,882.10 and $14,324.75, respectively. Page 2 CITY OF DUBLIN · 400 c~v~c PLAZA, DUBLIN, CALIFORNIA 94568 .t. (925) 833-6630 CONTRACT CHANGE ORDER NO. 7 (925) 829-9248 FAX DATE: PROJECT/ROAD: CONTRACT NO: TO: September 17, 2001 Dublin Boulevard Widening - Dougherty Road to Scarlett Drive 00-16 MCGUIRE & HESTER, 9009 Railroad Avenue, Oakland, CA 94603 PAGE: 1 of 1 You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract. Please note that this change order is not effective until approved by the Public Works Director. This change order is requested by Dublin San Ramon Services District (DSRSD). Furnish all materials, equipment and labor to properly support the exposed 16" CWR pipeline during the installation of the 24" recycled water pipeline near STA-RW 11+50, as directed by DSRSD. This extra work is to be paid for on a force account basis, as shown on approved Extra Work Report. Furnish all materials, equipment and labor to properly realign 24" recycled water pipeline near existing 54" storm drain pipe at STA-RW 12+20, as directed by DSRSD. This extra work is to be paid for on a force account basis, as shown on approved Extra Work Report. Furnish all materials, equipment and labor to relocate and resize blow-off from STA 15+46 to STA 15+83, as directed by DSRSD. This extra work is to'be paid for on a force account basis, as shown on approved Extra Work Report. Furnish all materials, equipment and labor to install a 24" flange adapter to existing 24" RW pipeline at STA 15+97.61, as directed by DSRSD. This extra work is to be paid for on a force account basis, as shown on approved Extra Work Report. $4,539.24 $10,442.46 $1,407.96 $4,492.44 ESTIMATED COST INCREASE: $20,882.10 BY REASON OF THIS CHANGE ORDER, THE TIME OF COMPLETION WILL BE ADJUSTED 6 WORKIN,/G~AYS. /,: St~ee ~/ Date ~hodora Bia~t~/ / Sate ~ . ~m~ ~ Date Associate CiviFEngineer A~ociate En~n~ Public ~irector We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and .perform all services necessary for the work above specified, and will accept as full payment therefor the prices shown above. Accepted: Date ~'~/~,/~/~..-~ Contractor: Signed By: " If the Contractor does not sign acceptance of this order, his/her attentior, specifications as to proceeding with the ordered work and filing a written protest CITY OF DUBLIN 100 CIVIC PLAZA, DUBLIN, CALIFORNIA 94568 · (925) 833-6630 CONTRACT CHANGE ORDER NO. 8 (925) 829-9248 FAX DATE: PROJ ECT/ROAD: CONTRACT NO: TO: September 12, 2001 Dublin Boulevard Widening - Dougherty Road to Scarlett Drive 00-16 MCGUIRE & HESTER, 9009 Railroad Avenue, Oakland, CA 94603 PAGE: 1 of 1 You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract, Please note that this change order is not effective until approved by the Public Works Director. This change order is requested by the City. 1. Furnish all materials, equipment and labor to relocate traffic signal interconnect conduit to south side of Dublin Boulevard, as shown on attached plan and as directed by the Engineer. This extra work is to be paid for as follows: a) Add 400 LF trench for DLC at $8.50/LF. $3,400.00 b) Add 1,188 LF of 3" PVC conduit (with pull-boxes every 200') at $2.75/LF. $3,267.00 Furnish all materials, equipment and labor to upgrade 100 LF of 3" PVC conduit to rigid metal conduit at $7.75/LF and 60 LF of 2" PVC conduit to rigid metal conduit at $5.25/LF. This extra work upgrades conduits within the concrete encasement at culvert crossing. $1,090.00 Furnish ail materials, equipment and labor to complete traffic signal interconnect to Dougherty Road as shown on attached plan and as directed by the Engineer. This extra work is to be paid for as follows: a) Trench 35 LF at 15.75/LF. $551.25 [~) 35 LF of two 3" PVC conduit at $5.50/LF. $192.50 Furnish all materials, equipment and labor to install one 2" PVC conduit, Schedule 40, 44 LF, with #5 box with ground rod and fuse kit as shown on attached plans. This extra work is to be paid for at the agreed lump sum price of $1,278.00. $1,278.00 5. Furnish all materials, equipment and labor-to relocate streetlight box in median near STA 26+20 approximately 8' east, as directed by the Engineer. This extra work is to be paid for at the agreed lump sum price of $1,481.00. $1,481.00 6. Furnish all materials, equipment and labor to install a 4" PVC conduit, Schedule 40, 44 LF, at STA 27+51.35, as shown on attached plans. This extra work is to be paid for at the agreed lump sum price of $3,065.00. $3,065.00 ESTIMATED COST INCREASE: $14,324.75 BY REASON OF THIS CHANGE ORDER, THE TIME OF COMPLETION WILL BE ADJUSTED 2 WOR//KING DAYS. SU ITTED BY: APPROVAL/RE'CO~MENDED BY: / ~C)VED B~: 'Fe~rd Del Rosark~/ ' a e ~ S.~o~mp.s~n ~ Date S Date D Associate .L;ivil Eng' eer Senior Civil Engineer Public'~C6r~s Director We, tl'ie undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is aPproved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefor the prices shoWn above. Date ~'~b/~/~ .n Contractor: Accepted: ~ ~ ~ , Signed By: ~~~/ --' Title: ~~~ ~/~~ If the Contractor does not sign acceptance of this order, his/her attention specifications as to proceeding with the ordered work and filing a wriEen protest DATE: September 17, 2001 CHANGE ORDER SUMMARY PROJECT NAME: CIP #: Dublin Boulevard Widening - Dougherty Road to Scarlett Drive 96890 CONTRACT NO: 00-16 CONTRACTOR: McGuire & Hester PERCENT COMPLETED: 80% CONTRACT AMOUNT: APPROVED BUDGET AMT: $1,493,338.50 $1,671,820.00 (Revised) CHANGER ORDERS: CHANGE ORDER #1 CHANGE ORDER #2 C~HANGE ORDER #3 CHANGE ORDER #4 CHANGE ORDER #5 CHANGE ORDER #6 CHANGE ORDER #7 CHANGE ORDER #8 TOTAL OF CHANGE ORDERS: $3,000.00 $2,063.50 $5,750.00 $29,193.'00 $14,781.00 $3,9O0.0O $20,882.10 $14,324.75 $93,894.35 CURRENT CHANGE ORDER DESCRIPTION: Modifications to the DSRSD recycled water pipeline and traffic signal system. Install additional conduits across Dublin Boulevard for future extension of median island. ADJUSTED CONTRACT AMOUNT: PROGRESS PAYMENTS MADE: PAYMENT #1 PAYMENT #2 PAYMENT #3 PAYMENT #4 PAYMENT #5 PAYMENT #6 PAYMENT #7 PAYMENT #8 PAYMENT #9 PAYMENT #10 TOTAL PROGRESS PAYMENTS: REMAINING BALANCE ON CONTRACT: $1,587,232.85 $60,853.00 $74,371.00 $121,070.53 $332,893.00 $157,178.00 $746,365.53 $840,867.32 RECOMMENDATION: SIGNATURES: APPROVED DENIEO PU blic-'l/VoYkCDir~cto r APPROVED DENIED City Manager APPROVED DENIED Mayor