HomeMy WebLinkAboutPC Reso05-47 Rec CC Storm Water Quality Basin Stg2 PD
RESOLUTION NO. 05 - 47
A RESOLUTION OF THE PLANNING COMMISSION
OF THE CITY OF DUBLIN
RECOMMENDING THAT THE CITY COUNCIL ADOPT AN ORDINANCE APPROVING A
STAGE 2 DEVELOPMENT PLAN FOR A STORM WATER QUALITY CONTROL BASIN ON
AN I I.I96-ACRE SITE WITHIN AREA H OF DUBLIN RANCH LOCATED IN THE EASTERN
DUBLIN SPECIFIC PLAN AREA NORTH OF INTERSTATE HIGHWAY 580 AND SOUTH OF
THE PROPOSED EXTENSION OF DUBLIN BOULE V ARD
P A 05-005
WHEREAS, the Applicant, James Tong (representing Chang Su-O Lin, Hong Yao Lin & Hong
Lien Lin), submitted an application for a Stage 2 Development Plan for a I 1. I 93-acre site located within
Area H of Dublin Ranch in the Eastern Dublin Specific Plan Area. The Project Site is known as the
Storm Water Quality Control Basin (WQCB) (or detention basin). The application also includes a Site
Development Review in accordance with the proposed Stage 2 Development Plan; and
WHEREAS, the Project Site generally is located north oflnterstate Highway 580 (1-580), south
of the proposed extension of Dublin Boulevard and between the proposed extensions of Brannigan and
Keegan Streets in an area designated as Tassajara Gateway of the Eastern Dublin Specific Plan area; and
WHEREAS, in 2000 an Initial Study was prepared for P A 98-070, the Stage I Planned
Development approval for Area H (SCH #99-1120412), and a determination was made that the project is
within the scope of the Eastern Dublin Specific Plan and General Plan Amendment, for which a Program
EIR was certified (SCH #91-103064) in 1993 including revisions to Part I of the Responses to Comments
relating to the Kit Fox, the Addendum to the DEIR dated May 4, 1993, and a DKS Associates Traffic
Study dated December 15, 1992 ("Eastern Dublin EIR"). The City also adopted a mitigation-monitoring
program, which included numerous measures intended to reduce impacts from the development of the
Eastern Dublin area. The timing for implementation of these mitigation measures is summarized in the
adopted Mitigation and Monitoring Program matrix; and
WHEREAS, the Initial Study prepared for P A 98-070, the Program EIR along with all subsequent
Supplements, and the adopted Mitigation and Monitoring Program adequately address anticipated
environmental impacts resulting from the proposed project for the purpose of compliance with CEQA;
and
WHEREAS, a staff report, dated August 9, 2005 and incorporated herein by reference, describes
and analyzes the Project; and
WHEREAS, the Planning Commission reviewed the staff report and previously prepared
environmental documentation at a duly noticed public hearing held on August 9, 2005, at which time all
interested parties had the opportunity to be heard.
NOW, THEREFORE, BE IT RESOLVED that the foregoing recitals are true and correct and
made a part ofthis resolution.
A. The Planning Commission of the City of Dublin finds that the proposed Stage 2
Development Plan:
is consistent with the: a) General Plan and Eastern Dublin Specific Plan, b) the zoning
district of Planned Development Campus Office ad General Commercial, and c) purpose
and intent of the Stage I Development Plan for Area H of Dublin Ranch PA 00-070.
will be harmonious and compatible with existing and future development in the
surrounding area.
will occur within the Dublin City limits on a site that is planned to be surrounded by urban
uses;
will not displace habitat for endangered, rare, or threatened species;
will not result in any significant negative effects relating to traffic, noise, air quality, or
water quality; and;
is an improvement that will satisfy the requirements of the Regional Water Quality Control
Board to implement a storm water management plan.
BE IT FURTHER RESOLVED that the Planning Commission of the City of Dublin
recommends that the City Council approve the ordinance attached as Exhibit A and incorporated herein
by reference, which adopts a Stage 2 Development Plan, based on the above-referenced findings.
PASSED, APPROVED, AND ADOPTED this 9th day of August, 2005 by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
H/~-,
Planning Commission Chair
ATTEST:
/~
\ '"
Planning anager
G:\PA#\2005\05-005 Water Quality Pond Area H\PC Reso CC recommendation.DOC
2